Pavement Management Program (PMP) Updates
Engineering Links

2025-101 PMP Street Improvement Project
Towne Terrace (James Avenue to Humboldt Avenue)
The contractor will finish paving the first layer of asphalt the week of July 14. This work will be followed by soft surface restoration around the yards. The paving of the final layer of asphalt will follow later in the week of July 21
W 105th Street (Thomas Avenue to Sheridan Avenue)
The contractor will finish paving the first layer of asphalt the week of July 14. This work will be followed by soft surface restoration around the yards. The paving of the final layer of asphalt will follow later in the week of July 21.
Fremont Avenue
The contractor completed removals earlier the week of July 14. The utility subcontractor has begun installing the various pits required for pipe jacking operations. The utility portion of this work is scheduled for 9 to 10 weeks, during this time Freemont Avenue will only be open to local traffic.
10th Avenue and 99th Street
Levelling and grading work is ongoing and will run through the week of July 14. Concrete curb and gutter installation along with paving of the first layer of asphalt are scheduled for the week of July 28
12th Avenue
Utility work is ongoing and will continue through the week. Levelling and grading work will follow in the week July 22. Concrete curb and gutter installation along with paving of the first layer of asphalt are scheduled for the week of July 28
E 90th Street
Levelling and grading work is scheduled for the week July 21. Concrete curb and gutter installation along with paving of the first layer of asphalt are scheduled for the week of July 28.
Elliott Avenue
The contractor will begin removals on this segment around mid-week the week of July 21.
2025-102 PMP Street Maintenance Project
Hyland Area (Hyland Creek Road, Nesbitt Road, Hyland Creek Circle, Norman Ridge Circle)
Asphalt paving is scheduled for Friday, July 18th.
Nine Mile Creek Parkway (W. 90th Street to Stanley Avenue)
The contractor will be in the week of July 21st to begin site restoration including topsoil and sod. Asphalt milling is scheduled for Friday, July 25th.
Vincent Area (Vincent Place, Vincent Circle)
The contractor will be in the week of July 21st to begin removals and utility work.
Terracewood Area (Terracewood Drive, Morris Circle, Morris Lane, Rich Circle, W 114th Street, Rich Road)
The contractor mobilize into the site the week of July 21st. They will be installing inlet protection and begin utility work.
2025-101 PMP Street Improvement Project
Towne Terrace (James Avenue to Humboldt Avenue)
The contractor completed the installation of curb and gutter this week. They plan on paving the first layer of asphalt the week of July 14.
W 105th Street (Thomas Avenue to Sheridan Avenue)
The contractor will be paving the first layer of asphalt the week of July 14.
Fremont Avenue
The contractor is working on removals of the areas necessary to allow the utility crews to begin installation of the new sanitary sewer the week of July 7. The utility subcontractor will move in the week of July 14 to begin excavation of the jacking pits required for the trenchless installation of the new sanitary sewer line. The utility portion of this work is scheduled for 9 to 10 weeks, during this time Freemont Avenue will only be open to local traffic.
10th Avenue and 99th Street
The contractor finished removals of the asphalt surface earlier in the week of July 7. Utility work is ongoing and will continue through the week. Levelling and grading work will follow in the week July 14.
12th Avenue
The contractor finished removals of the asphalt surface the week of July 7. Utility work is ongoing and will continue through the week. Levelling and grading work will follow in the week July 22.
E 90th Street
The contractor finished removals of the asphalt surface earlier the week of July 7. Utility work is completed. Levelling and grading work will follow in the week July 14.
2025-102 PMP Street Maintenance Project
Hyland Area (Hyland Creek Road, Nesbitt Road, Hyland Creek Circle, Norman Ridge Circle)
The contractor be in early the week of July 14th to continue sod installation. Asphalt milling is scheduled for July 16th and asphalt paving is scheduled for Friday, July 18th. Work is weather dependent and subject to change.
Nine Mile Creek Parkway (W. 90th Street to Stanley Avenue)
The contractor will be in the week of July 14th raising maintenance hole and gate valve covers in preparation for asphalt milling & paving.
Vincent Area (Vincent Place, Vincent Circle)
The contractor will be in the week of July 14th to begin removals.
2025-101 PMP Street Improvement Project
Towne Terrace (James Ave to Humboldt Ave)
The contractor will be working on finishing the installation of the storm sewer. This will be followed by curb and gutter installation the week of July 7.
W 105th Street (Thomas Ave to Sheridan Ave)
The contractor will be installing curb and gutter the week of July 7.
Fremont Avenue
The contractor will begin removals of the areas necessary to allow the utility crews to begin installation of the new sanitary sewer the week of July 7. The utility subcontractor will move in the area later in the week to begin excavation of the jacking pits required for the trenchless installation of the new sanitary sewer line.
10th Avenue and 99th St
The contractor will begin removals of the asphalt surface the week of July 7. This will be followed by utility work later in the same week.
12th Avenue
The contractor will begin removals of the asphalt surface the week of July 7. This will be followed by utility work later in the same week.
E 90th St
The contractor will begin removals of the asphalt surface the week of July 7. This will be followed by utility work later in the same week.
2025-101 PMP Street Improvement Project
Towne Terrace (James Ave to Humboldt Ave)
The contractor is currently performing grading and levelling of the street. This work will continue into the week of July 1.
W 105th Street (Thomas Ave to Sheridan Ave)
The contractor will in the week of July 1 to begin grading and levelling of the street.
6701 W 78th St
The contractor is working on patching the area around the newly constructed median. This work will continue into the week of July 1.
2025-102 PMP Street Maintenance Project
Cavell Area (Cavell Avenue, Cavell Circle (1), Cavell Circle (2), Cavell Circle (3), W. 100th Street)
The contractor will be in early the week of June 30th to complete asphalt paving.
Hyland Area (Hyland Creek Road, Nesbitt Road, Hyland Creek Circle, Norman Ridge Circle)
The contractor will be in the week of June 30th to beginning pouring concrete curb & gutter and sidewalk.
Nine Mile Creek Parkway (W. 90th Street to Stanley Avenue)
The contractor will be in the week of June 30th continuing removals and will begin utility work.
I-494 Reconstruction Project
Portions of both I-494 & I-35W will be closed this weekend to facilitate demolition of the existing I-494 westbound bride over I-35W. The closures are summarized below:
- I-494 eastbound closed between Hwy. 100 and I-35W
- I-494 westbound closed between T.H. 77 and Hwy 100
- I-35W (both directions) closed between I-494 and Hwy 62
The closure will start at 10 P.M. Friday, June 27th through 5 A.M. Monday, June 30th.
2025-101 PMP Street Improvement Project
Towne Terrace (James Ave to Humboldt Ave)
The contractor is scheduled to begin pavement and concrete removals the week of June 16. This will be followed by utility work the week of June 23.
W 105th Street (Thomas Ave to Sheridan Ave)
The contractor is scheduled to begin pavement and concrete removals the week of June 16. This will be followed by utility work the week of June 23.
2025-102 PMP Street Maintenance Project
W. 111th Area (W. 111th Street, Sumter Avenue, Rhode Island Avenue, Quebec Circle)
Asphalt paving has been completed in this area. Traffic control will be picked up the week of June 23rd.
Cavell Area (Cavell Avenue, Cavell Circle (1), Cavell Circle (2), Cavell Circle (3), W. 100th Street)
The contractor will be in this week to complete asphalt milling & paving the week of June 23rd.
Hyland Area (Hyland Creek Road, Nesbitt Road, Hyland Creek Circle, Norman Ridge Circle)
The contractor will continue with utility work the week of June 23rd. Concrete curb & gutter and sidewalk replacement will also begin the week of June 23rd.
Nine Mile Creek Parkway (W. 90th Street to Stanley Avenue)
The contractor will be in the week of June 23rd to begin asphalt and concrete removals. Minor repair of utilities will also begin the week of June 23rd.
2025-101 PMP Street Improvement Project
Towne Terrace (James Ave to Humboldt Ave)
The contractor is scheduled to begin pavement and concrete removals the week of June 16. This will be followed by utility work the week of June 23.
W 105th Street (Thomas Ave to Sheridan Ave)
The contractor is scheduled to begin pavement and concrete removals the week of June 16. This will be followed by utility work the week of June 23.
6701 W 78th St
The contractor will be starting median modifications adjacent to the Enclave Development at 6701 W 78th St the week of June 16.
9830 Nicollet Avenue
The contractor will be installing a hydrant adjacent to 9830 Nicollet Avenue the week of June 16.
2025-102 PMP Street Maintenance Project
W. 111th Area (W. 111th Street, Sumter Avenue, Rhode Island Avenue, Quebec Circle)
Asphalt milling is scheduled to be completed on Friday, June 13th and asphalt paving is scheduled for Monday, June 16th.
Cavell Area (Cavell Avenue, Cavell Circle (1), Cavell Circle (2), Cavell Circle (3), W. 100th Street)
The contractor will be in the week of June 16th to asphalt patch and begin site restoration including topsoil and sod.
Hyland Area (Hyland Creek Road, Nesbitt Road, Hyland Creek Circle, Norman Ridge Circle)
The contractor will continue with utility work the week of June 16th.
Bush Lake Road (Old Shakopee Road to Chalet Road)
The contractor will continue utility work and be completed early the week of June 16th.
2025-101 PMP Street Improvement Project
Towne Terrace (James Ave to Humboldt Ave)
The contractor anticipates starting pavement and concrete removals the week of June 16th.
W 105th Street (Thomas Ave to Sheridan Ave)
The contractor anticipates starting pavement and concrete removals the week of June 16th.
2025-102 PMP Street Maintenance Project
W. 111th Area (W. 111th Street, Sumter Avenue, Rhode Island Avenue, Quebec Circle)
The contractor will be in the week of June 9th for site restoration, including topsoil and sod.
Cavell Area (Cavell Avenue, Cavell Circle (1), Cavell Circle (2), Cavell Circle (3), W. 100th Street)
The contractor will be in the week of June 9th to begin pouring curb & gutter and sidewalk.
Hyland Area (Hyland Creek Road, Nesbitt Road, Hyland Creek Circle, Norman Ridge Circle)
The contractor will mobilize in the week of June 9th to install inlet protection. Removals needed for repair of city-owned utilities may begin late the week of June 9th.
Bush Lake Road (Old Shakopee Road to Chalet Road)
The contractor will be mobilizing into Bush Lake Road the week of June 9th to begin repair of City-owned utilities on Bush Lake Road. This work is in preparation for a Hennepin County overlay of Bush Lake Road scheduled for later this summer.
2025-101 PMP Street Improvement Project
A preconstruction conference was held on Monday, May 19th . Work is expected to begin in early June.
2025-102 PMP Street Maintenance Project
W. 111th Area (W. 111th Street, Sumter Avenue, Rhode Island Avenue, Quebec Circle)
The contractor will be in the week of June 2nd to asphalt patch the new curb areas and begin to prep for site restoration, including topsoil and sod.
Cavell Area (Cavell Avenue, Cavell Circle (1), Cavell Circle (2), Cavell Circle (3), W. 100th Street)
The contractor will be in the week of June 2nd to begin repair of City-owned utilities. Removal and select curb & gutter and concrete sidewalk will also occur the week of June 2nd.
I-494 Reconstruction Project
I-494 between Hwy. 100 and T.H. 77 will be closed this weekend to facilitate the demolition of the existing Portland Avenue bridge. The closure will start at 10 P.M. Friday, May 30th through 5 A.M. Monday, June 2nd.
2025-101 PMP Street Improvement Project
A preconstruction conference was held on Monday, May 19th . Work is expected to begin in early June.
2025-102 PMP Street Maintenance Project
W. 111th Area (W. 111th Street, Sumter Avenue, Rhode Island Avenue, Quebec Circle)
The contractor will be in the week of May 26th to begin installing inlet protection, traffic control, and start removal of existing concrete items.
Cavell Area (Cavell Avenue, Cavell Circle (1), Cavell Circle (2), Cavell Circle (3), W. 100th Street)
The contractor will be in the week of May 26th to begin installing inlet protection, traffic control, and start removal of existing concrete items.
2025-101 PMP Street Improvement Project
A preconstruction conference is scheduled for Monday, May 19th . Work is expected to begin in late May/early June.
2025-102 PMP Street Maintenance Project
W. 111th Area (W. 111th Street, Sumter Avenue, Rhode Island Avenue, Quebec Circle)
The contractor will be in the week of May 19th to begin installing inlet protection, traffic control, and start removal of existing concrete items.
Cavell Area (Cavell Avenue, Cavell Circle (1), Cavell Circle (2), Cavell Circle (3), W. 100th Street)
The contractor will be in the week of May 19th to begin installing inlet protection, traffic control, and start removal of existing concrete items.