2025-101 PMP Street Improvement Project
Towne Terrace (James Ave to Humboldt Ave)
The contractor is scheduled to begin pavement and concrete removals the week of June 16. This will be followed by utility work the week of June 23.
W 105th Street (Thomas Ave to Sheridan Ave)
The contractor is scheduled to begin pavement and concrete removals the week of June 16. This will be followed by utility work the week of June 23.
6701 W 78th St
The contractor will be starting median modifications adjacent to the Enclave Development at 6701 W 78th St the week of June 16.
9830 Nicollet Avenue
The contractor will be installing a hydrant adjacent to 9830 Nicollet Avenue the week of June 16.
2025-102 PMP Street Maintenance Project
W. 111th Area (W. 111th Street, Sumter Avenue, Rhode Island Avenue, Quebec Circle)
Asphalt milling is scheduled to be completed on Friday, June 13th and asphalt paving is scheduled for Monday, June 16th.
Cavell Area (Cavell Avenue, Cavell Circle (1), Cavell Circle (2), Cavell Circle (3), W. 100th Street)
The contractor will be in the week of June 16th to asphalt patch and begin site restoration including topsoil and sod.
Hyland Area (Hyland Creek Road, Nesbitt Road, Hyland Creek Circle, Norman Ridge Circle)
The contractor will continue with utility work the week of June 16th.
Bush Lake Road (Old Shakopee Road to Chalet Road)
The contractor will continue utility work and be completed early the week of June 16th.