Sidebar Widgets
E-Subscribe

Get email updates about the Pavement Management Program.

Contact Information

Contact Information

Engineering Division

Title

Pavement Management Program (PMP) Updates

Banner
Sections

September 2021

September 3, 2021

2021-101 PMP Street Improvement Project

Vincent Area Phase Two (W. 82nd Street, Sheridan Avenue, Russell Avenue, Queen Avenue, Sheridan Place (East of Sheridan Avenue))

Storm sewer installation will continue the week of September 13. Traffic control will also be set up on Penn Avenue between W. 84th Street and W. 82nd Street to accommodate installation of storm sewer on Penn Avenue. The contractor will also continue grading on W. 82nd Street between Xerxes Avenue and Thomas Avenue to prepare for the first lift of asphalt pavement.

Elliot Area (Elliot Avenue and E. 96th Street)

Concrete curb & gutter and concrete aprons will be installed on Friday, September 10 and Saturday, September 11. Residents who will have restricted access to their driveways during the concrete cure time will be notified via door hangers. The contractor will be final tolerancing the road base late the week of September 13 with the first lift of asphalt pavement scheduled for Saturday, August 18.

 

2021-102 PMP Street Maintenance Project

96th Street Area (W. 96th Street, W. 97th Street, W. 98th Street, Colorado Avenue, Colorado Road, Dakota Road, Edgewood Road, Alabama Circle, Brunswick Circle, Colorado Circle)

The contractor will begin grading the watermain trench on W. 96th Street will begin on Saturday, September 11. Concrete curb and gutter on W. 96th Street is scheduled for Wednesday, September 15.

Normandale Lake Area (Normandale Lake, American Boulevard, Green Valley Drive, W. 83rd Street, Norman Center Drive)

Concrete curb & gutter, concrete aprons, and concrete sidewalks will poured on Green Valley Drive on Friday, September 10 and Saturday, September 11. Milling of the existing pavement on Green Valley Drive is tentatively scheduled for Monday, September 20.

September 3, 2021

2021-101 PMP Street Improvement Project

Vincent Area Phase Two (W. 82nd Street, Sheridan Avenue, Russell Avenue, Queen Avenue, Sheridan Place (East of Sheridan Avenue))
Storm sewer installation will continue the week of August 6.

W. 108th Street (Johnson Avenue to France Avenue)
The final layer of asphalt was installed on Wednesday, September 1. Major work items in this area are complete.

E. 98th Street (Old Shakopee Road to Dellridge Road)
The final layer of asphalt was installed on Wednesday, September 1. Major work items in this area are complete.

Elliot Area (Elliot Avenue and E. 96th Street)
Concrete curb and gutter and concrete aprons are scheduled to begin on Wednesday, September 8. Residents who will have restricted access to their driveways during the concrete cure time will be notified via door hangers.
 

2021-102 PMP Street Maintenance Project

96th Street Area (W. 96th Street, W. 97th Street, W. 98th Street, Colorado Avenue, Colorado Road, Dakota Road, Edgewood Road, Alabama Circle, Brunswick Circle, Colorado Circle)
The contractor will begin the watermain testing process which will be begin late the week of August 30 and finish testing the week of September 7. The contractor will continue with the minor utility repairs in the area. CenterPoint Energy will begin the process of restoring the areas that were impacted by the gas main work.

Normandale Lake Area (Normandale Lake, American Boulevard, Green Valley Drive, W. 83rd Street, Norman Center Drive)
Work on the Green Valley Drive segment is scheduled to begin on Tuesday, September 7. The contractor will begin removing concrete curb and concrete aprons. The contractor will also be completing minor utility repairs.