Sidebar Widgets
E-Subscribe

Get email updates about the Pavement Management Program.

Contact Information

Contact Information

Engineering Division

Title

Pavement Management Program (PMP) Updates

Banner
Sections

September 2021

September 24, 2021

2021-101 PMP Street Improvement Project

Vincent Area Phase Two (W. 82nd Street, Sheridan Avenue, Russell Avenue, Queen Avenue, Sheridan Place (East of Sheridan Avenue))

The first lift of asphalt on W. 82nd Street from Xerxes Avenue to Russell Avenue will be installed on Friday, September 24. Concrete curb & gutter on the remaining street segments will be installed on Friday, September 24 and Saturday, September 25. Properties with concrete driveways will have their aprons installed early the week of  September 27. Residents who will have restricted access to their driveways during the concrete cure time will be notified via door hangers. The contractor is also installing the final lift of asphalt on Vincent Avenue and Upton Avenue on Friday, September 24.

Elliot Area (Elliot Avenue and E. 96th Street)

Topsoil installation and grading in preparation for sod installation is scheduled for the week of September 27.

W. 86th Street (Girard Avenue to Lyndale Avenue)

The City’s contractor will begin removing existing pavement on this segment on Tuesday, September 28. This segment of W. 86th Street will fully closed to thru traffic during the duration of the work. A signed detour will be provided.  

2021-102 PMP Street Maintenance Project

96th Street Area (W. 96th Street, W. 97th Street, W. 98th Street, Colorado Avenue, Colorado Road, Dakota Road, Edgewood Road, Alabama Circle, Brunswick Circle, Colorado Circle)

The contractor will also be removing and replacing miscellaneous concrete items throughout the area the week of September 27. The first lift of asphalt on the W. 96th Street watermain trench is scheduled to be installed the week of September 27.

Normandale Lake Area (Normandale Lake, American Boulevard, Green Valley Drive, W. 83rd Street, Norman Center Drive)

Milling of Green Valley Drive is scheduled for Tuesday, September 28 with asphalt paving scheduled for Saturday, October 2. This schedule is weather dependent and subject to change.

September 17, 2021

2021-101 PMP Street Improvement Project

Vincent Area Phase Two (W. 82nd Street, Sheridan Avenue, Russell Avenue, Queen Avenue, Sheridan Place (East of Sheridan Avenue))

Storm sewer installation will be completed by Friday, September 17. The contractor will begin tolerancing the road base on W. 82nd Street from Xerxes Avenue to Russell Avenue with the first lift of asphalt being installed on Thursday, September 24. Removal and replacement of the gravel base will begin on Monday, September 20 on the remaining sites in the area.

Elliot Area (Elliot Avenue and E. 96th Street)

The first lift of asphalt pavement is scheduled to be installed on Friday, September 17. Boulevard grading and topsoil installation is scheduled to begin on Friday, September 24.

W. 86th Street (Girard Avenue to Lyndale Avenue)

CenterPoint Energy is scheduled to complete its gas work in this area on Friday, September 24. The City’s contractor will begin removing existing pavement on this segment on Tuesday, September 28. This segment of W. 86th Street will fully closed to thru traffic during the duration of the work.

2021-102 PMP Street Maintenance Project

96th Street Area (W. 96th Street, W. 97th Street, W. 98th Street, Colorado Avenue, Colorado Road, Dakota Road, Edgewood Road, Alabama Circle, Brunswick Circle, Colorado Circle)

Concrete curb and gutter on W. 96th Street, Alabama Circle, and Brunswick Circle is scheduled to be installed the week of September 20. The contractor will also be removing and replacing miscellaneous concrete items throughout the area the week of September 20. The first lift of asphalt on the W. 96th Street watermain trench is scheduled to be installed the week of September 27.

Normandale Lake Area (Normandale Lake, American Boulevard, Green Valley Drive, W. 83rd Street, Norman Center Drive)

Restoration of the boulevard will be completed the week of September 20 on Green Valley Drive. The contractor has the mill and overlay on Green Valley Drive scheduled the week of September 27.

September 3, 2021

2021-101 PMP Street Improvement Project

Vincent Area Phase Two (W. 82nd Street, Sheridan Avenue, Russell Avenue, Queen Avenue, Sheridan Place (East of Sheridan Avenue))

Storm sewer installation will continue the week of September 13. Traffic control will also be set up on Penn Avenue between W. 84th Street and W. 82nd Street to accommodate installation of storm sewer on Penn Avenue. The contractor will also continue grading on W. 82nd Street between Xerxes Avenue and Thomas Avenue to prepare for the first lift of asphalt pavement.

Elliot Area (Elliot Avenue and E. 96th Street)

Concrete curb & gutter and concrete aprons will be installed on Friday, September 10 and Saturday, September 11. Residents who will have restricted access to their driveways during the concrete cure time will be notified via door hangers. The contractor will be final tolerancing the road base late the week of September 13 with the first lift of asphalt pavement scheduled for Saturday, August 18.

 

2021-102 PMP Street Maintenance Project

96th Street Area (W. 96th Street, W. 97th Street, W. 98th Street, Colorado Avenue, Colorado Road, Dakota Road, Edgewood Road, Alabama Circle, Brunswick Circle, Colorado Circle)

The contractor will begin grading the watermain trench on W. 96th Street will begin on Saturday, September 11. Concrete curb and gutter on W. 96th Street is scheduled for Wednesday, September 15.

Normandale Lake Area (Normandale Lake, American Boulevard, Green Valley Drive, W. 83rd Street, Norman Center Drive)

Concrete curb & gutter, concrete aprons, and concrete sidewalks will poured on Green Valley Drive on Friday, September 10 and Saturday, September 11. Milling of the existing pavement on Green Valley Drive is tentatively scheduled for Monday, September 20.

September 3, 2021

2021-101 PMP Street Improvement Project

Vincent Area Phase Two (W. 82nd Street, Sheridan Avenue, Russell Avenue, Queen Avenue, Sheridan Place (East of Sheridan Avenue))
Storm sewer installation will continue the week of August 6.

W. 108th Street (Johnson Avenue to France Avenue)
The final layer of asphalt was installed on Wednesday, September 1. Major work items in this area are complete.

E. 98th Street (Old Shakopee Road to Dellridge Road)
The final layer of asphalt was installed on Wednesday, September 1. Major work items in this area are complete.

Elliot Area (Elliot Avenue and E. 96th Street)
Concrete curb and gutter and concrete aprons are scheduled to begin on Wednesday, September 8. Residents who will have restricted access to their driveways during the concrete cure time will be notified via door hangers.
 

2021-102 PMP Street Maintenance Project

96th Street Area (W. 96th Street, W. 97th Street, W. 98th Street, Colorado Avenue, Colorado Road, Dakota Road, Edgewood Road, Alabama Circle, Brunswick Circle, Colorado Circle)
The contractor will begin the watermain testing process which will be begin late the week of August 30 and finish testing the week of September 7. The contractor will continue with the minor utility repairs in the area. CenterPoint Energy will begin the process of restoring the areas that were impacted by the gas main work.

Normandale Lake Area (Normandale Lake, American Boulevard, Green Valley Drive, W. 83rd Street, Norman Center Drive)
Work on the Green Valley Drive segment is scheduled to begin on Tuesday, September 7. The contractor will begin removing concrete curb and concrete aprons. The contractor will also be completing minor utility repairs.