Engineering Projects Links
Pavement Management Program (PMP)

2023 PMP Street Improvement Project
Mission Lane Street Width Survey Results
Option A (32’ width): 10
Option B (28’ width): 0
No response: 9
The City of Bloomington maintains around 342 miles of city streets. This includes snow removal, crack sealing, street patching, sweeping as well as structural maintenance.
Three construction techniques are used as part of the PMP program:
- Sealcoat involves spraying a bituminous adhesive on the existing surface. The surface is then topped with small, graded aggregate rock. Excess aggregate is swept off and recycled. This helps protect pavement from oxidation and the effects of moisture. Street segments are typically crack sealed the year prior to sealcoating.
- Mill and Overlay involves grinding off the top layer of surface and installing a new top layer of pavement. This extends the life cycle of the original pavement. In addition, street segments are typically crack sealed within a year or two of completing a mill and overlay to extend the life of the pavement.
- Reconstruction removes and replaces existing asphalt pavement and aggregate base. Curbs and gutters are installed if necessary.
Resources
- 2022 PMP Informational Meeting Video
-
2023 PMP Informational Meeting Presentation.pdf - PMP Brochure
- PMP Residential Street Policies
Street Restoration Map
Click upper-left arrows to view legend
STREET NAME |
START |
END |
Little Road |
Morris Avenue |
Poplar Bridge Road |
W 94th Street |
France Avenue |
W Terminus |
W 95th Street |
Normandale Boulevard |
Toledo Avenue |
Toledo Avenue |
Poplar Bridge Road |
W 95th Street |
Stanley Avenue |
West 95th Street |
Toledo Avenue |
W 104th Street |
Zion Avenue |
Wildwood Road |
Wildwood Road |
Wildwood Circle |
W 104th Street |
Zion Avenue |
W 104th Street |
Yosemite Road |
Yosemite Road |
Nesbitt Avenue |
W Old Shakopee Road |
Xavier Avenue |
Vessey Road @ 105th Street |
Yosemite Road |
Vessey Road |
Zion Avenue |
Xavier Avenue @ 107th Street |
Eliason Drive |
Vessey Road |
Xavier Avenue |
W 106th Street |
Vessey Road |
Normandale Boulevard |
York Avenue |
W 106th Street |
South Terminus |
W 106th Street |
York Avenue |
Xerxes Avenue |
Maple Circle |
Maple Avenue |
West Terminus |
Queen Circle |
Ivy Lane |
South Terminus |
Mission Lane |
Nicollet Avenue |
East Terminus |
Clinton Avenue |
E 102nd Street |
E 104th Street |
Bloomington Avenue |
E 82nd Street |
North Terminus |
STREET NAME |
START |
END |
Pioneer Trail |
Highway 169 |
Bloomington Ferry Road |
Bloomington Ferry Road |
Old Shakopee Rd |
W 106th Street |
Landau Circle |
Bloomington Ferry Road |
West Terminus |
Yukon Avenue |
W Old Shakopee Road |
W 110th Street |
W 109th Street Circle |
W 109th Street |
North Terminus |
W 109th Street |
Decatur Ave |
Yukon Avenue |
Decatur Avenue |
W 110th Street |
W 109th Street |
Cavell Circle |
W 110th Street |
South Terminus |
Boone Circle |
W 110th street |
South Terminus |
W 110th Street Circle |
W 110th Street |
North Terminus |
Yukon Circle |
W 110th Street |
South Terminus |
Xylon Avenue |
W 110th Street |
South Terminus |
W 110th Street |
Decatur Avenue |
Bloomington Ferry Road |
Bloomington Ferry Road |
Auto Club Road |
West Terminus |
Toledo Circle (1) |
W 102nd Street |
South Terminus |
Toledo Circle (2) |
Toledo Circle @ W 102 ½ Street |
East Terminus |
Chowen Avenue |
W 109th Street |
W 110th Street |
Portland Avenue |
E Old Shakopee Road |
E 99th Street |
10th Avenue |
E 90th Street |
E 92nd Street |
Crest Road |
12th Avenue |
14th Avenue |
Bloomington Avenue |
E American Boulevard |
E 80th Street |
E 80th Street |
13th Avenue |
Bloomington Avenue |
14th Avenue |
E 82nd Street |
E 86th Street |
15th Avenue |
E 82nd Street |
E 84th Street |
Bloomington Avenue |
E 82nd Street |
E 86th Street |
16th Avenue |
E 82nd Street |
E 86th Street |
17th Avenue |
E 82nd Street |
E 84th Street |
18th Avenue |
E 82nd Street |
E 84th Street |
E 83rd Street |
14th Avenue |
18th Avenue |
E 86th Street |
17th Avenue |
East Terminus |
Old Cedar Avenue |
E 86th Street |
E Old Shakopee Road |
E 88th Street |
E Old Shakopee Road |
West Terminus |
19th Avenue |
E 87th Street |
E 88th Street |
20th Avenue |
E 87th Street |
E 88th Street |
21st Avenue |
E 87th Street |
E 88th Street |
E 86 ½ Street |
Longfellow Avenue |
22nd Avenue |
Longfellow Avenue |
E 86 ½ Street |
E 87th Street |
22nd Avenue |
E 86th Street |
E 87th Street |
2022 Street Reconstruct Candidates | ||
---|---|---|
Road Name | From | To |
W 103rd Street |
Drew Avenue |
Abbott Avenue |
Canterbury Drive |
Abbott Avenue |
Xerxes Avenue |
Queen Avenue |
W Old Shakopee Road |
W 102nd Street |
Pillsbury Avenue |
W Old Shakopee Road |
South Terminus |
E 88th Street |
Nicollet Avenue |
Portland Avenue |
3rd Avenue |
E 90th Street |
E 88th Street |
3rd Avenue |
E 81st Street |
E 79 ½ Street |
10th Avenue |
E 94th Street |
E 92nd Street |
11th Avenue |
E 94th Street |
E 88th Street |
22nd Avenue |
E 86th Street |
North Terminus |
American Boulevard |
28th Avenue |
34th Avenue |
2022 Street Overlay Candidates | ||
---|---|---|
Road Name | From | To |
Veness Road |
Bloomington Ferry Road |
W Bush Lake Road |
W 93rd Street |
Veness Road |
Yukon Avenue |
W 93rd Street Circle |
W 93rd Street |
South Terminus |
Yukon Avenue |
Veness Road |
South Terminus |
Ensign Avenue |
Bloomington Ferry Road |
W 98th Street |
Woodbridge Drive |
Ensign Avenue |
Woodbridge Road |
Woodbridge Road |
North Terminus |
South Terminus |
Ensign Circle |
Ensign Avenue |
East Terminus |
W 97th Street |
Ensign Avenue |
Cavell Avenue |
W 97 ½ Street |
Ensign Avenue |
Cavell Avenue |
Cavell Avenue |
W 97th Street |
W 97 ½ Street |
W 97th Street Circle |
W 97th Street |
South Terminus |
Cavell Circle |
Cavell Avenue |
West Terminus |
W 98th Street |
Ensign Avenue |
Bloomington Ferry Road |
Zion Road |
Auto Club Road |
River Bluff Drive |
Zion Circle |
Zion Road |
East Terminus |
River Bluff Drive |
Zion Road |
Normandale Boulevard |
River Bluff Curve |
River Bluff Drive |
River Bluff Drive |
River Bluff Circle (1) |
River Bluff Drive |
Southeast Terminus |
River Bluff Circle (2) |
River Bluff Drive |
West Terminus |
Johnson Circle |
W Old Shakopee Road |
North Terminus |
Xerxes Avenue |
W 102nd Street |
W 98th Street |
Washburn Circle |
W 102nd Street |
South Terminus |
Xerxes Avenue |
W 90th Street |
W 84th Street |
Xerxes Circle (1) |
Xerxes Avenue |
North Terminus |
Xerxes Circle (2) |
Xerxes Avenue |
Southwest Terminus |
Xerxes Circle (3) |
Xerxes Avenue |
West Terminus |
Knox Avenue |
W 82nd Street |
W 81st Street |
W 89th Street |
Penn Avenue |
Knox Avenue |
Logan Avenue |
Knox Avenue |
W 88th Street |
Penn Glen Place |
Logan Avenue |
East Terminus |
Newton Avenue |
W 90th Street |
W 89th Street |
Morgan Avenue |
W 90th Street |
W 89th Street |
Logan Avenue |
W 90th Street |
W 89th Street |
Knox Avenue |
W 90th Street |
W 89th Street |
James Avenue |
W 89th Street |
W 88th Street |
Irving Avenue |
W 89th Street |
W 88th Street |
W 89th Street |
Knox Avenue |
Humboldt Avenue |
W 91st Street |
Oliver Avenue |
Logan Avenue |
W 91 ½ Street |
Penn Avenue |
Oliver Avenue |
W 92nd Street |
Oliver Avenue |
James Avenue |
Oliver Avenue |
W 92nd Street |
W 91st Street |
Newton Avenue |
W 92nd Street |
W 91st Street |
Morgan Avenue |
W 92nd Street |
W 91st Street |
PMP trails
The PMP trails program addresses the design, construction, and maintenance of the City’s 25 miles of street trails and 13 miles of park trails.
Trail segments selected for rehabilitation are designed to meet modern standards, including minimum trail widths and proper geometry. The construction techniques used include crack sealing, fog sealing, or completing reconstruction.
Trails projects do not occur every year. Annual funding amounts are saved until they meet budgeted project amounts.
The next PMP trails project will include the reconstruction of the asphalt trails within the Dred Scott Park area. Also as part of this project, the Girard Lake Park Parking Lot will be reconstructed to include an asphalt parking lot with concrete curb and gutter. This work is anticipated to occur in Fall 2022.
Project Scope:
The 2022-401 portion of the project includes the reconstruction of the Girard Lake Park Parking Lot at 3701 W 84th Street, the existing gravel parking lot will be replaced with concrete curb and gutter and asphalt pavement. The parking lot will remain closed during the duration of the project.
The 2022-402 portion consists of the reconstruction of all the trail segments connecting the Dred Scott ball fields at 10820 Bloomington Ferry Road. This work will also include ADA upgrades of the pedestrian ramps at the connection of the trails with the parking lots. The project will be capped off with the seal coating and re-stripping of the parking lots adjacent to the playfields. The playfields will remain closed during construction.
Project Funding:
The Project will be funded with a combination of American Rescue Fund (ARP Funds), Park Trail Reconstruction Funds and Park Maintenance Funds. Property assessments are not included as part of the funding for this project.
Project Schedule:
Construction is scheduled to begin in early fall 2022 and is anticipated to be completed late in 2022.
Updates:
October 21, 2022
The contractor is currently working on seeding the disturbed areas and tree planting. This work will conclude the portion of the project scheduled for this year. The Contractor will be back in the spring of 2023 to seal coat and install striping on all the parking lots part of the complex.
October 14, 2022
The contractor finished paving all the trails on October 11. They will be working on restoring pedestrian ramp and installing topsoil on the disturbed areas through the week of October 17. Also, in the week of October 17 they will work on restoring the green spaces and other clean up items.
October 7, 2022
2022-401 Girard Lake Park Parking Lot
The Contractor completed all the restoration work the week of October 3. The parking lot will reopen on October 7.
2022-402 Dred Scott Trails
All the trail removals are completed. The contractor plans on proceeding with the restoration in three phases. Phase one which includes all the trails on the southwest portion of the complex was completed on October 5. Phase two which includes the trails on the northwest part of the complex is scheduled for October 7. Phase three which is composed of the remaining segments is scheduled for the week of October 10
September 30, 2022
2022-401 Girard Lake Park Parking Lot
The Contractor finished paving the final layer of asphalt on Friday September 29. They will be working on restoring all the disturbed green spaces along with striping the new parking lot pavement through the week of October 2.
2022-402 Dred Scott Trails
The Contractor completed concrete removals earlier this week. They are currently working on removing the bituminous trails and upgrading the concrete pedestrian ramps. They will begin paving the base layer of bituminous materials for the trails the week of October 2.
September 23, 2022
2022-401 Girard Lake Park Parking Lot
The Contractor finished the installation of the new curb and gutter the week of September 19, the have also completed all the scheduled storm utility work. They are currently working on topsoil restoration. They will begin grading and tolerancing the parking early to week of September 23, with the paving of the base course and final layer of bituminous material scheduled for later that week.
2022-402 Dred Scott Trails
The Contractor will begin removals of concrete curb and gutter the week of September 26.
September 16, 2022
2022-401 Girard Lake Park Parking Lot
The Contractor is working on removing the existing gravel lot through the week of September 12. Once this work is completed they will begin grading the parking lot with the new fill material in preparation for curb installation. The installation of concrete curb and gutter is scheduled for later in the week of September 19. Utility crews will also be present on site during the week of September 19 to work on rehabilitating an existing storm sewer outlet that is adjacent to the westerly border of the parking lot.
September 9, 2022
2022-401 Girard Lake Park Parking Lot
The Contractor will begin work at the gravel parking lot located at 3701 W 84th Street the week of September 12. This project will replace the existing gravel parking lot with concrete curb and gutter and asphalt pavement. The parking lot will be closed beginning late in the week of September 12 and will remain closed for the duration of the project.
Every mile of Bloomington streets are entered into a computerized program designed to maximize the life of City Streets and to minimize costs by applying the most cost effective maintenance technique to the various roadways. The computer program lists the streets that are in need of maintenance. City staff analyzes the recommended streets and proceeds with the streets in a manner that "makes sense" and is within the funding provided. The goal of the program is to "do the right maintenance at the right time."
City staff brings the recommended seal coat and overlay program to the City Council for their information, approval and ordering of the improvements. Streets eligible for reconstruction are handled differently.
City staff provides a number of streets eligible for reconstruction to the City Council. Staff selects streets for reconstruction based on a variety of factors starting with the Pavement Condition Index (PCI) of the pavement. City staff conducts a field survey of a third of the streets in the City every year. The PCI is a numeric reflection of the structural integrity of the pavement including potholes, cracking, rutting, etc.
Several other factors which will be considered in order to determine the best candidates for street reconstruction are, but not limited to, the following.
- Condition/effectiveness of existing surface drainage system.
- Condition of underground water and sewer system.
- Whether a street meets recommended standards for curb and gutter and street width.
- Opportunities to improve water quality of lakes downstream of street.
- Available State and City funding.
- Elimination of hazardous situations and to provide safety improvements.
- County construction projects on adjacent roadways.
- Reconstruction of adjacent City streets.
- Major redevelopment projects within City.
- Neighborhood petitions.
Sealcoat
City's General Fund
Overlay
Infrastructure Replacement Fund
Distributed by the State of Minnesota from fuel sales tax and license tab fees along with General Fund augmentation.
Reconstruction
General Fund and assessments
Single and two-family residences pay 25 percent of their portion of the project through assessments; commercial, industrial or multi-family residences pay 50 percent of the cost through assessments.
The area in front of your home which is occupied by street, public utilities (sanitary sewer, water and storm sewer), private utilities (electric power, telecommunication and gas) and other necessary items such as street signing, snow storage and lights is public right-of-way.
A typical right-of-way width in residential areas in Bloomington is 60 feet. (Not all the right-of-way widths are the same and yours may vary from this width. The project engineer can confirm the width for you.) Since a typical residential street width in Bloomington from 32 feet to 36 feet and is centered in the right-of-way approximately 12 feet to 14 feet of public right-of-way exists on either side of the existing streets.
The actual disturbed area will vary, but a good assumption would be that the 12 feet to 14 feet of public right-of-way will be disturbed. For actual limits please contact the project engineer.
Signs will be posted allowing local traffic only on the streets under construction. Residents who live on these streets will have access to the street throughout construction.
The overlay project is anticipated to start in May with the reconstruction project following shortly thereafter in late May-early June. Both projects are anticipated to be substantially complete and open to all traffic in the fall.
The City Council has approved a number of policies in conjunction with the Pavement Management Policy. One policy is: All new street construction and street reconstruction in Bloomington will include concrete curb and gutter. This is for a number of reasons:
- Provide a stable maintenance edge for plowing and sweeping operations.
- Reduce plow damage to yards and mailboxes.
- Protect the edge of the bituminous surface from deteriorating.
- Channel storm water runoff away from street.
- Reduce erosion from boulevards/lawns.
- Define roadway limits.
Council also has approved street width with the standard residential street width being 32' face of curb to face of curb. The policy allows deviation from the standard considering factors such as traffic volumes, emergency vehicle access, drainage and special situations. Other policies include that streets without curb and gutter are not eligible for overlay. The City Council and Staff schedule neighborhood meetings with the impacted properties to begin discussion about construction issues, identify additional concerns and propose possible solutions.
After the Public Hearing and discussion, the City Council approves streets for reconstruction and orders the improvement.