Skip to main content
2016 PMP Construction

Pavement Management Program (PMP) Updates

November 2018

November 16, 2018

2018-101 PMP Street Improvement Project

83rd Street Area (includes E 83rd St, Columbus Ave, Elliot Ave)
Winter stabilization of the boulevard areas is complete. The boulevards will finish being graded and sodded in the Spring of 2019. Remaining punch list work will also be completed in the Spring.

16th Avenue (from 82nd St to North Terminus)
Winter stabilization of the boulevard areas is anticipated to complete by the end of the week of November 12. The boulevards will finish being graded and sodded in the Spring of 2019. Remaining punch list work will also be completed in the Spring.

Glenview Lane (from E Old Shakopee Rd to Southeast Terminus)
Winter stabilization of the boulevard areas is anticipated to complete by the end of the week of November 12. The boulevards will finish being graded and sodded in the Spring of 2019. Remaining punch list work will also be completed in the Spring.

November 9, 2018

2019-101 PMP Street Improvement Project

Public informational meetings were held on Monday, November 5 at 2 PM and 5:30 PM in the Public Works Training Room. A PDF copy of the informational presentation can be found in the resource section of the City’s PMP webpage or click here. The public hearing is scheduled for Monday, November 19.

2018-101 PMP Street Improvement Project

83rd Street Area (includes E 83rd St, Columbus Ave, Elliot Ave)
Paving of the final layer of asphalt is complete. Boulevard restoration remains, winter stabilization of the boulevard areas may be necessary due to inclement weather. If installation of sod is viable, the contractor will grade the boulevard areas to accommodate the installation. Punchlist items remain.

16th Avenue (from 82nd St to North Terminus)
Paving of the final layer of asphalt is complete. Boulevard restoration remains, winter stabilization of the boulevard areas may be necessary due to inclement weather. If installation of sod is viable, the contractor will grade the boulevard areas to accommodate the installation. Punchlist items remain.

Glenview Lane (from E Old Shakopee Rd to Southeast Terminus)
Paving of the final layer of asphalt is complete. Boulevard restoration remains, winter stabilization of the boulevard areas may be necessary due to inclement weather. If installation of sod is viable, the contractor will grade the boulevard areas to accommodate the installation. Punchlist items remain.

2018-102 PMP Street Maintenance Project

20th Avenue at Killebrew Drive
Traffic signal revision work at the intersection was completed November 7. Additional testing remains.

12th Avenue Area (12th Ave from E 86th St to American Blvd, E 82nd St from 12th Ave to West Terminus)
Traffic signal revision work at the intersection of 12th Ave and American Blvd has been scheduled for November 14.

November 2, 2018

2019-101 PMP Street Improvement Project

Public informational meetings are scheduled for Monday, November 5th at 2:00 PM and 5:30 PM in the Public Works Training Room. The public hearing is scheduled for Monday, November 19.

2018-101 PMP Street Improvement Project 


Park Avenue Area (includes Park Avenue, East 87 ½ Street, Oakland Avenue)
Paving of the final layer of asphalt is complete.  Sod installation is complete and seed installation is anticipated to complete the week of November 5.  

83rd Street Area (includes East 83rd Street, Columbus Avenue, Elliot Avenue)
Paving of the final layer of asphalt on the west portion of the area, which includes 83rd Street and Columbus Avenue is complete and sod installation is anticipated to complete by early in the week of November 5.  The Contractor will complete raising manholes and gate valves in the east portion of the area, which includes 83rd Street and Elliot Avenue the week of October 29.  Paving of asphalt driveways, sod installation and paving of the final layer of asphalt is scheduled for the week of November 5.

16th Avenue (from 82nd Street to North Terminus) 
Paving of the first layer of asphalt is complete.  Raising of manholes and gate valves, sod installation and paving of the final layer of asphalt is scheduled for the week of November 5. 

Glenview Lane (from East Old Shakopee Road to Southeast Terminus)
Paving of the first layer of asphalt is complete.  Raising of manholes and gate valves, sod installation and paving of the final layer of asphalt is scheduled for the week of November 5. 
 

2018-102 PMP Street Maintenance Project

20th Avenue at Killebrew Drive
Traffic signal revision work at the intersection has been rescheduled for Wednesday, November 7th to accommodate additional testing of signal equipment.  Appropriate traffic control will be used to direct traffic.

12th Avenue Area (12th Avenue from E. 86th Street to American Boulevard, E. 82nd Street from 12th Avenue to West Terminus)
Traffic signal revision work at the intersection of 12th Avenue and American Boulevard has been postponed pending additional programming and testing.  Additional pavement marking has been scheduled for E. 82nd Street between Smith Park and 12th Avenue.
 

October 2018

October 26, 2018

2018-101 PMP Street improvement Project

4th Avenue (from 84th Street to 86th Street)

Raising of manholes and gate valves, paving of asphalt driveways and boulevard restoration is anticipated to complete late in the week of October 22, weather permitting.  Paving of the final layer of asphalt is anticipated to complete the week of October 29.

 

Park Avenue Area (includes Park Avenue, East 87 ½ Street, Oakland Avenue)

Paving of the first layer of asphalt was slightly delayed and is scheduled for late in the week of October 22, weather permitting.  Boulevard restoration has started and will continue the week of October 29 along with raising of manholes and gate valves and paving of asphalt driveways. 

83rd Street Area (includes East 83rd Street, Columbus Avenue, Elliot Avenue)

Concrete work in the eastern portion of this area that includes 83rd Street and Elliot Avenue is anticipated to start late in the week of October 22 and complete the week of October 29.  This will be followed by final grading of the class 5 gravel and paving of the first layer of asphalt late in the week of October 29.  Paving of the first layer of asphalt in the western portion of this area, which includes 83rd Street and Columbus Avenue is scheduled for late in the week of October 22, weather permitting.  This will be followed by raising of manholes and gate valves, paving asphalt driveways and boulevard restoration the week of October 29.

16th Avenue (from 82nd Street to North Terminus)

Concrete work is anticipated to start late in the week of October 22 and complete early in the week of October 29.  This will be followed by final grading of the class 5 gravel and paving of the first layer of asphalt later in the week of October 29.

Glenview Lane (from East Old Shakopee Road to Southeast Terminus)

Concrete work is anticipated to start late in the week of October 22 and complete early in the week of October 29.  This will be followed by final grading of the class 5 gravel and paving of the first layer of asphalt later in the week of October 29

2018-102 PMP Street Maintenance Project

20th Avenue at Killebrew Drive

Traffic signal revision work at the intersection has been rescheduled for Wednesday, October 31st  and will require a shutdown of the signal. Appropriate traffic control will be used to direct traffic.

12th Avenue Area (12th Avenue from E. 86th Street to American Boulevard, E. 82nd Street from 12th Avenue to West Terminus)

Paving of the new asphalt surface was completed late the week of October 15th and was followed by installation of pavement marking early the week of October 22nd.  Traffic signal revision work at the intersection of 12th Avenue and American Boulevard has been scheduled for Wednesday, November 7th and will require a shutdown of the signal.  Appropriate traffic control will be used to direct traffic.

American Boulevard Area (E. American Boulevard from 24th Street to 28th Avenue)

Paving of the new asphalt surface was completed early the week of October 22nd and was followed by installation of pavement marking later in the week.  Work is substantially complete in the area with punch list items remaining.

October 19, 2018

2018-101 PMP Street Improvement Project

4th Avenue (from 84th Street to 86th Street)   
Paving of the first layer of asphalt is scheduled for late in the week of October 15. Raising of manholes and gate valves, paving of asphalt driveways and boulevard restoration will follow paving the week of October 22. Paving of the final layer of asphalt is anticipated to occur late in the week of October 22, weather permitting.
 
Park Avenue Area (includes Park Avenue, East 87 ½ Street, Oakland Avenue)
Paving of the first layer of asphalt is scheduled for late in the week of October 15.  The remaining concrete work is anticipated to complete by early in the week of October 22.  Raising of manholes and gate valves, paving of asphalt driveways and boulevard restoration will follow paving the week of October 22. Paving of the final layer of asphalt is anticipated to occur late in the week of October 22, weather permitting.
 
83rd Street Area (includes East 83rd Street, Columbus Avenue, Elliot Avenue)
Storm sewer work along with common excavation and placement of class 5 is complete. Concrete work has started and is anticipated to complete mid-week of October 22. This will be followed by final grading of the class 5 gravel and paving of the first layer of asphalt the week of October 29.
 
16th Avenue (from 82nd Street to North Terminus)
Storm sewer work is complete.  Common excavation and placement of class 5 gravel is anticipated to complete late in the week of October 15 with concrete work scheduled for mid-week of October 22. This will be followed by final grading of the class 5 gravel and paving of the first layer of asphalt the week of October 29.
 
Glenview Lane (from East Old Shakopee Road to Southeast Terminus)
Storm sewer work is complete. Common excavation and placement of class 5 gravel is anticipated to complete late in the week of October 15 with concrete work scheduled for mid-week of October 22. This will be followed by final grading of the class 5 gravel and paving of the first layer of asphalt the week of October 29.

2018-102 PMP Street Improvement Project

20th Avenue at Killebrew Drive
Traffic signal revision work at the intersection has been rescheduled for Wednesday, October 24th  and will require a shutdown of the signal.  Appropriate traffic control will be used to direct traffic.
 
12th Avenue Area (12th Avenue from E. 86th Street to American Boulevard, E. 82nd Street from 12th Avenue to West Terminus)
Milling of the existing pavement was completed the week of October 15 and was followed by paving of the new asphalt surface late in the week. Additional boulevard restoration will follow early the week of October 22.  Installation of pavement marking is expected late the week of October 22nd and is to be striped as a three lane configuration. 
 
American Boulevard Area (E. American Boulevard from 24th Street to 28th Avenue)
Milling of the existing asphalt was completed late the week of October 15th and will be followed by paving of the new asphalt surface early the week of October 22. Installation of pavement marking is expected late the week of October 22.

2019-101 PMP Street Improvement Project

Notices regarding the 2019 PMP Street Improvement Project have been mailed to all affected properties. Public informational meetings are scheduled for Monday, November 5 at 2 p.m. and 5:30 p.m. in the Public Works Training Room. The public hearing is scheduled for the Monday, November 19.

October 12, 2018

2018-101 PMP Street Improvement Project

4th Avenue (from 84th Street to 86th Street)

Concrete installation was delayed due to weather, but is now complete.  Fine grading of class 5 gravel is scheduled for the week of October 15, with paving of the first layer of asphalt to follow later in the week, weather permitting.  Raising of manholes and gate valves, paving of asphalt driveways and boulevard restoration will follow paving the week of October 22.

Park Avenue Area (includes Park Avenue, East 87 ½ Street, Oakland Avenue)

Storm sewer and water main work is complete.  The intersection of 86th Street and Park Avenue is scheduled to reopen to traffic by the early evening on Friday, October 12.  Concrete work is scheduled to complete the week of October 15.  Fine grading of class 5 gravel is anticipated to occur later in the week of October 15, in preparation for paving of the first layer of asphalt.  Raising of manholes and gate valves, paving of asphalt driveways and boulevard restoration will follow paving the week of October 22.

83rd Street Area (includes East 83rd Street, Columbus Avenue, Elliot Avenue)

Storm sewer work has started and is scheduled to complete early in the week of October 15.  Common excavation and placement of class 5 gravel is scheduled for the week of October 15 with concrete work to start later in the week, weather permitting.

16th Avenue (from 82 Street to North Terminus)

Pavement removal is scheduled for Monday, October 15.  Storm sewer work will follow later in the week.  Common excavation and placement of class 5 gravel will begin late in the week of October 15 or the week of October 22.

Glenview Lane (from East Old Shakopee Road to Southeast Terminus)

Pavement removal is scheduled for Monday, October 15.  Storm sewer work will follow later in the week.  Common excavation and placement of class 5 gravel will begin late in the week of October 15 or the week of October 22.

2018-102 PMP Street Maintenance Project

20th Avenue at Killebrew Drive

Traffic signal revision work at the intersection has been rescheduled for Wednesday, October 24th  and will require a shutdown of the signal.  Appropriate traffic control will be used to direct traffic.

 12th Avenue Area (12th Avenue from E. 86th Street to American Boulevard, E. 82nd Street from 12th Avenue to West Terminus)

Completion of concrete work is expected by weeks end and will be followed by boulevard restoration.  Milling of the existing pavement has been scheduled for Thursday, October 18th and Friday October 19th.  Paving of the new asphalt surface is scheduled for Friday, October 19th and Saturday, October 20th.

American Boulevard Area

Concrete work is scheduled to be complete late the week of October 8th and will be followed by milling of the existing pavement on Friday, October 19th.  Milling will be followed by paving of the new asphalt surface on Saturday, October 20th.

October 5, 2018

2018-101 PMP Street Improvement Project

James Avenue Area (includes James Avenue, Knox Avenue, West 91st Street)
Paving of the final layer of asphalt is complete.  Punch list work remains. 

West 86th Street (from Xerxes Avenue to Penn Avenue)
Paving of the final layer of asphalt is complete.  Punch list work remains. 

4th Avenue (from 84th Street to 86th Street)   
Common excavation and placement of class 5 gravel is complete.  Concrete installation is anticipated to start late in the week of October 1, weather permitting, and continue the week of October 8.  Fine grading of class 5 gravel will follow later in the week of October 8.  The first layer of asphalt is anticipated to be paved the week of October 15.

Park Avenue Area (includes Park Avenue, East 87 ½ Street, Oakland Avenue)
Storm sewer and water main work is scheduled to complete early in the week of October 8.  The remaining water main work will require 1 more water main shutdown on Park Avenue and is scheduled for Monday, October 8, weather permitting.  Affected property owners will be notified 48 hours in advance of the water shutdown.  The connection of storm sewer into 86th Street from Park Avenue will require a closure of 86th Street for approximately 2-3 days and is scheduled to start on Monday, October 8.  A detour will be provided.  Grading and placement of class 5 gravel is also scheduled to start late in the week of October 1 and continue the week of October 8.  Concrete work is anticipated to begin late in the week of October 8.

83rd Street Area (includes East 83rd Street, Columbus Avenue, Elliot Avenue)
Pavement removal is complete and storm sewer work is scheduled for the week of October 8.

16th Avenue (from 82nd Street to North Terminus)
Pavement removal is scheduled for the week of October 15.

Glenview Lane (from East Old Shakopee Road to Southeast Terminus)
Pavement removal is scheduled for the week of October 15.

2018-102 PMP Street Maintenance Project

20th Avenue at Killebrew Drive
Traffic signal revision work at the intersection has been scheduled for Wednesday, October 17 and will require a shutdown of the signal.  Appropriate traffic control will be used to direct traffic.

12th Avenue Area (12th Avenue from E. 86th Street to American Boulevard, E. 82nd Street from 12th Avenue to West Terminus)
Concrete work in the area continues and is expected to be completed early the week of October 8.  Boulevard restoration has begun in the area and will continue into the week of October 8, and is expected to be followed by milling of the existing pavement.

American Boulevard Area (E. American Boulevard from 24th Street to 28th Avenue)
Removal of concrete items will continue into the week of October 8, and be followed by replacement of concrete items.  Adjustment of utility structures is scheduled to begin early the week of October 8.  Milling of the existing pavement is scheduled to follow later in the week.

[accordion]

September 2018

September 28, 2018

2018-101 PMP Street Improvement Project

An assessment informational meeting was held on Monday, September 24 at 5:30 p.m. in the Bloomington Public Works Training Room.  The public hearing is scheduled for Monday, October 1. 

Girard Avenue (from West 102nd Street to West 100th Street)
Paving of the final layer of asphalt is complete.  Punch list work remains. 

James Avenue Area (includes James Avenue, Knox Avenue, West 91st Street)
Sod and seed installation and raising on manholes and gate valves have started and will complete early in the week of October 1 and be followed by paving of the final layer of asphalt. 

West 86th Street (from Xerxes Avenue to Penn Avenue)
Paving of the first layer of asphalt is complete.  Raising of manholes and gate valves along with sod installation is scheduled to complete early in the week of October 1.  Paving of the final layer of asphalt is also scheduled for the week of October 1.

4th Avenue (from 84th Street to 86th Street)   
Storm sewer work is complete.  Common excavation and placement of class 5 gravel has started and is anticipated to complete early in the week of October 1.  Concrete installation is scheduled for mid-late in the week of October 1, weather permitting.

Park Avenue Area (includes Park Avenue, East 87 ½ Street, Oakland Avenue)
Storm sewer and water main work is scheduled for the week of October 1 and will complete the week of October 8.  The water main work will require two separate 1-day water main shutdowns on Oakland Avenue and Park Avenue to allow for gate valves and hydrants to be installed.  Affected property owners will be notified 48 hours in advance of the water shutdowns.  The connection of storm sewer into 86th Street from Park Avenue will require a closure of 86th Street for approximately 3 days and is anticipated to begin on Monday, October 8.  A detour will be provided.

83rd Street Area (includes East 83rd Street, Columbus Avenue, Elliot Avenue)
Pavement removal has been slightly delayed in this area and is anticipated to occur the week of October 1.

16th Avenue (from 82nd Street to North Terminus)
Pavement removal is anticipated to occur either the week of October 8 or 15.

Glenview Lane (from East Old Shakopee Road to Southeast Terminus)
Pavement removal is anticipated to occur either the week of October 8 or 15.

2018-102 PMP Street Maintenance Project

24th Avenue at Killebrew Drive
Traffic signal revision work at the intersection has been scheduled for Wednesday, October 3 and will require a shutdown of the signal.  Appropriate traffic control and personnel will be onsite to direct traffic.

34th Avenue at Appletree
Traffic signal revision work at the intersection was completed Wednesday, September 26 and included installation and programming of a new controller cabinet.  A new pedestrian signal pole was installed as well.

12th Avenue Area (12th Avenue from E. 86th Street to American Boulevard, E. 82nd Street from 12th Avenue to West Terminus)
Adjustment of utility structures began the week of September 24 and is expected to be completed the week of October 1.  Additional concrete work in the area will continue through the week the early part of next week. 

American Boulevard Area (E. American Boulevard from 24th Street to 28th Avenue)
Removal of concrete items will continue into the week of October 1 and be followed by replacement of concrete items.  Adjustment of utility structures is expected to take place the week of October 1.

Brookside Area (includes Brookside Avenue, Brookside Circle, Upton Circle, Washburn Avenue, Upton Road, Xerxes Curve, York Curve, W. 100th Street, W. 101st Street, W. 98th ½ Street)
Milling of the existing pavement was completed early the week of September 24 and was followed by paving the new asphalt surface.  Due to a rainy September, sod availability is limited and has delayed sod installation.  Sod installation is expected late in the week of October 1.

September 21, 2018

2018-101 PMP Street Improvement Project

An assessment informational meeting for the 2018-101 PMP Street Improvement Project is scheduled for Monday, September 24 at 5:30 PM in the Bloomington Public Works Training Room. The public hearing to order the assessments at Bloomington City Council is scheduled for Monday, October 1. Mailings have been sent to all affected residents.

Girard Avenue (from West 102nd Street to West 100th Street)
Boulevard restoration and sod installation is anticipated to complete early in the week of September 24. Paving of the final layer of asphalt is scheduled for the week of September 24.

James Avenue Area (includes James Avenue, Knox Avenue, West 91st Street)
Raising of manholes and gate valves is scheduled for late in the week of September 17. Boulevard restoration, sod installation, and paving of asphalt driveways are scheduled for the week of September 24. The final layer of asphalt is anticipated to be paved late in the week of September 24 or the week of October 1.

West 86th Street (from Xerxes Avenue to Penn Avenue)
Concrete installation is anticipated to complete late in the week of September 17, weather permitting. Final grading of class 5 gravel is scheduled for late in the week of September 17, including Saturday, September 22, weather permitting. Paving of the first layer of asphalt is anticipated to occur the week of September 24. This will be followed by raising of manholes and gate valves and boulevard restoration later in the week.

4th Avenue (from 84th Street to 86th Street)
Pavement removal is scheduled for September 24 and will be followed by storm sewer work. Common excavation and placement of class 5 gravel is anticipated to begin later in the week of September 24.

Park Avenue Area (includes Park Avenue, East 87th 1/2 Street, Oakland Avenue)
Pavement removal is scheduled for September 24. Storm sewer and water main work is scheduled to begin mid-week of September 24 and complete the week of October 1. Storm sewer work on Park Avenue at 86th Street will require a short 1-2 day closure of 86th Street at Park Avenue. This will be followed by common excavation and placement of class 5 gravel.

83rd Street Area (includes East 83rd Street, Columbus Avenue, Elliot Avenue)
Pavement removal is scheduled for late in the week of September 24. Storm sewer work will then follow the week of October 1.

16th Avenue (from 82nd Street to North Terminus)
Pavement removal is anticipated to occur in early October. More information will be given when a schedule is determined.

Glenview Lane (from East Old Shakopee Rd to Southeast Terminus)
Pavement removal is anticipated to occur in early October. More information will be given when a schedule is determined.

2018-102 PMP Street Maintenance Project

34th Avenue at Appletree
Traffic signal revision work at the intersection has been scheduled for Wednesday, September 26 and will require a shutdown of the signal. Appropriate traffic control and personnel will be onsite to direct traffic.

24th Avenue at Killebrew Drive
Traffic signal revision work at the intersection has been scheduled for Wednesday, October 3 and will require a shutdown of the signal. Appropriate traffic control and personnel will be onsite to direct traffic.

12th Avenue Area (12th Avenue from East 86th Street to American Boulevard, East 82nd Street from 12th Avenue to West Terminus)
Removals are expected to continue into the week of September 24, and will be followed by replacement of concrete curb and gutter in the area as well as sidewalk replacement and construction.

American Boulevard Area (East American Boulevard from 24th Avenue to 28th Avenue)
Removal of concrete items will continue into the week of September 24, and be followed by replacement of concrete items.

Brookside Area (includes Brookside Avenue, Brookside Circle, Upton Circle, Washburn Avenue, Upton Road, Xerxes Curve, York Curve, West 100th Street, West 101st Street, West 98th 1/2 Street)
Concrete work was completed late the week of September 17, and is scheduled to be followed by boulevard restoration. Milling of the existing pavement is scheduled for late the week of September 24, and be followed by final paving.

September 14, 2018

2018-101 PMP Street Improvement Project

An assessment informational meeting for the 2018-101 PMP Street Improvement Project is scheduled for Monday, September 24 at 5:30 PM in the Bloomington Public Works Training Room. The public hearing to order the assessments at Bloomington City Council is scheduled for Monday, October 1. Mailings have been sent to all affected residents.

Girard Avenue (from West 102nd Street to West 100th Street)
Concrete work and paving of the first layer of asphalt is complete. Boulevard restoration and raising of manholes and gate valves has started and will complete early in the week of September 17. Paving of asphalt driveways and sod installation are scheduled for the week of September 17. Paving of the final layer of asphalt is anticipated to occur late in the week of September 17 or the week of September 24.

James Avenue Area (includes James Avenue, Knox Avenue, West 91st Street)
Concrete installation is complete and final grading of class 5 gravel has started and is anticipated to complete by Saturday, September 15. Paving of the first layer of asphalt is scheduled for early in the week of September 17 and will be followed by boulevard restoration, paving of asphalt driveways and raising of manholes and gate valves.

West 86th Street (from Xerxes Avenue to Penn Avenue)
Common excavation and placement of class 5 gravel is complete. Concrete installation has started and will complete early in the week of September 17. Final grading of class 5 gravel and paving of the first layer of asphalt will follow later in the week of September 17.

4th Avenue (from 84th Street to 86th Street)
Pavement removal is anticipated to occur the week of September 24.

83rd Street Area (includes East 83rd Street, Columbus Avenue, Elliot Avenue)
Pavement removal is anticipated to occur the week of September 24.

Park Avenue Area (includes Park Avenue, East 87th 1/2 Street, Oakland Avenue)
Pavement removal is anticipated to occur the week of September 24.

2018-102 PMP Street Maintenance Project

34th Avenue at American Boulevard
Traffic signal revision work at the intersection will be evaluated early Monday morning on September 17.

12th Avenue Area (12th Avenue from East 86th Street to American Boulevard, East 82nd Street from 12th Avenue to West Terminus)
Removal of existing concrete curb and gutter has been scheduled for the week of September 17. Tree clearing and sidewalk removals are also expected.

24th Avenue at Killebrew Drive
Traffic signal revision work at the intersection has been scheduled for Tuesday, September 18 and will require a shutdown of the signal. Appropriate traffic control and personnel will be onsite to direct traffic.

34th Avenue at Appletree
Traffic signal revision work at the intersection has been tentatively scheduled for Saturday, September 22 and will require a shutdown of the signal. Appropriate traffic control and personnel will be onsite to direct traffic.

American Boulevard Area (East American Boulevard from 24th Avenue to 28th Avenue)
Work in the area is expected to begin late the week of September 17 with removal of existing concrete items. Advance notification signs for the area were placed September 13.

Brookside Area (includes Brookside Avenue, Brookside Circle, Upton Circle, Washburn Avenue, Upton Road, Xerxes Curve, York Curve, West 100th Street, West 101st Street, West 98th 1/2 Street)
Concrete work for curb and gutter as well as installation of driveways continues in the Brookside area and is expected to be completed the week of September 17. Adjustment of utility structures to meet the proposed asphalt surface is scheduled for the week of September 17.

Bloomington Cemetery (Cemetery Road from Lyndale Avenue to the West)
Paving of the final layer of asphalt was completed Wednesday, September 12 and was followed by boulevard restoration work on September 13 and 14. The area is substantially complete with punch list items remaining.

September 7, 2018

2018-101 PMP Street Improvement Project

Girard Avenue (from West 102nd Street to West 100th Street) 
Concrete curb and driveway installation has started and is scheduled to complete by Saturday, September 8. Final grading of class 5 gravel is scheduled for early in the week of September 10 and paving of the first layer of asphalt will follow later in the week.

James Avenue Area (includes James Avenue, Knox Avenue, West 91st Street)
Storm sewer work is complete. Common excavation and installation of class 5 gravel is anticipated to complete by Saturday, September 8. Concrete curb and driveway installation is scheduled for the week of September 10.

West 86th Street (from Xerxes Avenue to Penn Avenue)
Storm sewer work has started and will complete early in the week of September 10. Common excavation and placement of class 5 gravel is scheduled to begin early in the week of September 10 and will be followed by concrete curb and driveway installation, either late in the week of September 10 or the week of September 17.

2018-102 PMP Street Maintenance Project

34th Avenue at American Boulevard
Traffic signal revision work at the intersection is scheduled to begin late the week of September 10 and will continue into the weekend. Traffic signal work will be coordinated with Metro Transit LRT and their scheduled LRT shutdown.

12th Avenue Area (12th Avenue from East 86th Street to American Boulevard, East 82nd Street from 12th Avenue to West Terminus)
Work is scheduled to begin early the week of September 17. Advance notice signs will be placed early next week in addition to other preliminary work such as delivery of traffic control. 

Brookside Area (includes Brookside Avenue, Brookside Circle, Upton Circle, Washburn Avenue, Upton Road, Xerxes Curve, York Curve, West 100th Street, West 101st Street, West 98th ½ Street)
Removal of existing curb and gutter continued through the week of September 3 and was followed by installation of concrete curb and gutter.  Concrete work is expected to continue into the week of September 10.  Adjustment of utility structures continues in the area.

Bloomington Cemetery (Cemetery Road from Lyndale Avenue to the west)
Paving of the base layer of asphalt was completed and followed by driveway installations and boulevard restoration. Final paving is currently scheduled to be completed the week of September 10 to substantially complete work in the area.

August 2018

August 31, 2018

2018-101 PMP Street Improvement Project

West 108th Street Area (includes West 108th Street, Chowen Avenue, Chowen Circle)
Paving of the final layer of asphalt is complete.  Sod and seed installation is scheduled to complete late in the week of August 27 (weather permitting).  If weather does not allow, the sod will be completed the week of September 3, which will not impact access to Westwood Schools adjacent to 108th Street.  

Kell Avenue Area (includes Kell Avenue, Kell Circle)
Paving of the final layer of asphalt is complete.  Sod and seed installation is scheduled to complete late in the week of August 27 (weather permitting).  If weather does not allow, the sod will be completed the week of September 3, which will not impact school access on Kell Avenue.  

Sherwood Circle (from Overlook Drive to South Terminus)
Paving of the final layer of asphalt along with sod installation are scheduled to complete by the week of September 3.

Upton Circle (from West 106th Street to North Terminus)
Paving of the final layer of asphalt along with sod installation are scheduled to complete by the week of September 3.

Girard Avenue (from West 102nd Street to West 100th Street)
Common excavation and installation of class 5 gravel is anticipated to complete by the end of the week of August 27.  Concrete curb installation is scheduled for the week of September 3.

James Avenue Area (includes James Avenue, Knox Avenue, West 91st Street)
Water main installation is complete and storm sewer work is anticipated to complete by the end of the week of August 27.  Common excavation and installation of class 5 gravel is scheduled for the week of September 3, which will be followed by concrete curb installation.

West 86th Street (from Xerxes Avenue to Penn Avenue)
Storm sewer work is scheduled to begin early in the week of September 3.  This will be followed by common excavation and placement of class 5 gravel.

Dakota Road (from West 96th Street to Colorado Avenue)
Paving of the final layer of asphalt was delayed due to rain and is scheduled for early in the week of September 3 (weather permitting). 

W. 98th Street (from Colorado Road to Nesbitt Avenue)
Paving of the final layer of asphalt was delayed due to rain and is scheduled for early in the week of September 3 (weather permitting). 

2018-102 PMP Street Maintenance Project

Brookside Area (includes Brookside Avenue, Brookside Circle, Upton Circle, Washburn Avenue, Upton Road, Xerxes Curve, York Curve, W. 100th Street, W. 101st Street, W. 98th ½ Street )
Removals in the Brookside Area began early the week of August 27 and will continue through the week of September 3.  Storm sewer utility work is scheduled to begin after the Labor Day holiday. 

W. 78th Street from Viking Drive to W. 78th Street Circle
Paving of the new asphalt surface was completed early the week of August 27 and followed by pavement markings to substantially complete work in the area.  Punch list work remains.

Bloomington Cemetery (Cemetery Road from Lyndale Avenue to the west)
Installation of concrete curb and gutter was completed the week of August 27 and followed by fine grading of the aggregate rock base.  Paving of the base layer of asphalt is scheduled for early the week of September 3.  Construction of service entrances and boulevard restoration to follow.

August 24, 2018

2018-101 PMP Street Improvement Project

Dakota Road (from West 96th Street to Colorado Avenue)
Paving of the final layer of asphalt is scheduled for early in the week of August 27. 
 
W. 98th Street (from Colorado Road to Nesbitt Avenue)
Paving of the final layer of asphalt is scheduled for early in the week of August 27. 
 
West 108th Street Area (includes West 108th Street, Chowen Avenue, Chowen Circle)
Boulevard restoration along with sod and seed installation is scheduled to complete the week of August 27 (weather permitting).  Paving of the final layer of asphalt is scheduled for late in the week of August 27.  
 
Kell Avenue Area (includes Kell Avenue, Kell Circle)
Boulevard restoration along with sod and seed installation is scheduled to complete the week of August 27 (weather permitting).  Paving of the final layer of asphalt is scheduled for late in the week of August 27.  
 
Sherwood Circle (from Overlook Drive to South Terminus)
Boulevard restoration along with sod installation is anticipated to complete the week of August 27 (weather permitting).  Paving of the final layer of asphalt in anticipated to occur in early September.
 
Upton Circle (from West 106th Street to North Terminus)
Boulevard restoration along with sod installation is anticipated to complete the week of August 27 (weather permitting).  Paving of the final layer of asphalt in anticipated to occur in early September.
 
Girard Avenue (from West 102nd Street to West 100th Street)
Storm sewer work has started and will complete early in the week of August 27.  Common excavation and installation of class 5 gravel will follow behind the storm sewer work.
 
James Avenue Area (includes James Avenue, Knox Avenue, West 91st Street)
Storm sewer work is scheduled for early in the week of August 27.  Water main installation on the north end of Knox Avenue is scheduled to begin early-mid week of August 27.  This work will require a 1 day, approximately 8 hour water main shutdown to make the water main connections.  The affected properties will be along 90th Street and residents will be notified in advance of the work.  Common excavation and installation of class 5 gravel will follow after the water main and storm sewer work is complete.
 
West 86th Street (from Xerxes Avenue to Penn Avenue)
Pavement removal is scheduled for early in the week of August 27.  This will be followed by storm sewer work the remainder of the week.

2018-102 PMP Street Maintenance Project

Brookside Area (includes Brookside Avenue, Brookside Circle, Upton Circle, Washburn Avenue, Upton Road, Xerxes Curve, York Curve, W. 100th Street, W. 101st Street, W. 98th ½ Street )
Work in the Brookside area is scheduled to begin on Monday, August 27 with removals. Preliminary work, including the installation of inlet protection was completed late the week of August 20. Center Point Energy is currently working on Brookside Avenue with gas main and services repairs.
 
West 109th Street Area (includes West 109th Street, Goodrich Avenue, Harrison Avenue, Irwin Avenue)
Milling of the existing pavement was completed Wednesday August 22  and followed by paving of the new asphalt the on Thursday, August 23. Restoration of boulevard areas remains in addition to punchlist items.
 
West 78th Street from Viking Drive to West 78th Street Circle
Milling of the existing pavement was completed on Thursday, August 23 and scheduled to be paved the following day barring inclement weather.  Monday, August 27 has been schedule as a backup date. Pavement striping to follow late the week of August 27.
 
Bloomington Cemetery (Cemetery Road from Lyndale Avenue to the west)
Excavation of the proposed road extension has been completed along with the installation of rock aggregate base.  Installation of concrete curb and gutter is scheduled to be completed early the week of August 27.

August 17, 2018

2018-101 PMP Street Improvement Project

West 108th Street Area (includes West 108th Street, Chowen Avenue, Chowen Circle)
Paving of the first layer of asphalt will be complete by the end of the week of August 13.  This will be followed by raising of manholes and gate valves and boulevard restoration continuing through the week of August 20.  Sod and seed installation is anticipated to occur the week of August 27 and be followed by paving of the final layer of asphalt later in the week.  

Kell Avenue Area (includes Kell Avenue, Kell Circle)
Paving of the first layer of asphalt will be complete by the end of the week of August 13.  This will be followed by raising of manholes and gate valves and boulevard restoration continuing through the week of August 20.  Sod and seed installation is anticipated to occur the week of August 27 and be followed by paving of the final layer of asphalt later in the week.  

Sherwood Circle (from Overlook Drive to South Terminus)
Fine grading of class 5 gravel is scheduled to be complete by the end of the week of August 13, with paving of the first layer of asphalt scheduled for early in the week of August 20.  This will be followed by raising of manholes and gate valves along with boulevard restoration the remainder of the week of August 20.  Sod installation is anticipated to occur in late August, with paving of the final layer of asphalt in early September.

Upton Circle (from West 106th Street to North Terminus)
Fine grading of class 5 gravel is scheduled to be complete by the end of the week of August 13, with paving of the first layer of asphalt scheduled for early in the week of August 20.  This will be followed by raising of manholes and gate valves, along with boulevard restoration the remainder of the week of August 20.  Sod installation is anticipated to occur in late August, with paving of the final layer of asphalt in early September.

Girard Avenue (from West 102nd Street to West 100th Street)
Pavement removal is scheduled to begin early in the week of August 20.  Storm sewer work will follow pavement removal later in the week of August 20.

James Avenue Area (includes James Avenue, Knox Avenue, West 91st Street)
Pavement removal is scheduled for mid-week of August 20.  Storm sewer and water main work is anticipated to begin late in the week of August 20 or the week of August 27.

West 86th Street (from Xerxes Avenue to Penn Avenue)
Pavement removal is anticipated to begin late in the week of August 20 or early in the week of August 27.

2018-102 PMP Street Maintenance Project

W. 109th Street Area (includes W. 109th Street, Goodrich Avenue, Harrison Avenue, Irwin Avenue)
Restoration of the boulevard areas is scheduled to be completed early the week of August 20, and will be followed by the milling of the existing pavement and paving the new asphalt surface.

W. 78th Street from Viking Drive to W. 78th Street Circle
Adjustment of utility structures and patching of the area will continue to early the week of August 20 and will be followed boulevard restoration.  Milling of the existing pavement and paving of the new asphalt surface are scheduled for late the week of August 20.  W. 78th Street from Viking Drive to Computer Avenue remains closed and is expected to be opened early the week of August 20. 

Bloomington Cemetery (Cemetery Road from Lyndale Avenue to the west)
Construction of the Cemetery Road extension is scheduled to begin Monday, August 20 with removals and excavation of the proposed road area.  Any ceremonies scheduled with the City Clerk’s Office will be coordinated with the project.

August 10, 2018

2018-101 PMP Street Improvement Project

Dakota Road (from West 96th Street to Colorado Avenue)
Paving of the final layer of asphalt has been slightly delayed and will either occur late in the week of August 6 or the week of August 13. 

W. 98th Street (from Colorado Road to Nesbitt Avenue)
Paving of the final layer of asphalt has been slightly delayed and will either occur late in the week of August 6 or the week of August 13. 

W. 108th Street Area (includes West 108th Street, Chowen Avenue, Chowen Circle)
Concrete installation is scheduled to be complete by late in the week of August 6.  Fine grading of class 5 gravel is scheduled for the week of August 13 with paving of the first layer of asphalt anticipated to occur late in the week of August 13 (weather permitting).  

Kell Avenue Area (includes Kell Avenue, Kell Circle)
Concrete installation is scheduled to be complete by late in the week of August 6.  Fine grading of class 5 gravel is scheduled for the week of August 13 with paving of the first layer of asphalt anticipated to occur late in the week of August 13 (weather permitting).  

Sherwood Circle (from Overlook Drive to South Terminus)
Pavement removal, excavation and initial placement of class 5 are anticipated to be complete by late in the week of August 6.  Concrete removal and installation are scheduled for early in the week of August 13.  Fine grading of class 5 gravel is scheduled for late in the week of August 13, which will be followed by paving of the first layer of asphalt the week of August 20.

Upton Circle (from West 106th Street to North Terminus)
Pavement removal, excavation and initial placement of class 5 are anticipated to be complete by late in the week of August 6.  Concrete removal and installation are scheduled for early in the week of August 13.  Fine grading of class 5 gravel is scheduled for late in the week of August 13, which will be followed by paving of the first layer of asphalt the week of August 20.

Girard Avenue (from West 102nd Street to West 100th Street)
Saw cutting in advance of concrete and pavement removal is anticipated to begin the week of August 13.  Pavement removal is anticipated to occur the week of August 20.

James Avenue Area (includes James Ave, Knox Ave, W 91st St)
Saw cutting in advance of concrete and pavement removal is anticipated to begin the week of August 13.  Pavement removal is anticipated to occur the week of August 20.

2018-102 PMP Street Maintenance Project

Killebrew Drive from MN Trunk Highway 77 to 24th Avenue (CSAH 1)
Striping and installation of pavement messages have been completed at 20th Avenue and Killebrew Drive to substantially complete work in the area.  Punchlist, traffic signal and signage work will occur periodically in the coming months with temporary traffic control.

W. 109th Street Area (includes W. 109th Street, Goodrich Avenue, Harrison Avenue, Irwin Avenue)
Work on the adjustment of utility structures is ongoing and is expected to be complete the week of August 13 and be followed by boulevard the restoration the week of August 20.

W. 78th Street from Viking Drive to W. 78th Street Circle
Construction for the area began on Tuesday, August 7 with removals and continues with concrete curb and gutter work that will be followed by pavement restoration and concrete sidewalk work the week of August 13.  W. 78th Street/Normandale Service Road remains closed between Viking Drive and Computer Avenue, business access continues to be maintained.

Bloomington Cemetery (Cemetery Road from Lyndale Avenue to the west)
Construction of the Cemetery Road extension has been tentatively scheduled for late the week of August 13.  Work would begin with removals of existing pavement and excavation of the proposed road area.

August 3, 2018

2018-101 PMP Street Improvement Project

Palmer Road Area (includes Palmer Road, Quinn Road, Rich Road, West 93rd Street, West 94th Street, Fawnridge Circle and Collegeview Circle)
Paving of the final layer of asphalt has started and will complete by Friday, August 3 (weather permitting).

Dakota Road (from West 96th Street to Colorado Avenue)
Sod installation is complete and paving of the final layer of asphalt is scheduled to complete by the end of the day Friday, August 3 (weather permitting). 

W. 98th Street (from Colorado Road to Nesbitt Avenue)
Sod installation is complete and paving of the final layer of asphalt is scheduled to complete by the end of the day Friday, August 3 (weather permitting). 

W. 108th Street Area (includes West 108th Street, Chowen Avenue, Chowen Circle)
Excavation and initial placement of class 5 gravel is complete.  Concrete installation is scheduled for the week of August 6.

Kell Avenue Area (includes Kell Avenue, Kell Circle)
Excavation and initial placement of class 5 gravel has started and will continue the week of August 6.  This will be followed by concrete installation later in the week.

Sherwood Circle (from Overlook Drive to South Terminus)
Concrete removal and replacement is anticipated to begin late in the week of August 6.

Upton Circle (from West 106th Street to North Terminus)
Concrete removal and replacement is anticipated to begin late in the week of August 6. 

2018-102 PMP Street Maintenance Project

W. 110th Street Area (includes W. 110th Street, W. 109th Street, Bush Lake Road, Louisiana Avenue)
Striping and pavement messages are expected to be completed late the week of July 30.

W. 111th Street Area (includes W. 111th Street, W. 110th Street, Nesbitt Avenue)
Striping and pavement messages are expected to be completed late the week of July 30.

Killebrew Drive from MN Trunk Highway 77 to 24th Avenue (CSAH 1)
Paving of the wearing coarse at the Killebrew Drive and 20th Avenue intersection has been completed.  Striping and pavement message installation has been scheduled late the week of August 6 and will be followed by periodic traffic signal work in the coming months.

Nicollet Avenue (CSAH 52) 98th Street to American Boulevard
Manhole rehabilitation work along Nicollet Avenue has been completed.

Portland Avenue (CSAH 35) E. 98th Street to E. 81st  Street
Manhole rehabilitation on Portland Avenue has been completed.

W. 109th Street Area (includes W. 109th Street, Goodrich Avenue, Harrison Avenue, Irwin Avenue)
Removal of concrete curb and concrete walk has been removed and replaced for the area.  Storm sewer utility work has been completed as well.  The contractor will commence the adjustment of utility structures in the area the week of August 6.

W. 78th Street from Viking Drive to W. 78th Street Circle
Construction is scheduled to begin on Tuesday, August 7 barring inclement weather.  A closure notice of Normandale Service Road/W. 78th Street between Viking Drive and Computer Avenue will be posted with corresponding detour signs.

 

 

July 2018

July 27, 2018

2018-101 PMP Street Improvement Project

Palmer Road Area (includes Palmer Road, Quinn Road, Rich Road, W. 93rd Street, W. 94th Street, Fawnridge Circle and Collegeview Circle)
Sod installation is complete and paving of the final layer of asphalt is scheduled for the week of July 30.

Dakota Road (from W. 96th Street to Colorado Avenue)
Paving of the first layer of asphalt is complete, Raising of manholes and gate valves, boulevard restoration and paving of asphalt driveways will occur over the next week with paving of the final layer of asphalt anticipated to occur the week of August 6.

W. 98th Street (from Colorado Road to Nesbitt Avenue)
Paving of the first layer of asphalt is complete. Raising of manholes and gate valves, boulevard restoration and paving of asphalt driveways will occur over the next week, with paving of the final layer of asphalt anticipated to occur the week of August 6.

W. 108th Street Area (includes W. 108th Street, Chowen Avenue, Chowen Circle)
Concrete removals have started in the area and pavement removal is scheduled for Saturday, July 28. Storm sewer work and manhole reconstruction is scheduled for the week of July 30, which will be followed by excavation and placement of class 5 gravel.

Kell Avenue Area (includes Kell Avenue, Kell Circle)
Concrete removals have started in the area and pavement removal is scheduled for Saturday, July 28. Storm sewer work and manhole reconstruction is scheduled for the week of July 30, which will be followed by excavation and placement of class 5 gravel.

Sherwood Circle (from Overlook Drive to South Terminus)
Manhole reconstruction is scheduled for late in the week of July 30. Concrete removals are anticipated to occur the week of August 6.

Upton Circle (from West 106th Street to North Terminus)
Manhole reconstruction is scheduled for late in the week of July 30. Concrete removals are anticipated to occur the week of August 6.

2018-102 PMP Street Maintenance Project

W 109th Street Area (includes W 109th Street, Goodrich Avenue, Harrison Avenue, Irwin Avenue)
Construction is scheduled to begin in the W 109th Street Area on July 30 with storm sewer utility work. Removal of existing concrete is expected to take place early the week of July 30 with the installation of new concrete to follow.

W 110th Street Area (includes W 110th Street, W 109th Street, Bush Lake Road, Louisiana Avenue)
Paving of the asphalt surface was completed earlier in the week, striping and pavement messages are scheduled to be installed the week of July 30 to substantially complete the area. Punchlist items will remain.

W 111th Street Area (includes W 111th Street, W 110th Street, Nesbitt Avenue)
Paving of the asphalt surface was completed earlier in the week, striping and pavement messages are scheduled to be installed the week of July 30 and will be followed by minimal electrical work. Punchlist items will remain.

Killebrew Drive from MN Trunk Highway 77 to 24th Avenue (CSAH 1)
Storm sewer work was completed early the week of July 23, and was followed by concrete work and paving of the initial asphalt lifts at 20th Avenue and Killebrew Drive. Landscaping and electrical work will continue into the week of July 30.

Nicollet Avenue (CSAH 52) (98th Street to American Boulevard)
Manhole rehabilitation work along Nicollet Avenue continues, and is expected to be completed the week of July 30. Completion of the manhole rehabilitation work will be followed by the CenterPoint Energy Beltline Project on Nicollet Avenue.

Portland Avenue (CSAH 35) (98th Street to E 81st Street)
Manhole rehabilitation on Portland Avenue is scheduled to begin the week of July 23, and is expected to be completed late the week of July 30. Completion of the manhole rehabilitation work will be followed by the Hennepin County Mill and Overlay project.

July 20, 2018

2018-101 PMP Street Improvement Project

Palmer Road Area (includes Palmer Road, Quinn Road, Rich Road, W. 93rd Street, W. 94th Street, Fawnridge Circle and Collegeview Circle)
Sod installation is scheduled for the week of July 23, which will be followed by paving of the final layer of asphalt.

Dakota Road (from W. 96th Street to Colorado Avenue)
Concrete replacement has been slightly delayed by rain, but is anticipated to complete early in the week of July 23.  Fine grading of class 5 gravel has started and paving of the first layer of asphalt is scheduled for the week of July 23.  This will be followed by raising of manholes and gate valves, and boulevard restoration.

W. 98th Street (from Colorado Road to Nesbitt Avenue)
Concrete replacement is complete.  Fine grading of class 5 gravel has started and paving of the first layer of asphalt is scheduled for the week of July 23.  This will be followed by raising of manholes and gate valves, and boulevard restoration.

W. 108th Street Area (includes W. 108th Street, Chowen Avenue, Chowen Circle)
Pavement removal is anticipated to occur late in the week of July 23.

Kell Avenue Area (includes Kell Avenue, Kell Circle)
Pavement removal is anticipated to occur late in the week of July 23.

2018-102 PMP Street Maintenance Project

W. 110th Street Area (includes W. 110th Street, W. 109th Street, Bush Lake Road, Louisiana Avenue)
Milling of the existing pavement is expected to be completed by week’s end, prior to paving of the new asphalt surface to be completed early the week of July 23. A variance to begin work early in the area has been approved for the dates of July 20, 23-24.

W. 111th Street Area (includes W. 111th Street, W. 110th Street, Nesbitt Avenue)
Milling of the existing pavement is expected to be completed by week’s end, prior to paving of the new asphalt surface to be completed early the week of July 23. A variance to begin work early in the area has been approved for the dates of July 20, 23-24.

Killebrew Drive from MN Trunk Highway 77 to 24th Avenue (CSAH 1)
Relocation of a traffic signal pole was completed earlier in the week, in addition to boulevard restoration.  Boulevard restoration is expected to be completed the week of July 23, as work transitions to the northeast portion of the intersection with storm sewer utility and concrete work. 

Nicollet Avenue (CSAH 52) (98th Street to American Boulevard)
Manhole rehabilitation work along Nicollet Avenue continues into the week of July 23 and is expected to be completed the week of July 30.

Portland Avenue (CSAH 35) (E. 98th Street to E. 81st  Street)
Manhole rehabilitation on Portland Avenue is scheduled to begin the week of July 23 and is expected to be completed late the week of July 30.

July 13, 2018

2018-101 PMP Street Improvement Project

Palmer Road Area (includes Palmer Road, Quinn Road, Rich Road, W. 93rd Street, W. 94th Street, Fawnridge Circle and Collegeview Circle)
Boulevard restoration has started and will continue the week of July 16 along with raising of manholes and gate valves.  Sod installation is anticipated to occur the week of July 23, which will be followed by paving of the final layer of asphalt.

Dakota Road (from W. 96th Street to Colorado Avenue)
Concrete replacement is scheduled for early in the week of July 16.  Fine grading of class 5 gravel is anticipated to begin late in the week of July 16, which will be followed by paving of the first layer of asphalt the week of July 23.

W. 98th Street (from Colorado Road to Nesbitt Avenue)
Concrete replacement is scheduled for early in the week of July 16.  Excavation and placement of class 5 gravel has been slowed due to the recent rain and is anticipated to complete early in the week of July 16.  Fine grading of class 5 gravel is anticipated to begin late in the week of July 16, which will be followed by paving of the first layer of asphalt the week of July 23.

W. 108th Street Area (includes W. 108th Street, Chowen Avenue, Chowen Circle)
CenterPoint Energy has completed gas main and service installation in this area.  Pavement removal as part of the 2018-101 PMP Project is anticipated to begin in late July.

Kell Avenue Area (includes Kell Avenue, Kell Circle)
Tree removal in advance of the 2018-101 PMP Project is anticipated to occur the week of July 16.  Pavement removal in the area is anticipated to begin in late July.

Girard Avenue (from W 100th Street to W 102nd Street)
CenterPoint Energy has completed gas main and service installation in this area.  Tree removal in advance of the 2018-101 PMP Project is anticipated to occur the week of July 16.  More information will be given when pavement removal is scheduled later in the summer.

James Avenue Area (includes James Avenue, Knox Avenue, W 91st Street)
CenterPoint energy has started gas main replacement in this area and will continue for the next couple of weeks.  Tree removal in advance of the 2018-101 PMP Project is anticipated to occur the week of July 16.  More information will be given when pavement removal is scheduled later in the summer.

86th Street (from Xerxes Avenue to Penn Avenue)
Tree removal in advance of the 2018-101 PMP Project is anticipated to occur the week of July 16.  More information will be given when pavement removal is scheduled later in the summer.

2018-102 PMP Street Maintenance Project

W. 110th Street Area (includes W. 110th Street, W. 109th Street, Bush Lake Road, Louisiana Avenue)
Boulevard restoration is ongoing and is expected to be completed early the week of July 16.  Milling of the existing pavement is expected to begin by late the week of July 16 and will be followed by paving of the new asphalt surface.  A variance to begin work early in the area is expected to be requested for the dates July 20, 23-24

W. 111th Street Area (includes W. 111th Street, W. 110th Street, Nesbitt Avenue)
Boulevard restoration is ongoing and is expected to be completed early the week of July 16.  Milling of the existing pavement is expected to begin later in the week and will be immediately followed by paving of the new asphalt surface.  A variance to begin work early in the area is expected to be requested for the dates July 20, 23-24

Killebrew Drive from MN Trunk Highway 77 to 24th Avenue (CSAH 1)
Work at the 20th Avenue and Killebrew Drive intersection began the week of July 9 with initial removals to accommodate the electrical work for the proposed signal location.  Electrical work was followed by concrete installation for the first phase of the work.  Relocation of the signal pole is schedule for the midweek, the week of July 16, and will require a signal shutdown of the area. Paving of the initial asphalt for the first phases has been scheduled late the week of July 16.

Nicollet Avenue (CSAH 52) 98th Street to American Boulevard
Man hole rehabilitation work along Nicollet began the week of July 9 and is expected to carry into the week of July 16.  Additional lane closures on Nicollet Avenue, between American Boulevard and 81st Street are anticipated.

July 5, 2018

2018-101 PMP Street Improvement Project

Palmer Road Area (includes Palmer Road, Quinn Road, Rich Road, W 93rd Street, W 94th Street, Fawnridge Circle and Collegeview Circle)
Fine grading of class 5 gravel has started and will be followed by paving of the first layer of asphalt either late in the week of July 2 or the week of July 9. Paving of asphalt driveways is also anticipated to occur the week of July 9. Boulevard restoration will follow behind asphalt paving.

 

Dakota Road (from W 96th Street to Colorado Avenue) 
Excavation and placement of class 5 gravel will continue the week of July 9. Concrete replacement is anticipated to occur the week of July 16.

 

 

W 98th Street (from Colorado Road to Nesbitt Avenue)
Excavation and placement of class 5 gravel will continue the week of July 9. Concrete replacement is anticipated to occur the week of July 16.

 

 

W 108th Street Area (includes W 108th Street, Chowen Avenue, Chowen Circle)
Gas main and service installation will continue in this area the week of July 9.

 

2018-102 PMP Street Maintenance Project

 

W 110th Street Area (includes W 110th Street, W 109th Street, Bush Lake Road, Louisiana Avenue)
Adjustment of utility structures has been completed and will be followed by boulevard restoration, restoration work is expected to carry into the week of July 9. Milling of the existing pavement has been scheduled for the week of July 16 and is to be followed by asphalt paving.


W 111th Street Area (includes W 111th Street, W 110th Street, Nesbitt Avenue)
Adjustment of utility structures has been completed and will be followed by boulevard restoration, restoration work is expected to carry into the week of July 9. Milling of the existing pavement has been scheduled for the week of July 16 and is to be followed by asphalt paving.


Killebrew Drive from MN Trunk Highway 77 to 24th Avenue (CSAH 1)
Construction is scheduled to begin on Monday, July 9 with removals in the area and are to be followed by electrical work for a proposed traffic signal revision by midweek.  Initial concrete work is expected to begin by weeks end.

 

June 2018

June 29, 2018

2018-101 PMP Street Improvement Project

Palmer Road Area (includes Palmer Road, Quinn Road, Rich Road, W 93rd Street, W 94th Street, Fawnridge Circle and Collegeview Circle)
Concrete installation has started and will complete early in the week of July 2.  Fine grading of class 5 gravel is scheduled for the week of July 2, which will be followed by paving of the first layer of asphalt the week of July 9.

Dakota Road (from W 96th Street to Colorado Avenue)
Pavement removal is complete and concrete removals are scheduled for early in the week of July 2.  Excavation and placement of class 5 gravel is anticipated to begin late in the week of July 2.

W 98th Street (from Colorado Road to Nesbitt Avenue)
Pavement removal is complete and storm sewer work is anticipated to complete by the end of the day Friday, June 29 (weather permitting).  This storm sewer work will require the closure of 98th Street just west of Nesbitt Avenue for approximately 5-6 hours.  Concrete removals are scheduled for the week of July 2 with excavation and placement of class 5 gravel anticipated to begin the week of July 9.

W 108th Street Area (includes W 108th Street, Chowen Avenue, Chowen Circle)
CenterPoint Energy’s gas main installation will continue in this area the week of July 2.

2018-102 PMP Street Maintenance Project

W 110th Street Area (includes W. 110th Street, W. 109th Street, Bush Lake Road, Louisiana Avenue)
Installation of concrete work in the area is expected to be completed by week's end.  Adjustment of utility structures in the roadway is ongoing and will carry into the week of July 2, and is anticipated to be completed before the holiday.  Restoration of boulevard areas is expected to begin late the week of July 2.

W 111th Street Area (includes W. 111th Street, W. 110th Street, Nesbitt Avenue)
Installation of concrete work in the area is expected to be completed by week's end.  Adjustment of utility structures in the roadway is ongoing and will carry into the week of July 2, and is anticipated to be completed before the holiday.  Restoration of boulevard areas is expected to begin late the week of July 2.

W 109th Street Area (includes W. 109th Street, Goodrich Avenue, Harrison Avenue, Irwin Avenue)
Though initially scheduled to have construction begin the week of July 2, construction has been has been postponed until a later time yet to be determined.

Killebrew Drive from MN Trunk Highway 77 to 24th Avenue (CSAH 1)
Preliminary work on Killebrew Drive is expected to take place late the week of July 2 in anticipation of construction scheduled to begin the week of July 9.

June 22, 2018

2018-101 PMP Street Improvement Project

Palmer Road Area (includes Palmer Road, Quinn Road, Rich Road, W 93rd Street, W 94th Street, Fawnridge Circle and Collegeview Circle)
Storm sewer work is complete.  Excavation and placement of class 5 gravel in the area has started and will complete early in the week of June 25.  Concrete installation is scheduled to begin early in the week of June 25.

Dakota Road (from W 96th Street to Colorado Avenue)
The contractor may begin pavement removal in this area late in the week of June 25 or it will occur in early July.

W 98th Street (from Colorado Road to Nesbitt Avenue)
The contractor may begin pavement removal in this area late in the week of June 25 or it will occur in early July.

W 108th Street Area (includes W 108th Street, Chowen Avenue, Chowen Circle)
CenterPoint Energy’s start in this area has been slightly delayed and they are scheduled to start the week of June 25.

Girard Avenue (from W 100th Street to W 102nd Street)
CenterPoint Energy has started gas main installation in this area and will continue with gas service installation the week of June 25.

2018-102 PMP Street Maintenance Project

W 110th Street Area (includes W 110th Street, W 109th Street, Bush Lake Road, Louisiana Avenue)
Concrete replacement was slightly delayed due to rain, but is anticipated to complete the week of June 25.  Reconstruction of manholes and storm sewer catch basins is also scheduled to complete the week of June 25.  Asphalt patching and adjustment of manholes and gate valves is scheduled for the week of June 25. 

W 111th Street Area (includes W 111th Street, W 110th Street, Nesbitt Avenue)
Concrete replacement was slightly delayed due to rain, but is anticipated to complete the week of June 25.  Reconstruction of manholes and storm sewer catch basins is also scheduled to complete the week of June 25.  Asphalt patching and adjustment of manholes and gate valves is scheduled for the week of June 25.

W 109th Street Area (includes W 109th Street, Goodrich Avenue, Harrison Avenue, Irwin Avenue)
Concrete removals are anticipated to start in this area the week of July 2.

June 15, 2018

2018-101 PMP Street Improvement Project

Palmer Road Area (includes Palmer Road, Quinn Road, Rich Road, W 93rd Street, W 94th Street, Fawnridge Circle and Collegeview Circle)
Pavement removal is complete and concrete removals will complete the week of June 18.  Storm sewer work along with manhole reconstruction has started and will complete the week of June 18.  Grading and placement of class 5 gravel in the area is scheduled to begin late in the week of June 18.  Concrete installation is anticipated to begin the week of June 25.

W 108th Street Area (includes W 108th Street, Chowen Avenue, Chowen Circle)
CenterPoint Energy anticipates starting gas main replacement in this area the week of June 18.

2018-102 PMP Street Maintenance Project

W 110th Street Area (includes W 110th Street, W 109th Street, Bush Lake Road, Louisiana Avenue)
Concrete removals and installation will continue the week of June 18.  Reconstruction of manholes and storm sewer catch basins is also scheduled to begin the week of June 18. 

W 111th Street Area (includes W 111th Street, W 110th Street, Nesbitt Avenue)
Concrete removals and installation will continue the week of June 18.  Reconstruction of manholes and storm sewer catch basins is also scheduled to begin the week of June 18.

June 8, 2018

2018-101 PMP Street Improvement Project

A Pre-Construction Meeting was held on June 5 at Bloomington Public Works.  The contractor anticipates starting work the week of June 11 in the areas listed below.

Palmer Road Area (includes Palmer Road, Quinn Road, Rich Road, W 93rd Street, W 94th Street, Fawnridge Circle and Collegeview Circle)
The contractor is scheduled to begin pavement and concrete removals in this area early in the week of June 11.

W 108th Street Area (includes W 108th Street, Chowen Avenue, Chowen Circle)
CenterPoint Energy anticipates starting gas main replacement in this area the week of June 18.

2018-102 PMP Street Maintenance Project

A Pre-Construction Meeting was held on June 6 at Bloomington Public Works.  The contractor anticipates starting work the week of June 11 in the areas listed below.

W 110th Street Area (includes W 110th Street, W 109th Street, Bush Lake Road, Louisiana Avenue)
The contractor is scheduled to begin concrete removals in this area mid-week of June 11.

W 111th Street Area (includes W 111th Street, W 110th Street, Nesbitt Avenue)
The contractor is scheduled to begin concrete removals in this area mid-week of June 11.

 

May 2018

May 25, 2018

2018-101 PMP Street Improvement Project

A pre-construction meeting has been scheduled during the week of June 4.  The contractor anticipates starting work around the week of June 11 and more information will be given when a schedule has been determined as to which areas will begin first. 

2018-102 PMP Street Maintenance Project

A pre-construction meeting has been scheduled for Wednesday, June 6 ahead of construction scheduled to begin the week of June 18.  The contractor is anticipating work to begin in the Bush Lake Road Area and Nesbitt Avenue areas south of Old Shakopee Road.

May 10, 2018

2018-102 PMP Street Maintenance Project
Irwin Area (W. 109th Street, Irwin Avenue, Harrison Avenue, Goodrich Avenue)

In advance of the City’s 2018 Street Maintenance Project, Center Point Energy will begin replacement of gas main and services in the Irwin Area the week of May 14.   

May 4, 2018

2018-101 PMP Street Improvement Project
Kell Avenue Area (includes Kell Avenue, Kell Circle)

CenterPoint Energy is scheduled to begin gas main replacement in this area the week of May 7, which is anticipated to take 2-3 weeks to complete.

Street reconstruction work for the 2018-101 PMP Project is anticipated to begin in early June, and more information will be given when the first areas have been scheduled to begin.

March 2018

March 23, 2018

The public hearing for the addition of W 91st Street to the 2018-101 PMP project is scheduled for Monday, April 2, 2018 at Bloomington City Council.  The Council meeting begins at 7:00pm.

February 2018

February 7, 2018

2018-101 PMP Street Improvement Project

The public hearing for the addition of 87 ½ Street and Oakland Avenue to the 2018-101 PMP Project is scheduled for February 12. 

February 2, 2018

2018-101 PMP Street Improvement Project

Notices regarding the 2018 PMP Street Improvement Project for the addition of 87 ½ Street and Oakland Avenue have been mailed to the affected properties.  Informational meetings will be scheduled for the week of February 5 for the affected properties.  The public hearing is scheduled for February 12.

November 2017

November 17, 2017

2018-101 PMP Street Improvement Project
Public informational meetings were held on November 13 at 2 p.m. and November 14 at 5:30 p.m. in the Public Works Training Room. The public hearing is scheduled for November 20.

November 9, 2017

2018-101 PMP Street Improvement Project
Notices regarding the 2018 PMP Street Improvement Project have been mailed to all affected properties.  Public informational meetings are scheduled for November 13 at 2 p.m. and November 14 at 5:30 p.m. in the Public Works Training Room. The public hearing is scheduled for November 20.

November 3, 2017

2018-101 PMP Street Improvement Project
Notices regarding the 2018 PMP Street Improvement Project have been mailed to all affected properties. Public informational meetings are scheduled for November 13 at 2:00 PM and November 14 at 5:30 PM in the Public Works Training Room. The public hearing is scheduled for November 20.

October 2017

October 6, 2017

2017-101 PMP Street Improvement Project
On Monday, October 2, a public hearing was held at City Council to order the assessments for all areas on the project.

September 2017

September 29, 2017

2017-101 PMP Street Improvement Project
Informational meetings for the assessment of the 2017-101 PMP Street Improvement Project were held in the Bloomington Public Works Training Room on Tuesday, September 26th at 2:00 p.m. and 5:30 p.m. The public hearing for the entire project will be held on Monday, October 2.

September 22, 2017

2017-101 PMP Street Improvement Project
Informational meetings for the assessment of the 2017-101 PMP Street Improvement Project will be held in the Bloomington Public Works Training Room on Tuesday, September 26 at 2:00 p.m. and 5:30 p.m. Residents may attend either meeting and are not required to attend both. Mailings for the meetings have been sent to the residents in the following areas.

Russell Area (Completed)

  • Russell Avenue from W. 108th Street to W. 106th Street
  • Queen Avenue from W. 108th Street to W. 106th Street
  • Queen Avenue from W. 106th Street to North Terminus
  • Queen Circle from Queen Avenue to West Terminus
  • W. 108th Street from Russell Avenue to Penn Avenue
  • W. 107th Street from Russell Avenue to Queen Avenue

Zenith Area (Completed)

  • Zenith Avenue from W. 110th Street to W. Old Shakopee Road
  • Abbott Avenue from W. 110th Street to W. 109th Street
  • Beard Avenue from W. 108th Street to W. Old Shakopee Road

Knox Area (In Progress)

  • Haeg Drive from W. 86th Street to Irving Avenue
  • Haeg Circle from Haeg Drive to East Terminus
  • Knox Avenue from W. 86th Street to W. 82nd Street
  • Irving Avenue from W. 85th Street to W. 83rd Street
  • Humboldt Avenue from W. 86th Street to W. 83rd Street
  • Valentine Terrace from Haeg Drive to Haeg Drive
  • W. 84th Street from Haeg Drive to Humboldt Avenue
  • W. 85th Street from Knox Avenue to Humboldt Avenue
  • Irving Curve from Knox Avenue to Irving Avenue
  • W. 83rd Street from Morgan Avenue to Humboldt Avenue

W. 80th Street Area (Completed)

  • W. 80th Street from American Boulevard to Thomas Avenue