Pavement Management Program (PMP) Updates

February 2018

February 7, 2018

2018-101 PMP Street Improvement Project

The public hearing for the addition of 87 ½ Street and Oakland Avenue to the 2018-101 PMP Project is scheduled for February 12. 

February 2, 2018

2018-101 PMP Street Improvement Project

Notices regarding the 2018 PMP Street Improvement Project for the addition of 87 ½ Street and Oakland Avenue have been mailed to the affected properties.  Informational meetings will be scheduled for the week of February 5 for the affected properties.  The public hearing is scheduled for February 12.

November 2017

November 17, 2017

2018-101 PMP Street Improvement Project
Public informational meetings were held on November 13 at 2 p.m. and November 14 at 5:30 p.m. in the Public Works Training Room. The public hearing is scheduled for November 20.

November 9, 2017

2017-101 PMP Street Improvement Project
Knox Area – Phase 2 (Street Segments West of Knox Avenue including Knox Avenue, Haeg Drive, Haeg Circle, Valentine Terrace, W. 84th Street and W. 83rd Street)
Final paving and installation of the sod were completed early the week of November 6 and have substantially completed work in the area.  Punch list items still remain.

2018-101 PMP Street Improvement Project
Notices regarding the 2018 PMP Street Improvement Project have been mailed to all affected properties.  Public informational meetings are scheduled for November 13 at 2 p.m. and November 14 at 5:30 p.m. in the Public Works Training Room. The public hearing is scheduled for November 20.

November 3, 2017

2017-101 PMP Street Improvement Project
Knox Area – Phase 2 (Street Segments West of Knox Avenue including Knox Avenue, Haeg Drive, Haeg Circle, Valentine Terrace, W. 84th Street and W. 83rd Street)
Adjustment of utility structures in the roadway were completed late the week of October 30 ahead of the final paving, scheduled to begin on Friday, November 3 and continue into early the following week.  Final paving will substantially complete the work in the area with only punchlist items remaining

2018-101 PMP Street Improvement Project
Notices regarding the 2018 PMP Street Improvement Project have been mailed to all affected properties. Public informational meetings are scheduled for November 13 at 2:00 PM and November 14 at 5:30 PM in the Public Works Training Room. The public hearing is scheduled for November 20.

October 2017

October 27, 2017

2017-101 PMP Street Improvement Project
Knox Area – Phase 2 (Street Segments West of Knox Avenue including Knox Avenue, Haeg Drive, Haeg Circle, Valentine Terrace, West 84th Street and West 83rd Street)

Boulevard grading and installation of sod will continue into the week of October 30 and is expected to completed by week’s end barring inclement weather. Adjustment of utility structures are also expected to be completed ahead of the scheduled paving days at the end of the week and early the week of November 6, when the final layer of asphalt is expected to be completed.

October 20, 2017

2017-101 PMP Street Improvement Project
Knox Area – Phase 1 (Street Segments East of Knox Avenue including W. 85th Street, W. 84th Street, Haeg Drive, W. 83rd Street, Irving Curve, Irving Avenue and Humboldt Avenue)
Paving of the final layer of asphalt for Phase 1 Streets was completed on October 16 and 17, substantially completing work for the listed street segments.  Additional items such spot restoration, erosion control and replacement tree plantings will follow during the week of October 23.  Rain garden plantings for the area are scheduled for Saturday, October 21. 

Knox Area – Phase 2 (Street Segments West of Knox Avenue including Knox Avenue, Haeg Drive, Haeg Circle, Valentine Terrace, W. 84th Street and W. 83rd Street)
Paving of the initial layer of asphalt for Phase 2 Streets was completed early the week of October 16 and will be followed by boulevard grading in preparation for sod restoration during the week of October 23.  Additionally, the adjustment of utility structures in roadways are scheduled for the week of October 23.  Rain garden plantings for the area are scheduled for Saturday, October 21.

October 13, 2017

2017-101 PMP Street Improvement Project
Knox Area – Phase 1 (Street Segments East of Knox Avenue including W. 85th Street, W. 84th Street, Haeg Drive, W. 83rd Street, Irving Curve, Irving Avenue and Humboldt Avenue)
Adjustment of utility structures is complete and paving of the final layer of asphalt is scheduled to complete early in the week of October 16. The remainder of sod installation is scheduled to complete the week of October 16.

Knox Area – Phase 2 (Street Segments West of Knox Avenue including Knox Avenue, Haeg Drive, Haeg Circle, Valentine Terrace, W. 84th Street and W. 83rd Street)
Fine grading of the aggregate rock base is complete and paving of the first layer of asphalt is scheduled to begin on Saturday, October 14 (weather permitting). The contractor has a noise exception to begin work at 7 a.m. Paving of asphalt driveways along with boulevard restoration will begin the week of October 16.

October 6, 2017

2017-101 PMP Street Improvement Project
On Monday, October 2, a public hearing was held at City Council to order the assessments for all areas on the project.

Knox Area – Phase 1 (Street Segments East of Knox Avenue including W. 85th Street, W. 84th Street, Haeg Drive, W. 83rd Street, Irving Curve, Irving Avenue and Humboldt Avenue)
Boulevard grading was completed late the week of October 2 and will be followed by sod restoration the week of October 9. The adjustment of utility structures will also take place the week of October 9 in anticipation of final paving tentatively schedule for the week of October 16.

Knox Area – Phase 2 (Street Segments West of Knox Avenue including Knox Avenue, Haeg Drive, Haeg Circle, Valentine Terrace, W. 84th Street and W. 83rd Street)
Installation of concrete curb and gutter was completed the week of October 2, in addition to installation of concrete sidewalk and driveways. Excavation of rainwater gardens began late this week and will continue into the week of October 9. Fine grading of the aggregate rock base is expected to begin on Saturday, October 7 and will continue into the following week. Depending on weather in the upcoming days and availability of equipment and personnel, the initial layer of asphalt could be paved as early as October 11, this is subject to change due to the previously mentioned factors.

September 2017

September 29, 2017

2017-101 PMP Street Improvement Project
Informational meetings for the assessment of the 2017-101 PMP Street Improvement Project were held in the Bloomington Public Works Training Room on Tuesday, September 26th at 2:00 p.m. and 5:30 p.m. The public hearing for the entire project will be held on Monday, October 2.

Knox Area – Phase 1 (Street Segments East of Knox Avenue including W. 85th Street, W. 84th Street, Haeg Drive, W. 83rd Street, Irving Curve, Irving Avenue and Humboldt Avenue)
Paving of asphalt driveways and boulevard grading have followed the initial layer of asphalt completed late the week of September 18. Additional boulevard work and adjustment of utility structures will take place the week of October 2nd in anticipation of sod installation and asphalt paving.

Knox Area – Phase 2 (Street Segments West of Knox Avenue including Knox Avenue, Haeg Drive, Haeg Circle, Valentine Terrace, W. 84th Street and W. 83rd Street)
Excavation of the existing road subgrade and installation of the aggregate rock base were completed late this week. Completion of the aggregate rock work was immediately followed by installation of concrete curb and gutter, the concrete work will carry into the week of October 2 and is expected to be completed late in the week, weather permitting.

2017-102 PMP Street Maintenance Project
Bloomington Ferry Road
(Pioneer Trail to 96th Street)
Seed and sod installation is complete. Final striping will complete by early October. Punch list work remains.

September 22, 2017

2017-101 PMP Street Improvement Project
Informational meetings for the assessment of the 2017-101 PMP Street Improvement Project will be held in the Bloomington Public Works Training Room on Tuesday, September 26 at 2:00 p.m. and 5:30 p.m. Residents may attend either meeting and are not required to attend both. Mailings for the meetings have been sent to the residents in the following areas.

Russell Area (Completed)

  • Russell Avenue from W. 108th Street to W. 106th Street
  • Queen Avenue from W. 108th Street to W. 106th Street
  • Queen Avenue from W. 106th Street to North Terminus
  • Queen Circle from Queen Avenue to West Terminus
  • W. 108th Street from Russell Avenue to Penn Avenue
  • W. 107th Street from Russell Avenue to Queen Avenue

Zenith Area (Completed)

  • Zenith Avenue from W. 110th Street to W. Old Shakopee Road
  • Abbott Avenue from W. 110th Street to W. 109th Street
  • Beard Avenue from W. 108th Street to W. Old Shakopee Road

Knox Area (In Progress)

  • Haeg Drive from W. 86th Street to Irving Avenue
  • Haeg Circle from Haeg Drive to East Terminus
  • Knox Avenue from W. 86th Street to W. 82nd Street
  • Irving Avenue from W. 85th Street to W. 83rd Street
  • Humboldt Avenue from W. 86th Street to W. 83rd Street
  • Valentine Terrace from Haeg Drive to Haeg Drive
  • W. 84th Street from Haeg Drive to Humboldt Avenue
  • W. 85th Street from Knox Avenue to Humboldt Avenue
  • Irving Curve from Knox Avenue to Irving Avenue
  • W. 83rd Street from Morgan Avenue to Humboldt Avenue

W. 80th Street Area (Completed)

  • W. 80th Street from American Boulevard to Thomas Avenue

Knox Area – Phase 1 (Street Segments East of Knox Avenue including W. 85th Street, W. 84th Street, Haeg Drive, W. 83rd Street, Irving Curve, Irving Avenue and Humboldt Avenue)
Fine grading of the aggregate rock base was completed early the week of September 18 in preparation for the paving of the initial layer of asphalt in Phase 1 areas. Paving will be followed by boulevard grading, asphalt driveway paving and adjustment of utility structures.

Knox Area – Phase 2 (Street Segments West of Knox Avenue including Knox Avenue, Haeg Drive, Haeg Circle, Valentine Terrace, W. 84th Street and W. 83rd Street)
Storm sewer installations were completed late the week of September 18 and will be followed by excavation of the existing road base, as well as the installation of the aggregate rock base on Knox Avenue. Excavation and rock aggregate base have been completed for other areas of Phase 2 streets in anticipation of concrete curb and gutter work scheduled to begin during the first week of October.

2017-102 PMP Street Maintenance Project
Heritage Hills Drive (Rich Road to France Avenue)
Sod installation is complete, punch list work remains.

Bloomington Ferry Road (Pioneer Trail to 96th Street)
Paving is complete and striping is scheduled to complete the week of September 25. Seed and sod installation is scheduled to complete the week of September 25.

September 15, 2017

2017-101 PMP Street Improvement Project
Knox Area – Phase 1 (Street Segments East of Knox Avenue including W. 85th Street, W. 84th Street, Haeg Drive, W. 83rd Street, Irving Curve, Irving Avenue and Humboldt Avenue)
Concrete curb and gutter for Phase 1 streets has been substantially completed and was followed by fine grading of the aggregate rock base late this week. Fine grading will continue through midweek of September 18 and will be followed by paving of the initial layer of asphalt. Additional concrete flat work was completed for concrete driveways and sidewalks.

Knox Area – Phase 2 (Street Segments West of Knox Avenue including Knox Avenue, Haeg Drive, Haeg Circle, Valentine Terrace, W. 84th Street and W. 83rd Street)
Storm sewer installations resumed this week and will continue into the week of September 18. Additional excavation of the existing road base and placement of the aggregate rock base will continue on Phase 2 streets.

2017-102 PMP Street Maintenance Project
Heritage Hills Drive (Rich Road to France Avenue)
Paving and striping are complete. Final sod installation is scheduled for the week of September 18.

Bloomington Ferry Road (Pioneer Trail to 96th Street)
Concrete work is complete. Milling of the northbound side is complete and due to some equipment issues, completion of the southbound side was delayed but is scheduled to complete on Saturday, September 16. The northbound side will be paved on Friday, September 15 with the southbound side paved on Monday, September 18 (weather permitting). Traffic will be switched to one side of the median and then the other with one lane in both directions as this paving is completed. Seed and sod installation is anticipated to occur the week of September 18 along with striping.

September 8, 2017

2017-101 PMP Street Improvement Project
Knox Area – Phase 1 (Street Segments East of Knox Avenue including W. 85th Street, W. 84th Street, Haeg Drive, W. 83rd Street, Irving Curve, Irving Avenue and Humboldt Avenue)
Installation of concrete curb and gutters began on September 7 and is anticipated to be completed early the week of September 11. Concrete work will continue on Saturday, September 9, for which the contractor has been granted a variance to begin work at 7 a.m. Installation of concrete driveways will follow late this week and be completed early the following week.

Knox Area – Phase 2 (Street Segments West of Knox Avenue including Knox Avenue, Haeg Drive, Haeg Circle, Valentine Terrace, W. 84th Street and W. 83rd Street)
Excavation of the existing road base and placement of the aggregate rock base continues and will follow further storm sewer installations. Installation of storm sewer pipe and manholes will resume on Tuesday, September 12 on the north end of Knox Avenue and will proceed south. Removal of driveways in the area was completed late this week.

2017-102 PMP Street Maintenance Project
Heritage Hills Drive (Rich Road to France Avenue)
Concrete replacement is complete. Boulevard restoration in preparation for sod is scheduled to complete late in the week of September 4. Milling is scheduled for Friday, September 8 followed by paving on Friday, September 8 and Saturday, September 9. Final sod installation and striping are scheduled for the week of September 11.

Bloomington Ferry Road (Pioneer Trail to 96th Street)
Concrete removal and replacement has started and is scheduled to complete early in the week of September 11. Boulevard restoration in preparation for sod/seed along with bituminous patching is scheduled for mid-week of September 11. Milling and paving is anticipated to occur late in the week of September 11 or the week of September 18.

September 1, 2017

2017-101 PMP Street Improvement Project
Knox Area – Phase 1 (Street Segments East of Knox Avenue including W. 85th Street, W. 84th Street, Haeg Drive, W. 83rd Street, Irving Curve, Irving Avenue and Humboldt Avenue)
Excavation of the existing road base and the placement of the rock aggregate base continued the week of August 28, and is scheduled to be completed on September 5. The excavation and base work will be followed by installation of concrete curb and gutter scheduled to begin shortly after the Labor Day holiday.

Knox Area – Phase 2 (Street Segments West of Knox Avenue including Knox Avenue, Haeg Drive, Haeg Circle, Valentine Terrace, W. 84th Street and W. 83rd Street)
Installation of storm sewer utilities began early the week of August 28 and is scheduled to be completed late the week of September 11. Removal of the existing pavement was completed for Phase 2 streets and will be followed by excavation and placement of the rock aggregate base.

2017-102 PMP Street Maintenance Project
93rd Street area 
(includes 93rd Street, 92nd Street, Vincent Avenue, Washburn Avenue)
Paving is complete and boulevard restoration is scheduled to complete early in the week of September 4.

Heritage Hills Drive (Rich Road to France Avenue)
Concrete replacement is anticipated to complete by the end of the week, which will be followed by bituminous patching. Boulevard restoration is scheduled for the week of September 4. Milling and paving are anticipated to occur late in the week of September 4 or the week of September 11.

Bloomington Ferry Road (Pioneer Trail to 96th Street)
Minor utility work along with concrete work are scheduled to begin the week of September 4. Utility adjustments and boulevard restoration will follow the week of September 11.

August 2017

August 25, 2017

2017-101 PMP Street Improvement Project
Zenith Area
(Zenith Avenue, Abbott Avenue, Beard Avenue)
Paving of the final layer of asphalt was completed earlier this week to substantially end work in the area. Installation of replacement trees will take place during the appropriate planting season in the fall. Punchlist items will remain.

W. 80th Street (from American Boulevard to Thomas Avenue)
Paving of the final layer of asphalt was completed earlier this week, as were the installation of sidewalk fencing and additional landscape work. Striping of the center median gore near the intersection of W. 80th Street and W. American Boulevard is expected to be completed early the week of August 28. Traffic control signs have been removed, and the road has been reopened completely to traffic.

Knox Area – Phase 1 (Street Segments East of Knox Avenue including W. 85th Street, W. 84th Street, Haeg Drive, W. 83rd Street, Irving Curve, Irving Avenue and Humboldt Avenue)
Installation of underground storm sewer pipe and structures continued this week and is scheduled to be completed early the week of August 28 in Phase 1 Streets, prior to proceeding to Phase 2 Streets.  Excavation of the existing road base, and placement of the rock aggregate base began this week in the southern portions of Phase 1 Streets and will proceed north, this work is scheduled to continue through the week of August 28.

Knox Area – Phase 2 (Street Segments West of Knox Avenue including Knox Avenue, Haeg Drive, Haeg Circle, Valentine Terrace, W. 84th Street and W. 83rd Street)
Removal of the existing asphalt took place late this week on Haeg Drive and Valentine Terrace, in anticipation of underground storm sewer installations scheduled to begin early the week of August 28. Storm sewer installations will begin near Haeg Drive and W. 86th Street and will proceed north through Haeg Drive, Haeg Circle and Valentine Terrace. Further removal of asphalt will take place late the week of August 28.

2017-102 PMP Street Maintenance Project
Humboldt Avenue area
(includes 100th Street, 102nd Street, Fremont Avenue, Emerson Avenue, Dupont Avenue, Colfax Avenue, Humboldt Avenue, 98 ½ Street, Girard Avenue, W 104th Street)
Sodding is complete and striping is anticipated to complete by early in the week of August 28.

93rd Street area (includes 93rd Street, 92nd Street, Vincent Avenue, Washburn Avenue)
Concrete replacement is complete, along with patching. Boulevard restoration and paving are anticipated to complete the week of August 28.

Heritage Hills Drive (Rich Road to France Avenue)
The remainder of the manhole adjustments, along with minor utility work, is scheduled to complete by the end of the week (weather permitting). Concrete removal has started and will continue the week of August 28, along with replacement of the concrete. Bituminous patching is anticipated to complete prior to Labor Day weekend. Boulevard restoration, milling and paving are scheduled to complete in early September.

Bloomington Ferry Road (Pioneer Trail to 96th Street)
Minor utility work along, with concrete removals, have been slightly delayed in this area and will begin after Labor Day.

August 18, 2017

2017-101 PMP Street Improvement Project
Zenith Area
(Zenith Avenue, Abbott Avenue, Beard Avenue)
Paving of the final layer of asphalt has been delayed due to inclement weather, and has been scheduled to occur early the week of August 21.

W. 80th Street (from American Boulevard to Thomas Avenue)
Excavation and infills of areas near the sound wall were completed the week of August 14, in anticipation of final paving, scheduled to be completed early the week of August 21. In addition to paving, a sidewalk fence is scheduled to be installed late the week of August 21.

Knox Area – Phase 1 (Street Segments East of Knox Avenue including W. 85th Street, W. 84th Street, Haeg Drive, W. 83rd Street, Irving Curve, Irving Avenue and Humboldt Avenue)
Installation of underground storm sewer pipe and structures began on W. 85th Street, and continued onto W. 84th Street east of Knox Avenue. Excavation of the existing soils and placement of the aggregate rock base is scheduled to begin Monday, August 21, and will follow areas where storm sewer installation has been completed.

2017-102 PMP Street Maintenance Project
Humboldt Avenue area
(includes 100th Street, 102nd Street, Fremont Avenue, Emerson Avenue, Dupont Avenue, Colfax Avenue, Humboldt Avenue, 98 ½ Street, Girard Avenue, W 104th Street)
Paving is complete and striping on 100th Street and 104th Street is scheduled for early in the week of August 21. Sodding has been slightly delayed and is scheduled to complete early in the week of August 21.

93rd Street area (includes 93rd Street, 92nd Street, Vincent Avenue, Washburn Avenue)
Milling is complete. Concrete removal and replacement has started and will complete early in the week of August 21. Boulevard restoration and paving are anticipated to complete by late in the week of August 21 (weather permitting).

Heritage Hills Drive (Rich Road to France Avenue)
The remainder of the manhole adjustments, along with minor utility work, is scheduled for the week of August 21. Concrete removal and replacement is anticipated to begin late in the week of August 21 and complete the week of August 28.

Bloomington Ferry Road (Pioneer Trail to 96th Street)
Minor utility work, along with concrete removals, are anticipated to begin the week of August 28 in this area.

August 11, 2017

2017-101 PMP Street Improvement Project
Russell Ave area (Russell Avenue, Queen Avenue, Queen Circle, W. 108th Street, W. 107th Street)
The final layer of asphalt for the area has been paved to substantially complete reconstruction of the roads in the area. Tree replacement has been scheduled to occur during the appropriate planting season in the fall. Punchlist items remain.

Zenith Ave area (Zenith Avenue, Abbott Avenue, Beard Avenue)
Sod restoration and adjustment of utility structures will have been completed late the week of August 7th in anticipation of final paving, tentatively scheduled to occur late the week of August 14 or early the following week.

W. 80th St (from American Boulevard to Thomas Avenue)
Sod restoration and adjustment of utility structures will have been completed late the week of August 7th in anticipation of final paving, tentatively scheduled late the week of August 14 or early the following week. Excavation and infills of areas near the sound wall also began and will continue into the week of August 14th.

Knox Ave area – Phase 1 (Street Segments East of Knox Avenue including W. 85th Street, W. 84th Street, Haeg Drive, W. 83rd Street, Irving Curve, Irving Avenue and Humboldt Avenue)
Removal of the existing pavement will be completed by weeks end and will be followed by underground utility work on phase one streets. Other removals including trees, concrete and driveway removals that will continue into the week of August 14th.

2017-102 PMP Street Maintenance Project
Humboldt Avenue area (includes 100th Street, 102nd Street, Fremont Avenue, Emerson Avenue, Dupont Avenue, Colfax Avenue, Humboldt Avenue, 98 ½ Street, Girard Avenue, W 104th Street)
Concrete work is complete and bituminous patching will complete this week.  Boulevard restoration has started and will complete early in the week of August 14.  Milling and paving of the area is scheduled for the week of August 14.

93rd Street area (includes 93rd Street, 92nd Street, Vincent Avenue, Washburn Avenue)
Manhole adjustments are scheduled to complete this week.  Milling of the area along with concrete removal and replacement is scheduled for the week of August 14.  Boulevard restoration and paving are anticipated to occur the week of August 21.

Heritage Hills Drive (Rich Road to France Avenue)
Clearing of trees in advance of construction are anticipated to complete this week.  Manhole adjustments are anticipated to begin the week of August 14.  Minor utility work along with concrete removals are scheduled for the week of August 21.

August 4, 2017

2017-101 PMP Street Improvement Project
Russell Area
(Russell Avenue, Queen Avenue, Queen Circle, W. 108th Street, W. 107th Street)
With the restoration of the area having been completed, the final layer of asphalt has been scheduled to be paved early the week of August 7th.

Zenith Area (Zenith Avenue, Abbott Avenue, Beard Avenue)
Restoration work in the area continues with boulevard grading, top soil and sod installation currently in progress, following the completion of asphalt driveways.  The adjustment of underground utility structures will begin early the week of August 7th, in preparation for final paving.

W. 80th Street (from American Boulevard to Thomas Avenue)
Utility conflicts near the retaining wall required a modification to the fence post installations; fence installation is scheduled to be completed August 7th.  Additional restoration, adjustment of utility structures and installation of signs are also scheduled to be completed the week of August 7th.

Knox Area – Phase 1 (Street Segments East of Knox Avenue including: W. 85th Street, W. 84th Street, Haeg Drive, W. 83rd Street, Irving Curve, Irving Avenue and Humboldt Avenue)
Reconstruction of the Knox Area will be split into two phases to accommodate the size of the neighborhood. Phase 1 will include work on all streets in the area east of Knox Avenue, not including Knox Avenue. Phase 2 will include all streets west of Knox Avenue, including Knox Avenue. Moving forward the updates will be provided for each phase separately.

Removal work is scheduled to begin in Phase 1 of the Knox Area the week of August 7th and will include pavement, driveway and tree removals. Installation of underground storm sewer is also expected to begin later the same week.

2017-102 PMP Street Maintenance Project
Humboldt Avenue area
(includes 100th Street, 102nd Street, Fremont Avenue, Emerson Avenue, Dupont Avenue, Colfax Avenue, Humboldt Avenue, 98 ½ Street, Girard Avenue, W 104th Street)
Concrete removal and replacement is complete on all streets except for 104th Street and 100th Street. Concrete work on those streets is scheduled for early in the week of August 7. Boulevard restoration has started and will continue late in the week of August 7. Milling and paving of the area is anticipated to occur the week of August 14 (weather permitting).

93rd Street area (includes 93rd Street, 92nd Street, Vincent Avenue, Washburn Avenue)
The MCES Interceptor Project and CenterPoint Energy gas main replacement projects are complete in the area, excluding some minor restoration. Minor underground utility work along with manhole adjustments as part of the 2017-102 PMP project are scheduled for the week of August 7. Concrete removal and replacement is anticipated to occur the week of August 14.

Heritage Hills Drive (Rich Road to France Avenue)
This area is anticipated to begin with minor utility work and tree removal late in the week of August 14 or the week of August 21.

July 2017

July 28, 2017

2017-101 PMP Street Improvement Project
Russell Area
(Russell Avenue, Queen Avenue, Queen Circle, W. 108th Street, W. 107th Street)
Sod restoration delays have been addressed and will be completed early next week.

Zenith Area (Zenith Avenue, Abbott Avenue, Beard Avenue)
Earlier this week, the initial layer of asphalt was completed for all streets in the area as was the remaining concrete work in the area. The adjustment of utility structures within the roadway, boulevard grading and paving of asphalt driveways are schedule to take place next week.

W. 80th Street (from American Boulevard to Thomas Avenue)
Construction of a retaining wall and concrete work for the area were completed this week in anticipation of the initial layer of asphalt scheduled to be paved early next week. The paving will be followed by installation of a fence adjacent to the retaining wall and restoration of boulevard areas.

2017-102 PMP Street Maintenance Project
94th Street
(West Bloomington Freeway to Lyndale Avenue)
Paving and boulevard restoration is complete. Striping is scheduled to complete by the end of the week.

Humboldt Avenue area (includes 100th Street, 102nd Street, Fremont Avenue, Emerson Avenue, Dupont Avenue, Colfax Avenue, Humboldt Avenue, 98 ½ Street, Girard Avenue, W 104th Street)
Concrete removal and replacement has started and will continue the week of July 31. Boulevard restoration will follow concrete work late in the week of July 31 and the week of August 7.

93rd Street area (includes 93rd Street, 92nd Street, Vincent Avenue, Washburn Avenue)
The current projects in this area, which include the MCES Interceptor Project and CenterPoint Energy gas main replacement, are currently finishing restoration. The 2017-102 PMP Project is anticipated to begin in this area late in the week of July 31 with minor underground utility work.

July 21, 2017

2017-101 PMP Street Improvement Project
Russell Area
(Russell Avenue, Queen Avenue, Queen Circle, W. 108th Street, W. 107th Street)
Weather and restoration delays will require that final paving for the area be rescheduled for the week of July 30th.

Zenith Area (Zenith Avenue, Abbott Avenue, Beard Avenue)
Fine grading of the rock aggregate base and concrete work are to be completed by week’s end, in preparation for paving the first layer of asphalt early next week. Paving will be followed by restoration of asphalt driveways and boulevard grading behind the curb.

W. 80th Street (from American Boulevard to Thomas Avenue)
Removal of existing sidewalk and a retaining wall were completed this week along with underground storm sewer work. Excavation and placement of the rock aggregate base will also be completed by the end of the week ahead of concrete work and the reconstruction of the retaining wall; both are scheduled for next week.

2017-102 PMP Street Maintenance Project
94th Street (West Bloomington Freeway to Lyndale Avenue)

  • Milling and paving is scheduled for Friday, July 21 and Saturday, July 22 (weather permitting). The Contractor is approved to begin work at 6:00 am on Saturday, July 22.
  • Striping and final sodding is scheduled for early in the week of July 24.

Humboldt Avenue area (includes 100th Street, 102nd Street, Fremont Avenue, Emerson Avenue, Dupont Avenue, Colfax Avenue, Humboldt Avenue, 98 ½ Street, Girard Avenue, W 104th Street)

  • Minor utility work and manhole reconstruction is anticipated to complete by early in the week of July 24.
  • Concrete removal and replacement is scheduled for the week of July 24.
  • Boulevard restoration will follow concrete work the week of July 31.

July 14, 2017

2017-101 PMP Street Improvement Project
Russell Area
(Russell Avenue, Queen Avenue, Queen Circle, W. 108th Street, W. 107th Street)
Boulevard grading and the adjustment of existing structures began this week and will be followed by sod restoration to be completed early next week. Paving of the top layer of asphalt is tentatively scheduled to take place during the week of July 24th.

Zenith Area (Zenith Avenue, Abbott Avenue, Beard Avenue)
Construction of a retaining wall and a significant portion of the concrete work were completed this week. Fine grading of the rock aggregate base and concrete work will continue into next week. Paving of the base layer of asphalt is scheduled for the week of July 24th.

W. 80th Street (from American Boulevard to Thomas Avenue)
Work is scheduled to begin on W. 80th Street on Wednesday, July 19 and will involve removal of existing concrete items and will be followed by storm sewer work and excavation the following days. Work on W. 80th Street will require a closure of between Thomas and American Boulevard, however local access for residents on W. 80th Street and Washburn Circle will be maintained.

2017-102 PMP Street Maintenance Project
94th Street
(West Bloomington Freeway to Lyndale Avenue)

  • Concrete removal and replacement is complete.
  • Utility adjustments and boulevard restoration is scheduled for early in the week of July 17.
  • Milling and paving is scheduled for late in the week of July 17 (weather permitting).

Humboldt Avenue area (includes 100th Street, 102nd Street, Fremont Avenue, Emerson Avenue, Dupont Avenue, Colfax Avenue, Humboldt Avenue, 98 ½ Street, Girard Avenue, W 104th Street)

  • Minor utility work and manhole reconstruction is scheduled for the week of July 17.
  • Concrete removal and replacement is scheduled for the week of July 24.

July 7, 2017

2017-101 PMP Street Improvement Project
Russell Area (Russell Avenue, Queen Avenue, Queen Circle, W. 108th Street, W. 107th Street)
Paving of the base layer of asphalt was completed this week and will be followed by boulevard restoration and the adjustment of underground structures scheduled for next week.

Zenith Area (Zenith Avenue, Abbott Avenue, Beard Avenue)
Excavation of Zenith Avenue and the installation of the rock aggregate base will be completed late this week before the excavation and base work continues onto Beard Avenue. Excavation of Beard Avenue is expected to be completed early next week in anticipation of concrete work in the area that will also take place next week on all streets in the area. Work on Zenith Avenue and Beard Avenue will be coordinated with a planned Hennepin County Maintenance project that includes a mill and overlay of Old Shakopee Road (CSAH 1) between France Avenue (CSAH 17) and Logan Avenue.

2017-102 PMP Street Maintenance Project
86th Street (Nicollet Avenue to Portland Avenue)
Paving is complete and striping is scheduled to complete by the end of the week.

94th Street (West Bloomington Freeway to Lyndale Avenue)
Concrete removal and replacement is scheduled to begin early in the week of July 10 which will be followed by manhole reconstruction and utility adjustments.

Humboldt Avenue area (includes 100th Street, 102nd Street, Fremont Avenue, Emerson Avenue, Dupont Avenue, Colfax Avenue, Humboldt Avenue, 98 ½ Street, Girard Avenue, W 104th Street)
Minor utility work, manhole reconstruction and concrete removal are anticipated to begin in this area late in the week of July 10.

June 2017

June 30, 2017

2017-101 PMP Street Improvement Project
Russell Area
(Russell Avenue, Queen Avenue, Queen Circle, W. 108th Street, W. 107th Street)
Fine grading of the rock aggregate base was completed this week in anticipation of paving to begin next week after the Fourth of July holiday, the base layer of asphalt will be followed by the adjustment of underground structures and the beginning of boulevard restoration.

Zenith Area (Zenith Avenue, Abbott Avenue, Beard Avenue)
Excavation of the existing base and placement of the rock aggregate base was completed on Abbott Avenue and began on Zenith Avenue. Excavation work will continue on Zenith Avenue after the holiday and will then proceed to Beard Avenue. Concrete work will follow the excavation and base work for each street segment.

2017-102 PMP Street Maintenance Project
86th Street
(Nicollet Avenue to Portland Avenue)
Paving is scheduled to complete on Friday, June 30 if weather allows, otherwise it will be completed on Saturday, July 1. Striping is scheduled for late in the week of July 3.

Chicago Avenue (86th Street to North Terminus)
Paving is scheduled to complete on Friday, June 30 if weather allows, otherwise it will be completed on Saturday, July 1.

94th Street (West Bloomington Freeway to Lyndale Avenue)
Concrete removal and replacement is anticipated to begin early in the week of July 10.

Humboldt Avenue area (includes 100th Street, 102nd Street, Fremont Avenue, Emerson Avenue, Dupont Avenue, Colfax Avenue, Humboldt Avenue, 98 ½ Street, Girard Avenue, W 104th Street)
Minor utility work along with concrete removal and replacement is anticipated to begin the week of July 10.

June 23, 2017

2017-101 PMP Street Improvement Project
Russell Area
(Russell Avenue, Queen Avenue, Queen Circle, W. 108th Street, W. 107th Street)
Excavation and placement of the aggregate rock base is expected to be completed by the end of this week. Concrete curb and gutter work in the area was also completed and will be followed by additional concrete flat work next week. The shaping of the aggregate base to reflect the proposed roadways is scheduled for the middle of next week.

Zenith Area (Zenith Avenue, Abbott Avenue, Beard Avenue)
Underground storm sewer installation in the Zenith area was completed by week’s end, and will be followed by the excavation of the existing road base and replaced with the aggregate rock base next week.

2017-102 PMP Street Maintenance Project
86th Street (Nicollet Avenue to Portland Avenue)

  • Milling, final adjustments of manholes and paving is scheduled for the week of June 26.
  • Striping is scheduled for the week of July 3.

Chicago Avenue (86th Street to North Terminus)
Milling and paving is scheduled for the week of June 26.

94th Street (West Bloomington Freeway to Lyndale Avenue)

  • The Contractor has delayed the concrete removal and replacement in this area to allow for restoration from private utility work to complete.
  • Concrete removal and replacement is anticipated to begin late in the week of July 3.

Humboldt Avenue Area (includes 100th Street, 102nd Street, Fremont Avenue, Emerson Avenue, Dupont Avenue, Colfax Avenue, Humboldt Avenue, 98 ½ Street, Girard Avenue, W 104th Street)
Mailings have been sent to affected residents and the Contractor anticipates starting in this area in early-mid July.

June 16, 2017

2017-101 PMP Street Improvement Project
Russell Area
(Russell Avenue, Queen Avenue, Queen Circle, W. 108th Street, W. 107th Street)
For the majority of the neighborhood, excluding W. 108th Street, has been excavated and followed by the placement of the rock aggregate base. Excavation of W. 108th Street will take place Monday morning. Concrete crews will be in the area beginning Monday, working to install curb and gutter as well as concrete sidewalk and driveways. Tree removals in the area will be completed early next week.

Zenith Area (Zenith Avenue, Abbott Avenue, Beard Avenue)
The underground utility contractor began their work earlier this week and completed work on Beard and Abbott Avenue, they will continue their work on Zenith Avenue into next week. Upon completion of the storm sewer installation, the contractor will work to excavate the area and place the rock aggregate base. Tree removals in the area will be completed early next week.

2017-102 PMP Street Maintenance Project
82nd Street (24th Avenue to 28th Avenue), 26th Avenue (Lindau Lane to 82nd Street)
The remaining items to be installed include the Rectangular Rapid Flashing Beacon (RRFB) system, pedestrian lights on 26th Avenue and new light poles on 82nd Street and 26th Avenue. These items will be installed upon delivery either by late June-early July or will not installed until late July-early August after the X-games event is complete in the area.

86th Street (Nicollet Avenue to Portland Avenue)

  • Traffic is currently switched to the outer lanes while utility adjustments are completed in the center lane.
  • Boulevard restoration is scheduled for the week of June 19 and lane closures will be moved as work completes on both sides of 86th Street.
  • Milling and paving is scheduled for the week of June 26.

Chicago Avenue (86th Street to North Terminus)

  • Concrete replacement is scheduled to complete by the end of the week.
  • Reconstruction of the segment of Chicago Avenue between 83rd Street and Smith Park will complete by early in the week of June 19.
  • Boulevard restoration is scheduled for the week of June 19, with milling and paving to follow the week of June 26.

94th Street (West Bloomington Freeway to Lyndale Avenue)

  • CenterPoint Energy will complete restoration early in the week of June 19.
  • The Contractor is scheduled to begin concrete removal and replacement on the 2017-102 project on Wed, June 21.

Vincent Area (includes Vincent Avenue, Washburn Avenue, 92nd Street, 93rd Street)
CenterPoint Energy is scheduled to begin gas main and service replacement in this area the week of June 19, which is anticipated to take 3 weeks to complete.

June 9, 2017

2017-101 PMP Street Improvement Project
Russell Area
(Russell Avenue, Queen Avenue, Queen Circle, W. 108th Street, W. 107th Street)
Removal of the existing asphalt was completed this week as well as the underground storm sewer work at current catch basin locations. Excavation and placement of the aggregate base is scheduled for early next week in preparation for concrete curb and gutter work scheduled for mid-week. Concrete work will include construction of the new curb and gutter on Russell Avenue from W. 108th Street to just south of W. 107th Street, spot curb replacement will also occur in areas with existing curb and gutter. Removal of boulevard trees is scheduled for Monday morning ahead of the excavation work beginning on Queen Avenue.

Zenith Area (Zenith Avenue, Abbott Avenue, Beard Avenue)
Removal of the existing asphalt was completed this week and will be followed by underground storm sewer work scheduled to begin on Beard Avenue by mid-week and will be followed by similar work on Abbott Avenue. Removal of boulevard trees is scheduled for Monday morning.

2017-102 PMP Street Maintenance Project
82nd Street (24th Avenue to 28th Avenue), 26th Avenue (Lindau Lane to 82nd Street)

  • Milling and paving of the area is complete
  • Tinting (staining) and sealing all of the existing red colored and stamped concrete to a charcoal grey color is scheduled to complete by early in the week of June 12.
  • Sod installation is scheduled for June 12 following by striping of the pavement later in the week.
  • Installation of a lighting cabinet on 82nd Street is scheduled for the week of June 12 and installation of the new light poles will occur after they are delivered later in the summer.
  • Installation of the new Rectangular Rapid Flashing Beacon (RRFB) system at the crossing of 82nd Street at 26th Avenue will be installed upon delivery in late June.

80th Street (Bloomington Avenue to 17th Avenue), Bloomington Avenue (80th Street to 80th Street)

  • Concrete work is complete.
  • Restoration of the boulevards is scheduled to complete early in the week of June 12.

86th Street (Nicollet Avenue to Portland Avenue)

  • Concrete work (including curb, sidewalk and pedestrian ramp replacement) along with utility adjustments are complete on the south side of 86th Street (east bound lane).
  • Concrete work (including curb, sidewalk and pedestrian ramp replacement) along with utility adjustments on the north side (west bound lane) have started and will complete mid-week of June 12.
  • Traffic will be switched to the outer lanes late in the week of June 12 to allow for completion of utility adjustments in the center lane.
  • Boulevard restoration, milling and paving are anticipated to begin the week of June 19.

Old Cedar Avenue (86th Street to 82nd Street)

  • Milling and paving is complete. Sod installation and striping are scheduled for the week of June 12.

Chicago Avenue (86th Street to North Terminus)

  • Concrete replacement is scheduled for the week of June 12 along with the remainder of the minor utility work.
  • Reconstruction of the segment of Chicago Avenue between 83rd Street and Smith Park is anticipated to occur late in the week of June 12.
  • Boulevard restoration will follow the week of June 19.

94th Street (West Bloomington Freeway to Lyndale Avenue)

  • CenterPoint Energy has started gas main and service replacement in this area and anticipates completion by late in the week of June 12.
  • The Contractor anticipates starting removals in this area the week of June 19.

June 2, 2017

2017-101 PMP Street Improvement Project
A preconstruction meeting was held on Wednesday, May 31st in preparation for the start of construction. Construction is scheduled begin next week in the Russell Avenue and Zenith Avenue Areas pending the contractor receiving their Notice to Proceed.

2017-102 PMP Street Maintenance Project
82nd Street
(24th Avenue to 28th Avenue), 26th Avenue (Lindau Lane to 82nd Street)
The Contractor anticipates completing tinting (staining) and sealing all of the existing red colored and stamped concrete to a charcoal grey color, by early in the week of June 5. Milling of this area is scheduled to begin on Tuesday, June 6, which will be followed by paving later in the week. Boulevard restoration has started and final placement of sod in the area will complete after paving is complete. Median plantings will be installed late in the week of May 29.

80th Street (Bloomington Avenue to 17th Avenue), Bloomington Avenue (80th Street to 80th Street)
The second half of driveway entrances are scheduled to be installed late in the week of May 29. Boulevard restoration has started and will continue the week of June 5.

86th Street (Nicollet Avenue to Portland Avenue)
Minor utility work on the south side of 86th Street is complete. Concrete removal and replacement on the south side is anticipated to complete by early in the week of June 5. Work will then shift to the north side of 86th Street mid-week of June 5. Concrete removal and replacement along with minor utility work will begin later in the week on the north side.

Old Cedar Avenue (86th Street to 82nd Street)
Boulevard restoration is scheduled to complete by the end of the week of May 29. Milling is scheduled to begin Tuesday, June 6, which will be followed by paving later in the week.

Chicago Avenue (86th Street to North Terminus)
Minor utility work has started and will complete the week of June 5. Reconstruction of the area between 83rd Street and Smith Park will begin later in the week of June 5 along with concrete removal in the remainder of the area.

May 2017

May 26, 2017

2017-101 PMP Street Improvement Project
A preconstruction meeting is scheduled for Wednesday, May 31st in anticipation of work scheduled to begin the following days on June 1st or 2nd. A construction newsletter with project contacts has been mailed to residents of the neighborhoods where construction is expected to begin. Initial work is schedule to begin on the Zenith and Russell Avenue Areas detailed below:

Zenith Avenue Area
Zenith Avenue from W. 110th Street to W. Old Shakopee Road
Abbott Avenue from W. 110th Street to W. 109th Street
Beard Avenue from W. 108th Street to W. Old Shakopee Road

Russell Avenue Area
Russell Avenue from W. 108th Street to W. 106th Street
Queen Avenue from W. 108th Street to W. 106th Street
Queen Avenue from W. 106th Street to North Terminus
W. 108th Street from Russell Avenue to Penn Avenue
W. 107th Street from Russell Avenue to Queen Avenue
Queen Circle from Queen Avenue to West Terminus

2017-102 PMP Street Maintenance Project
82nd Street (24th Avenue to 28th Avenue), 26th Avenue (Lindau Lane to 82nd Street)
Concrete removal and replacement is complete. Boulevard restoration is scheduled to begin the week of May 29. The Contractor will also begin tinting (staining) and sealing all of the existing red colored and stamped concrete to a charcoal grey color, along 82nd Street between 24th Avenue and 26th Avenue the week of May 29. The new color will attempt to match that of the South Loop charcoal grey color, without having to remove and replace all existing red colored concrete. Milling and paving of this area is anticipated to occur the week of June 5.

80th Street (Bloomington Avenue to 17th Avenue), Bloomington Avenue (80th Street to 80th Street)
Sidewalk installation is complete and one half of all driveway entrances have been installed. The other half of the driveway entrances will be installed later in the week of May 29. This will be followed by boulevard restoration.

86th Street (Nicollet Avenue to Portland Avenue)
The Contractor will begin work in this area the week of May 29. Minor utility work including the removal and replacement of a hydrant will occur on Tuesday, May 30. Concrete removal and replacement on the south side of road will start the week of May 29 and continue for 1-2 weeks.

Old Cedar Avenue (86th Street to 82nd Street)
Concrete removal and replacement is complete. Boulevard restoration is anticipated to occur the week of May 29, which will be followed by milling and paving the week of June 5.

Chicago Avenue (86th Street to North Terminus)
CenterPoint Energy anticipates completing work in this area the week of May 29. Concrete removal and minor utility work is scheduled to begin the week of May 29.

94th Street (West Bloomington Freeway to Lyndale Avenue)
CenterPoint Energy is scheduled to start gas main removal and replacement in this are the week of May 29 and anticipated completing by mid-june

May 19, 2017

2017-102 PMP Street Maintenance Project
82nd Street (24th Avenue to 28th Avenue), 26th Avenue (Lindau Lane to 82nd Street)
Placement of topsoil in the median has been delayed due to weather and is scheduled to complete the week of May 22. Concrete removal and replacement continues and is anticipated to complete the week of May 22 (weather permitting), which will be followed by boulevard restoration. Electrical work for light pole installation on 82nd Street and 26th Avenue along with work at the signal system at 24th Avenue and 82nd Street will continue the week of May 22.

80th Street (Bloomington Avenue to 17th Avenue), Bloomington Avenue (80th Street to 80th Street)
Installation of the walk has been slightly delayed due to weather and is anticipated to occur the week of May 22 (weather permitting).

Old Cedar Avenue (86th Street to 80th Street)
Concrete removal and replacement has been slightly delayed due to weather and is anticipated to occur the week of May 22 (weather permitting).

Chicago Avenue (86th Street to North Terminus)
CenterPoint Energy continues gas main and service replacement in this area and is anticipated to complete by late May.

86th Street (Nicollet Avenue to Portland Avenue)
The Contractor anticipates starting removals in this area the week of May 29.

May 12, 2017

2017-102 PMP Street Maintenance Project
82nd Street (24th Avenue to 28th Avenue), 26th Avenue (Lindau Lane to 82nd Street)
Excavation of the median is complete and topsoil will be placed the week of May 15. Concrete removal and replacement has started and will continue the week of May 15. Electrical work for light pole installation on 82nd Street and 26th Avenue along with work at the signal system at 24th Avenue and 82nd Street will continue the week of May 15.

80th Street (Bloomington Avenue to 17th Avenue), Bloomington Avenue (80th Street to 80th Street)
Excavation for the new sidewalk has started and installation of the walk is anticipated to begin late in the week of May 15, weather permitting.

Old Cedar Avenue (86th Street to 80th Street)
Minor manhole reconstruction was completed this week. Concrete removal and replacement is anticipated to begin late in the week of May 15 or the week of May 22.

Chicago Avenue (86th Street to North Terminus)
CenterPoint Energy has started gas main replacement in this area which is anticipated to take 2-3 weeks to complete. The street maintenance project will start in this area after gas main work is complete.

Humboldt Avenue area (including 100th Street, 102nd Street, Fremont Avenue, Emerson Avenue, Dupont Avenue, Colfax Avenue, Humboldt Avenue, 98 ½ Street, Girard Avenue)
CenterPoint Energy is currently replacing gas main and services in this area which in anticipated to take 6-8 weeks to complete. The street maintenance project will start in this area after gas main work is complete.

May 5, 2017

2017-110 PMP Trail Improvement Project
Construction is scheduled to begin Monday, May 8 at the Collegeview Road Trail site. Later in the week, construction is scheduled to begin at the West Bush Lake Road Trail site.  Preliminary erosion control work has occurred this week in anticipation of removal and grading work scheduled for next week.

2017-102 PMP Street Maintenance Project
82nd Street (24th Avenue to 28th Avenue), 26th Avenue (Lindau Lane to 82nd Street)
Tree clearing and grubbing is complete in the median on 82nd Street. Excavation of the median on 82nd Street for the installation of a bio-retention basin has started and will continue the week of May 8. Minor storm sewer work, concrete removals and work on the signal system at 82nd Street and 24th Avenue are scheduled to begin the week of May 8. Concrete replacement is anticipated to begin late in the week of May 8.

80th Street (Bloomington Avenue to 17th Avenue), Bloomington Avenue (80th Street to 80th Street)
Tree clearing and grubbing is complete on this site. Excavation and installation of new sidewalk will begin in the coming weeks.

April 2017

April 28, 2017

2017-102 PMP Street Maintenance Project

The Pre Construction Conference is scheduled for the week of May 1 and the Contractor anticipates starting in the area that includes 82nd Street from 24th Avenue to 28th Avenue and 26th Avenue from Lindau Lane to 82nd Street late in the week of May 1.

April 21, 2017

2017-102 PMP Street Maintenance Project

A Pre Construction Meeting has been scheduled for the week of May 1.  Construction is anticipated to begin in early May, more information will be given when a schedule is determined.

February 2017

February 23, 2017

2017-102 PMP Street Maintenance Project
Mailings have been sent out to all properties adjacent to the 2017-102 PMP Street Maintenance Project informing them that the adjacent street has been selected as part of the overlay project.  Additional mailings will be sent out a week or two in advance of construction beginning in each particular neighborhood, giving more information on the construction along with both City and Contractor contact information.
One of the neighborhoods on this project includes portions of Fremont, Emerson, Dupont and Colfax Avenue between W. 102nd Street and W. 100th Street along with W. 102nd Street and W. 104th Street, which are directly adjacent to W. Bloomington Freeway.  A few residents have called or emailed staff since the mailings went out, regarding the status of W. Bloomington Freeway between W. 104th Street and W. 106th Street, which is not included as part of the 2017-102 Project.  This section of roadway is currently in poor condition and on the 5 year map for a full reconstruction, which would include new curb and gutter and a complete street reconstruction.  This section of roadway is within MnDOT ROW, and City and MnDOT staff will be working together on the replacement.  In addition, with the I-35W bridge over the MN River scheduled for replacement by MnDOT within the next 5 years, this construction work may have minor impacts on the W 106th Street intersection of I-35W, which would also impact W Bloomington Freeway. Given the need to coordinate with MnDOT on these items, staff didn’t want to miss the window to preserve the pavement in the neighborhood adjacent to W Bloomington Freeway at a lower cost than a reconstruct and included it in this year’s maintenance project.  Bloomington maintenance staff will continue to maintain and patch W. Bloomington Freeway until reconstruction occurs as per the agreement with MnDOT.

November 2016

November 18, 2016

2016-102 PMP Street Maintenance Project

Lyndale Avenue (from W. 94th Street to W. 86th Street)
The signal at the W. 94th Street intersection has been restored to working order and is fully operational.  The signal at the W. 86th Street intersection has been turned on and is operating under recall timing prior to the video detection set up scheduled to take place Monday, November 21.

November 11, 2016

2016-101 PMP Street Improvement Project

Lyndale Avenue (from W. 94th Street to W. 86th Street)
Striping of Lyndale Avenue was completed early this week ahead of ground-in pavement messages and crosswalks scheduled to be completed late this week.  The signal at W. 86th Street was not turned on this week due to complications with connecting the signal to power.  Xcel Energy will address the issue in the coming days.  The signal at W. 90th Street has been restored to working order.  The W. 94th Street signal work continues.

2017-101 PMP Street Improvement Project

A public hearing was held in the council chambers at City Hall on Monday, November 7, 2016.  At the public hearing council approved the 2017-101 Feasibility Study and adopted the resolution to order all streets for construction, including all benefitting properties in a special assessment.

November 4, 2016

2016-102 PMP Street Maintenance Project
Lyndale Avenue (from W. 94th Street to W. 86th Street)
Milling of Lyndale Avenue was completed on Tuesday, November 1st and was followed by paving on Wednesday and Thursday, November 2nd and 3rd.  Striping and installation of pavement messages are scheduled for early next week.  Traffic signal work at W 94th Street will continue; the signal at W 86th Street is scheduled to be turned on next week.

2017-101 PMP Street Improvement Project
A public hearing will be held in the council chambers at City Hall on Monday, November 7, 2016.

2016-101 PMP Street Improvement Project
Washburn Area (includes Washburn Avenue, Vincent Avenue, Thomas Avenue, Sheridan Avenue, Russell Avenue, Queen Avenue, 87th Street, 87 ½ Street)
Paving and sod installation is complete.  Punch list work remains.

October 2016

October 28, 2016

2016-101 PMP Street Improvement Project
Washburn Area (includes Washburn Avenue, Vincent Avenue, Thomas Avenue, Sheridan Avenue, Russell Avenue, Queen Avenue, 87th Street, 87 ½ Street)

Paving of the final layer of bituminous is complete in the entire area.  Sod installation was slightly delayed due to the recent rain and wet conditions.  It is anticipated to complete in the area the week of October 31.

2016-102 PMP Street Maintenance Project

Lyndale Avenue (from W. 94th Street to W. 86th Street)
Concrete work and restoration of boulevard areas was completed this week in preparation for milling and paving scheduled to take place next week.  Milling is scheduled to take place next week on Monday and Tuesday, October 31st and November 1st.  Paving will follow on Wednesday and Thursday, November 2nd and November 3rd .  Signal poles and pedestrian push buttons have been installed, electrical wiring for those items will follow next week.  Pavement marking of Lyndale Avenue is scheduled to take place the week of November 7th .

October 21, 2016

2016-102 PMP Street Maintenance Project
Lyndale Avenue (from W. 94th Street to W. 86th Street)
Concrete work on Lyndale Avenue at the W. 94th and W. 86th intersections will be completed by early next week.  Boulevard restoration including hydro seed and sod will take place the week of Monday, October 24th.  Electrical contractors will work to finish installation of signal mast arms and wire pulling the week of October 24th.  Milling is currently scheduled for Monday and Tuesday of October 31st and November 1st, in advance of paving scheduled for Wednesday and Thursday, November 2nd and 3rd.

2017-101 PMP Street Improvement Project
Public informational meetings will be held next week on Monday, October 24, 2016 at 2:00 PM and 5:30 PM in the Public Works Training Room. The public hearing is scheduled for Monday, November 7, 2016.

2016-101 PMP Street Improvement Project
Washburn Area (includes Washburn Avenue, Vincent Avenue, Thomas Avenue, Sheridan Avenue, Russell Avenue, Queen Avenue, 87th Street, 87 ½ Street)
Raising of manholes and gate valves is complete in the entire area.  Boulevard restoration and sod installation is nearing completion and is anticipated to complete by early in the week of October 24, which may include work on Saturday, October 22.  Paving of the final layer of bituminous is scheduled to continue early in the week of October 24, weather permitting.

October 14, 2016

2016-101 PMP Street Improvement Project
Washburn Area (includes Washburn Avenue, Vincent Avenue, Thomas Avenue, Sheridan Avenue, Russell Avenue, Queen Avenue, 87th Street, 87 ½ Street)
The first layer of bituminous has been paved in the entire area.  Raising of manholes and gate valves in the entire area is scheduled to complete late in the week of October 10.  Boulevard restoration and sod installation will continue the week of October 17 and is anticipated to complete in the entire area by the end of the week.  Paving of the final layer of bituminous is complete on Queen Avenue and Russell Avenue and is anticipated to complete in the remainder of the area by early in the week of October 24.

Rain water gardens are complete and replacement trees have also been planted on the entire project.

2016-102 PMP Street Maintenance Project

Lyndale Avenue (from W. 94th Street to W. 86th Street)
Xcel Energy has completed their work of the underground electrical duct relocation at the W 94th Street intersection and will be followed by grading of the proposed turn lane next week.  Concrete will take place late next week and will be followed by lawn restoration of the boulevard areas.  Electrical contractors continue to work on the signal system at the W 94th Street intersection, having installed one of the signal poles the contractors will proceed to work in the areas now vacated by Xcel Energy.

Pillsbury Area (Pillsbury Avenue from W. 82nd Street to W. 81st Street and Wentworth Avenue from W. 82nd Street to W. 81st Street)
Paving of Pillsbury Avenue and Wentworth Avenue was completed earlier this week.

2017-101 PMP Street Improvement Project

Notices regarding the 2017 PMP Street Improvement Project have been mailed to all affected properties. Public informational meetings are scheduled for Monday, October 24, 2016 at 2:00 PM and 5:30 PM in the Public Works Training Room. The public hearing is scheduled for Monday, November 7, 2016.

October 7, 2016

2016-102 PMP Street Maintenance Project

Lyndale Avenue (from W. 94th Street to W. 86th Street)
Xcel Energy began work on the lowering of the electrical duct earlier this week and will continue working into next week.  They are expected to complete this work by late next week or early the following week.  Electrical contractors are currently raising steel signal poles at W. 86th Street and will work on the corresponding electrical wiring next week.  Concrete for the W. 94th Street turn lane island will follow as will restoration items such as irrigation repairs and boulevard stabilization.

Pillsbury Area (Pillsbury Avenue from W. 82nd Street to W. 81st Street and Wentworth Avenue from W. 82nd Street to W. 81st Street)
Milling of the Pillsbury and Wentworth Avenue took place earlier this week in preparation for paving scheduled to take place Monday, October 10th.

2016-101 PMP Street Improvement Project
Washburn Area (includes Washburn Avenue, Vincent Avenue, Thomas Avenue, Sheridan Avenue, Russell Avenue, Queen Avenue, 87th Street, 87 ½ Street)

Concrete installation is complete in the entire area.  The first layer of bituminous has been paved on all streets, except for Washburn Avenue, 87th Street and the remainder of 87 ½ Street between Vincent Avenue and Xerxes Avenue.  These remaining streets will have the first layer of bituminous paved early in the week of October 10.  Boulevard restoration, sod installation and raising of manholes and gate valves will continue to head west in the neighborhood the week of October 10.  The final layer of bituminous is scheduled to be paved early in the week of October 10 on Queen Avenue, Russell Avenue, Sheridan Avenue and a portion of 87 ½ Street.  The final layer of bituminous will be paved in the remainder of the neighborhood the week of October 17.

Rain water garden mulching is scheduled for the week of October 10 and tree planting on the entire project will occur in October.

September 2016

September 30, 2016

2016-102 PMP Street Maintenance Project

Lyndale Avenue (from W. 94th Street to W. 86th Street)
Xcel Energy will work to lower an existing electrical duct near the intersection of W. 94th Street and Lyndale Avenue beginning next week.  Traffic control at the W. 94th Street intersection will need to restrict westbound traffic and a detour will be provided. This work is expected to take three weeks and will be followed by restoration work and subsequent paving.

Pillsbury Area (Pillsbury Avenue from W. 82nd Street to W. 81st Street and Wentworth Avenue from W. 82nd Street to W. 81st Street)
Previous work in the area completed by private companies postponed the milling and paving of the area to a time when the area could be completed concurrently with another segment.  As a result milling and paving are scheduled to take place at the end of October.

2016-101 PMP Street Improvement Project

The public hearing to order the assessments for the project is scheduled for Monday, October 3.

Washburn Area (includes Washburn Avenue, Vincent Avenue, Thomas Avenue, Sheridan Avenue, Russell Avenue, Queen Avenue, 87th Street, 87 ½ Street)
Paving of the first layer of bituminous on Sheridan Avenue (cul-de-sac), Thomas Avenue, Vincent Avenue and 87 ½ St from Thomas Avenue to Vincent Avenue is scheduled for Saturday, October 1 (weather permitting).  Paving of bituminous driveways will follow on these streets the week of October 3.  Boulevard restoration and raising of manholes and gate valves continues on Queen Avenue and Russell Avenue and will continue to head west in the neighborhood the week of October 3.

Installation of curb and concrete driveways is nearly complete in the entire neighborhood and the balance of this work is anticipated to complete early in the week of October 3.  Fine grading of class 5 on Washburn Avenue, 87th Street and the remainder of 87 ½ Street is scheduled for early in the week of October 3.  Paving of the first layer of bituminous will follow on these streets and is anticipated to occur late in the week of October 3.  This will be followed by boulevard restoration the week of October 10 along with the paving of the remainder of bituminous driveways.

Rain water garden installation continues and the planting of the rain water gardens is anticipated to occur on October 8.

September 23, 2016

2016-102 PMP Street Maintenance Project
Lyndale Avenue (from W. 94th Street to W. 86th Street)
Underground electrical work for the traffic signal revision continues on Lyndale Avenue at the W. 86th Street intersection; work at the W. 94th Street intersection will resume following the relocation of an Xcel Energy electrical conduit.

W. 98th Street Retaining Wall (2620 W. 98th Street)
Concrete work was completed earlier this week and was followed by restoration of the asphalt driveways.  Additional top soil work will take place prior to completion of the fence, installation of landscaping and boulevard restoration.

 E. 98th Street School Cross Walk (Indian Mounds Elementary School)
Concrete work and restoration of the boulevard areas were completed earlier this week.  The grinding of the existing cross walk and painting of the new cross walk will follow.

September 23, 2016

2016-101 PMP Street Improvement Project
Assessment informational meetings are scheduled for Monday, September 26 at 2:00 PM and 5:30 PM in the Bloomington Public Works Training Room.  The public hearing is scheduled for Monday, October 3.  Mailings have been sent to affected property owners regarding these meetings.

Washburn Area (includes Washburn Avenue, Vincent Avenue, Thomas Avenue, Sheridan Avenue, Russell Avenue, Queen Avenue, 87th Street, 87 ½ Street)
Paving of the first layer of bituminous in the stage 1 area (including Queen Avenue, Russell Avenue, Sheridan Avenue and 87 ½ Street from Thomas Avenue to Queen Avenue) is complete, excluding the Sheridan Avenue cul-de-sac, which is anticipated to be paved late in the week of September 26, weather permitting.  Boulevard restoration and raising of manholes and gate valves will continue in the stage 1 area the week of September 26.  Rain water garden excavation will continue the week of September 26.  Planting of the rain water gardens is anticipated to occur on October 8.

Excavation and placement of class 5 is complete in the entire stage 2 area (including Thomas Avenue, Vincent Avenue, Washburn Avenue, 87th Street and 87 ½ Street from Vincent Avenue to Thomas Avenue).  Due to the recent rain, concrete installation has been slightly delayed and will continue on 87 ½ Street from Xerxes Avenue to Vincent Avenue along with Washburn Avenue and 87th Street early in the week of September 26.  Fine grading of class 5 in this area continues and will continue the week of September 26.  Paving of the first layer of bituminous is anticipated to begin in this area late in the week of September 26.

September 16, 2016

2016-102 PMP Street Maintenance Project
Lyndale Avenue (from W. 94th Street to W. 86th Street)
Traffic control in the area has been relocated to close the outside lanes of both the northbound and southbound lanes to allow for boulevard restoration and underground electrical work.    The west side sidewalk remains closed to pedestrians to allow for concrete work.

W. 98th Street Retaining Wall (2620 W. 98th Street)
The retaining wall at W. 98th Street was painted early this week to a more natural color and was subsequently graded in anticipation of concrete work to take place late this week.  Restoration of resident driveways will take place once the new concrete has properly cured and will be followed by landscaping work.

E. 98th Street School Cross Walk (Indian Mounds Elementary School)
Removals were completed earlier than expected and will accommodate concrete work scheduled for the week’s end, barring weather delays.  Restoration, including grinding and striping of a new crosswalk, will follow.

2016-101 PMP Street Improvement Project
85th Area (includes 85th Street, 1st Avenue)
Sod installation and paving of the final layer of bituminous are complete.  Punch list work remains.

Washburn Area (includes Washburn Avenue, Vincent Avenue, Thomas Avenue, Sheridan Avenue, Russell Avenue, Queen Avenue, 87th Street, 87 ½ Street)
Concrete curb and driveway installation is complete in the stage 1 area (including Queen Avenue, Russell Avenue, Sheridan Avenue and 87 ½ Street from Thomas Avenue to Queen Avenue).  Paving of the first layer of bituminous on Queen Avenue is complete.  Boulevard restoration and raising of manholes and gate valves are scheduled to begin on Queen Avenue the week of September 19.  Fine grading of class 5 on Russell Avenue, Sheridan Avenue and 87 ½ Street will continue late in the week of September 19 with paving of the first layer of bituminous to follow the week of September 26.  Rain water garden excavation will continue the week of September 19.

Storm sewer work in the stage 2 area is complete (including Thomas Avenue, Vincent Avenue, Washburn Avenue, 87th Street and 87 ½ Street from Vincent Avenue to Thomas Avenue).  Concrete installation will continue on 87 ½ Street from Xerxes Avenue to Vincent Avenue along with Washburn Avenue and 87th Street starting late in the week of September 19 and continuing into the week of September 26 after excavation and grading are complete.  Fine grading of class 5 on Thomas Avenue and Vincent Avenue is anticipated to begin late in the week of September 19.

September 9, 2016

2016-101 PMP Street Improvement Project
American Boulevard sidewalk (from Portland Avenue to Chicago Avenue)
Boulevard restoration is complete.  Installation of trees and shrubs will occur in the Fall.  Punch list work remains.

85th Area (includes 85th Street, 1st Avenue)
Final completion of this area has been delayed due to the recent rain.  Sod installation is anticipated to complete early in the week of September 12.  Paving of the final layer of bituminous will follow sod installation the week of September 12.

Washburn Area (includes Washburn Avenue, Vincent Avenue, Thomas Avenue, Sheridan Avenue, Russell Avenue, Queen Avenue, 87th Street, 87 ½ Street)
Concrete curb and driveway installation continues in the stage 1 area (including Queen Avenue, Russell Avenue, Sheridan Avenue and 87 ½ Street from Thomas Avenue to Queen Avenue) and is anticipated to complete early in the week of September 12.  Fine grading of class 5 on Queen Avenue is scheduled for early in the week of September 12 and paving of the first layer of bituminous on Queen Avenue will follow later in the week.  Fine grading of class 5 will continue in the remainder of the stage 1 area later in the week of September 12.  Rain water garden excavation is scheduled to begin the week of September 12.

Storm sewer work in the stage 2 area (including Thomas Avenue, Vincent Avenue, Washburn Avenue, 87th Street and 87 ½ Street from Vincent Avenue to Thomas Avenue) is anticipated to complete late in the week of September 12.  Excavation, grading and placing of class 5 will continue to follow behind storm sewer installation the week of September 12.   Concrete curb and driveway installation is scheduled to start on Thomas Avenue late in the week of September 5.  Concrete installation will follow behind the completion of grading in the stage 2 area the week of September 12.

2016-102 PMP Street Maintenance Project
Lyndale Avenue (from W. 94th Street to W. 86th Street)
Removal and replacement work continues on the west side of Lyndale Avenue, due to the nature of this work and the construction of the turn lane on the south end of the project, the west sidewalk will remain closed.  For pedestrian use, the east sidewalk should be used, please use caution when traveling through the area.

W. 98th Street Retaining Wall (2620 W. 98th Street)
The retaining wall at W. 98th Street will be painted on Monday, September 12 and will be followed by restoration of the area including concrete and/or asphalt restoration for the adjacent driveways.  The sidewalk has been reopened and will remain open, so long as work is not occurring.  In the event the sidewalk is closed for work, the signs and barrels will be removed at the end of the working day barring protection for uncured concrete.

E. 98th Street School Cross Walk (Indian Mounds Elementary School)
Construction of the school cross walk at E. 98th Street is scheduled to begin the week of September 19.

September 2, 2016

2016-101 PMP Street Improvement Project
American Boulevard sidewalk (from Portland Avenue to Chicago Avenue)
Boulevard restoration will occur soon.  Installation of trees and shrubs will occur in September.  Punch list work remains.

Chalet Road (from Normandale Lake Drive to Hyland Hills Ski Chalet)
Work is complete except for punch list items.

85th Area (includes 85th Street, 1st Avenue)
Work is complete except for punch list items.

Washburn Area (includes Washburn Avenue, Vincent Avenue, Thomas Avenue, Sheridan Avenue, Russell Avenue, Queen Avenue, 87th Street, 87 ½ Street)
Storm sewer work is complete in the stage 1 area (including Queen Avenue, Russell Avenue, Sheridan Avenue and 87 ½ Street from Thomas Avenue to Queen Avenue).  Concrete curb, walks and driveways will be installed the week of September 5.
Storm sewer work in the stage 2 area (including Thomas Avenue, Vincent Avenue, Washburn Avenue, 87th Street and 87 ½ Street from Vincent Avenue to Thomas Avenue) has begun and will continue the week of September 5 and into the following week. Excavation and grading has started in this area and will follow behind storm sewer installation after Labor Day.

2016-102 PMP Street Maintenance Project
Lyndale Avenue (from W. 94th Street to W. 86th Street)
Traffic control was rearranged earlier this week to accommodate the removal and replacement work occurring on the west side of Lyndale Avenue, as well as utility adjustments. Traffic will now travel on north bound lanes between W. 86th Street and W. 94th Street.  Moving forward, traffic control will be altered to varying degrees to create a safe environment for construction crews to complete their work, please use additional caution while traveling through Lyndale Avenue and exercise patience with motorists and pedestrians at All-Way stops.

Pillsbury Area (Pillsbury Avenue from W. 82nd Street to W. 81st Street and Wentworth Avenue from W. 82nd Street to W. 81st Street)
Due to scheduling conflicts, work in the Pillsbury area has been delayed until the week of Monday, September 19.

W 98th Street Filtration Basin (Located East of the intersection of Nesbitt Avenue and W. 98th Street)
Top soil for the filtration basin was placed earlier this week and was subsequently followed by the installation of seed and blanket.

August 2016

August 26, 2016

2016-102 PMP Street Maintenance Project
Lyndale Avenue (from W. 94th Street to W. 86th Street)
Concrete removal and replacement began earlier this week and will continue on the eastside of Lyndale Avenue into next week.  Completion of the concrete and adjustment work on the eastside of Lyndale Avenue will be followed by a change in traffic control.  The change in traffic control will switch traffic from the southbound lanes to the northbound lanes to allow the crews to safely continue their work on the west side of Lyndale Avenue.  Electrical work in for new traffic signal poles will continue as well and has progressed with the installation of the signal pole bases.

Pillsbury Area (Pillsbury Avenue from W. 82nd Street to W. 81st Street and Wentworth Avenue from W. 82nd Street to W. 81st Street)
Utility patches for the road are expected to be completed next week. Milling and paving of the area will follow after the holiday weekend.

W 98th Street Filtration Basin (Located East of the intersection of Nesbitt Avenue and W. 98th Street)
Construction of the filtration basin was completed early this week.  Top soil will be placed after three consecutive dry days, with seed blankets to follow shortly thereafter.

2016-101 PMP Street Improvement Project
American Boulevard sidewalk (from Portland Avenue to Chicago Avenue)
Boulevard restoration is underway.  Installation of trees and shrubs will occur in September.  Punch list work remains.

Chalet Road (from Normandale Lake Drive to Hyland Hills Ski Chalet)
Sod and seed installation is complete and the final layer of bituminous has been paved.  Final striping is scheduled to occur the week of August 29.

85th Area (includes 85th Street, 1st Avenue)
Concrete work is complete and the first layer of bituminous has been paved.  Boulevard restoration will continue the week of August 29.

Washburn Area (includes Washburn Avenue, Vincent Avenue, Thomas Avenue, Sheridan Avenue, Russell Avenue, Queen Avenue, 87th Street, 87 ½ Street)
Storm sewer work is progressing from east to west and will continue the week of August 29 in the stage 1 area (including Queen Avenue, Russell Avenue, Sheridan Avenue and 87 ½ Street from Thomas Avenue to Queen Avenue).  Excavation, grading and placement of class 5 has started in this area and will follow behind storm sewer installation the week of August 29.

Pavement removal in the stage 2 area (including Thomas Avenue, Vincent Avenue, Washburn Avenue, 87th Street and 87 ½ Street from Vincent Avenue to Thomas Avenue) is scheduled to begin early in the week of August 29.  Similar to the stage 1 area, this will be followed by storm sewer work later in the week of August 29.

August 19, 2016

2016-102 PMP Street Maintenance Project
Lyndale Avenue (from W. 94th Street to W. 86th Street)
Removals began this week in anticipation of concrete work to take place next week on the east side of Lyndale Avenue.  Adjustment of utility structures will also take place next week.  Late next week traffic will moved to the north bound lanes to accommodate work on the west side of Lyndale Avenue.

Humboldt Area (Humboldt Avenue, Irving Avenue, Girard Avenue and W. 97th Street)
The Humboldt Area was paved early this week.

Pillsbury Area (Pillsbury Avenue from W. 82nd Street to W. 81st Street and Wentworth Avenue from W. 82nd Street to W. 81st Street)
Operations are currently delayed due to private utility work and the corresponding restoration.

W 98th Street Filtration Basin (Located East of the intersection of Nesbitt Avenue and W. 98th Street)
Construction of the filtration basin resumed this week and will be completed early next week.

2016-101 PMP Street Improvement Project
90th Street (from 12th Avenue to Old Cedar Avenue)
90th Street paving and striping is complete and 90th Street has been reopened to traffic.  Punch list work remains.

American Boulevard sidewalk (from Portland Avenue to Chicago Avenue)
Boulevard topsoil has been placed and sod and seed installation is anticipated to complete the week of August 22.

Chalet Road (from Normandale Lake Drive to Hyland Hills Ski Chalet)
Concrete installation is complete.  Boulevard topsoil has been placed and sod and seed installation is anticipated to complete early in the week of August 22.  Paving of the final layer of bituminous is scheduled for late in the week of August 22.  Final striping will occur the week of August 29.

85th Area (includes 85th Street, 1st Avenue)
A minor amount of concrete sidewalk work remains and will complete by early in the week of August 22.  Fine grading of class 5 is scheduled for the week of August 22.  The first layer of bituminous is anticipated to be paved by late in the week of August 22 which will be followed by paving of bituminous driveways.  Boulevard restoration is anticipated to occur the week of August 29.

Washburn Area (includes Washburn Avenue, Vincent Avenue, Thomas Avenue, Sheridan Avenue, Russell Avenue, Queen Avenue, 87th Street, 87 ½ Street)
Pavement removal in the stage 1 area (including Queen Avenue, Russell Avenue, Sheridan Avenue and 87 ½ Street from Thomas Avenue to Queen Avenue) is complete.  Storm sewer work in this area is scheduled to start Friday, August 19 (weather permitting) and continue for approximately two weeks.  Excavation, grading and placement of class 5 is scheduled to start the week of August 22 following behind storm sewer installation.
Pavement removal in the stage 2 area (including Thomas Avenue, Vincent Avenue, Washburn Avenue, 87th Street and 87 ½ Street from Vincent Avenue to Thomas Avenue) is still anticipated to begin early in the week of August 29.  Similar to the stage 1 area, this will be followed by storm sewer work later in the week of August 29.

August 12, 2016

2016-102 PMP Street Maintenance Project
Lyndale Avenue (from W. 94th Street to W. 86th Street)
Underground utility structures were reconstructed and adjusted this week and will continue into next week.  Future utility work will require changes to the traffic control that will utilize an All-Way Stop at the intersection of Lyndale Avenue and W. 90th Street.  Electrical work associated with traffic signal revisions continue.

James Area (James Road, James Circle, Bliss Lane, Bliss Lane Circle, Emerson Road, River Terrace Drive)
Paving of the James Area was completed this week.

Abbott Area (Abbott Avenue from W. 108th Street to W. 107th Street and W. 107th Street from Abbott Avenue to Zenith Avenue)
Paving of the Abbott area was completed this week.

Humboldt Area (Humboldt Avenue, Irving Avenue, Girard Avenue and W. 97th Street)
The Humboldt Area was milled earlier this week and is scheduled to be paved on Monday, August 15th.  Restoration work was completed late this week as well.

Pillsbury Area (Pillsbury Avenue from W. 82nd Street to W. 81st Street and Wentworth Avenue from W. 82nd Street to W. 81st Street)
Concrete replacement work as the result of a utility project has been completed.  Restoration will follow prior to milling.

W. 98th Street Filtration Basin (Located East of the intersection of Nesbitt Avenue and W. 98th Street)
Construction of the filtration basin is scheduled to resume next Friday, August 19th.  In preparation for construction, the basin will be pumped and cleaned.

W. 98th Street Retaining Wall (2620 W. 98th Street)
Installation of the galvanized chain link fence took place this week and will include landscaping plantings to be planted at a later date.

2016-101 PMP Street Improvement Project
90th Street (from 12th Avenue to Old Cedar Avenue)
Paving of the final layer of bituminous is complete.  Final striping is scheduled for early in the week of August 15.  90th Street is anticipated to be re-opened to traffic early in the week of August 15.

American Boulevard sidewalk (from Portland Avenue to Chicago Avenue)
Boulevard restoration has started and will continue the week of August 15.

Chalet Road (from Normandale Lake Drive to Hyland Hills Ski Chalet)
Paving of the first layer of bituminous is complete.  Paving of bituminous driveways is also complete.  The remainder of the concrete work in this area is anticipated to complete by early in the week of August 15.  Boulevard restoration and raising of manholes and gate valves has started and will continue the week of August 15.

85th Area (includes 85th Street, 1st Avenue)
Concrete work has started and is anticipated to complete early in the week of August 15.  This will be followed by fine grading of the class 5 late in the week of August 15.  The first layer of bituminous is anticipated to be paved the week of August 22.

Washburn Area (includes Washburn Avenue, Vincent Avenue, Thomas Avenue, Sheridan Avenue, Russell Avenue, Queen Avenue, 87th Street, 87 ½ Street)
Tree removal in the entire area has started and is anticipated to complete early in the week of August 15.

Pavement removal in the stage 1 area, which includes Queen Avenue, Russell Avenue, Sheridan Avenue and 87 ½ Street from Thomas Avenue to Queen Avenue is scheduled to begin Tuesday, August 16.  Storm sewer work in this area is scheduled to begin late in the week of August 15 and continue the week of August 22.  Excavation, grading and placement of class 5 will follow storm sewer work as it progresses.

Pavement removal in the stage 2 area, which includes Thomas Avenue, Vincent Avenue, Washburn Avenue, 87th Street and 87 ½ Street from Vincent Avenue to Thomas Avenue is anticipated to begin early in the week of August 29.  Similar to the stage 1 area, this will be followed by storm sewer work later in the week of August 29.

August 5, 2016

2016-101 PMP Street Improvement Project

South Bay Area (includes South Bay Drive, South Bay Circle)
Sod installation, milling and paving of the final layer of bituminous is complete.  Punch list work remains.

90th Street (from 12th Avenue to Old Cedar Avenue)
Boulevard restoration along with raising of manholes and gate valves has started and is scheduled to complete the week of August 8.  Paving of the final layer of bituminous is anticipated to occur late in the week of August 8.  Final striping of the new pavement will occur approximately 3 days after the street is paved and 90th Street will be reopened to traffic at that time.

American Boulevard sidewalk (from Portland Avenue to Chicago Avenue)
Concrete work is complete.  Boulevard restoration is scheduled for the week of August 8.

Chalet Road (from Normandale Lake Drive to Hyland Hills Ski Chalet)
Excavation, grading and placement of class 5 is complete.  Concrete work was slightly delayed due to the rain this week and will continue late in the week of August 1.  Fine grading of class 5 in preparation for paving of the first layer of bituminous is scheduled for the week of August 8.

85th Area (includes 85th Street, 1st Avenue)
Excavation, grading and placement of class 5 has started and will continue the week of August 8.  Concrete work is anticipated to begin late in the week of August 8.

Washburn Area (includes Washburn Avenue, Vincent Avenue, Thomas Avenue, Sheridan Avenue, Russell Avenue, Queen Avenue, 87th Street, 87 ½ Street)
Pavement removal in the stage 1 area is scheduled for early in the week of August 15.  Storm sewer work will follow pavement removal in the stage 1 area the week of August 15 and continue the week of August 22.

2016-102 PMP Street Maintenance Project
Lyndale Avenue (from W. 94th Street to W. 86th Street)
Installation of electrical conduit continues in the area, this work has also included the removal of existing traffic signal poles and the relocation of utility power poles.  Utility adjustments and reconstructions are scheduled to begin early next week.  Underground utility work will require lane closures, as such motorists are advised to use extra caution and to expect delays when traveling through the area. 
City forces will be sealcoating Lyndale Avenue south of W 94th Street on Sunday, August 7th.

James Area (James Road, James Circle, Bliss Lane, Bliss Lane Circle, Emerson Road, River Terrace Drive)
Restoration of the area is complete in anticipation of milling to take place Monday, August 8th.  Paving will follow on Tuesday, August 9th.

Abbott Area (Abbott Avenue from W. 108th Street to W. 107th Street and W. 107th Street from Abbott Avenue to Zenith Avenue)
Restoration of the area is complete in anticipation of milling to take place Monday, August 8th.  Paving will follow on Tuesday, August 9th.

Humboldt Area (Humboldt Avenue, Irving Avenue, Girard Avenue and W. 97th Street)
Installation of concrete curb and gutter will be completed late this week and will be followed by the reconstruction of utility structures in the area.  Milling and paving is tentatively scheduled late next week and will be determined by completion of work in other areas of town.

Pillsbury Area (Pillsbury Avenue from W. 82nd Street to W. 81st Street and Wentworth Avenue from W. 82nd Street to W. 81st Street)
Concrete work in the area has been completed.  Private utility work took place on Friday, August 5th and may require follow up concrete work early next week.  The area is anticipated to be milled on Tuesday, August 9th.  Paving will follow soon after.

W 98th Street Filtration Basin (Located East of the intersection of Nesbitt Avenue and W. 98th Street)
Iron filings needed to create iron enhanced sand have been received by the contractor.  Work on the filtration basin will begin upon completion of underground utility work in time sensitive area of town.  A late August/ early September timeline is expected for completion of the filtration basin.

W. 98th Street Retaining Wall (2620 W. 98th Street)
Installation of fence posts was completed this week and will be followed by some grading work behind the wall.  The color of the wall is currently being discussed with the contractors.

July 2016

July 29, 2016

2016-102 PMP Street Maintenance Project
Lyndale Avenue (from W. 94th Street to W. 86th Street)
Bloomington’s mill and overlay project will begin on Lyndale Avenue Monday, August 1.  Traffic signal revision work will require removal of existing signal poles at the intersections of W. 94th Street and W. 86th Street, as such these intersections will require a 4-way stop.  Residents are advised to use extra caution when navigating through the Lyndale Avenue and to expect delays.
Xcel Energy continues installation of electrical conduit in the area and will begin installing light poles and bases next week.

East Bush Lake Road (Right Turn Lane at W. 86th Street)
Paving of the new East Bush Lake Road right turn lane is complete and will be striped on Saturday, July 30.

W. 84th Street (from Normandale Lake Boulevard to Normandale Boulevard)
Paving of the W. 84th Street was completed early this week after delays caused by the weather on Saturday, July 23.  The area has been pre-marked for striping, which will take place Saturday, July 20.

James Area (James Road, James Circle, Bliss Lane, Bliss Lane Circle, Emerson Road, River Terrace Drive)
Reconstruction and adjustment of utility structures is complete.  The area has been prepped for sod, but has not been placed due to the recent heat wave.  The contractor will continue restoration next week.

Abbott Area (Abbott Avenue from W. 108th Street to W. 107th Street and W. 107th Street from Abbott Avenue to Zenith Avenue)
Reconstruction and adjustment of utility structures is complete.  The area has been prepped for sod, but has not been placed due to the high temperatures of late.  The contractor will continue restoration next week.

Humboldt Area (Humboldt Avenue, Irving Avenue, Girard Avenue and W. 97th Street)
Concrete removal and replacement has begun and will continue into next week.  Reconstruction and adjustment of existing utility structures will begin next week.

Pillsbury Area (Pillsbury Avenue from W. 82nd Street to W. 81st Street and Wentworth Avenue from W. 82nd Street to W. 81st Street)
Adjustment of utility structures in the area will begin Saturday, July 30th.

W. 98th Street Retaining Wall (2620 W. 98th Street)
Construction of the wall has been completed and will be followed by the removal of existing driveways and sidewalk adjacent to the wall.  Restoration behind the wall will also begin next week.

2016-101 PMP Street Improvement Project
South Bay Area (includes South Bay Drive, South Bay Circle)
Sod installation has started and is anticipated to complete by the end of the day Friday, July 29.  Milling and paving of the final layer of bituminous is scheduled for early in the week of August 1.

90th Street (from 12th Avenue to Old Cedar Avenue)
The first two layers of bituminous have been paved and concrete work is complete.  Boulevard restoration along with raising of manholes and gate valves is scheduled for the week of August 1.  Paving of the final layer of bituminous is anticipated to occur the week of August 8.

American Boulevard sidewalk (from Portland Avenue to Chicago Avenue)
Concrete curb installation is complete and installation of the new sidewalk is scheduled for early in the week of August 1.  This will be followed by boulevard restoration.

Chalet Road (from Normandale Lake Drive to Hyland Hills Ski Chalet)
Storm sewer work is complete.  Excavation, grading and placement of class 5 has started and is anticipated to complete early in the week of August 1.  This will be followed by concrete work the week of August 1.

85th Area (includes 85th Street, 1st Avenue)
Pavement removal and storm sewer work is complete.  Excavation, grading and placement of class 5 is scheduled for the week of August 1.  This will be followed by concrete work either late in the week of August 1 or the week of August 8.

Washburn Area (includes Washburn Avenue, Vincent Avenue, Thomas Avenue, Sheridan Avenue, Russell Avenue, Queen Avenue, 87th Street, 87 ½ Street)
This large area will be broken into two stages, with stage 1 including Queen Avenue, Russell Avenue, Sheridan Avenue and 87 ½ Street from Thomas Avenue to Queen Avenue.  Stage 2 will include the remainder of the area which includes Thomas Avenue, Vincent Avenue, Washburn Avenue, 87th Street and 87 ½ Street from Vincent Avenue to Thomas Avenue.  The Contractor anticipates removing pavement and starting storm sewer work in stage 1 the week of August 15.  Stage 2 is anticipated to begin approximately 2 weeks after stage 1 as phases of construction progress.  More information will be given as construction nears.

July 22, 2016

2016-102 PMP Street Maintenance Project
Nesbitt Area (Nesbitt Avenue from W. 102nd to W. 98th Street and W. 98th Street from Nesbitt Avenue to Normandale Boulevard)
Installation of ground in pavement messages and crosswalks were completed at W. 98th Street and Normandale Boulevard.

East Bush Lake Road (Right Turn Lane at W. 86th Street)
Restoration of the boulevard area was completed this week with plans to pave the final lift of asphalt on Saturday, July 23.

W. 84th Street (from Normandale Lake Boulevard to Normandale Boulevard)
Restoration of the boulevard areas adjacent to W. 84th Street were completed this week in anticipation of milling to take place on Wednesday, July 21 and Thursday, July 22.  This work will be followed by the final paving of the area and is scheduled to take place on Saturday, July 23.  The contractor has been granted a variance to begin work in the area between the hours of 4 AM – 7 AM and 10 PM – 11 PM on July 21, 22 and, 23.

James Area (James Road, James Circle, Bliss Lane, Bliss Lane Circle, Emerson Road, River Terrace Drive)
Removal and replacement of existing concrete was completed early this week.  Reconstruction and adjustment of existing utility structures will take place late this week and will last until early next week.  Restoration work will begin soon after.

Abbott Area (Abbott Avenue from W. 108th Street to W. 107th Street and W. 107th Street from Abbott Avenue to Zenith Avenue)
Removal and replacement of existing concrete was completed early this week.  Reconstruction and adjustment of existing utility structures will take place late this week and will last until early next week.  Restoration work will begin soon after.

Humboldt Area (Humboldt Avenue, Irving Avenue, Girard Avenue and W. 97th Street)
Concrete removal and replacement is scheduled to begin early next week on Tuesday, July 26.  This work will be followed by the reconstruction and adjustment of existing utility structures.

W. 98th Street Retaining Wall (2620 W. 98th Street)
Excavation of the retaining wall was completed this week and was followed by the construction of a concrete leveling pad.  Construction of the wall will begin at the end of this week and will carry into next week.  The sidewalk adjacent to the wall remains closed.

Lyndale Avenue (from W. 94th Street to W. 86th Street)
Center Point Energy has completed installation of gas services and will continue to work on restoration of the area.
Xcel Energy began their light pole replacement project early this week and their work is expected to last until the end of July. 
Bloomington’s mill and overlay project will commence on Lyndale Avenue following completion of Xcel Energy’s light pole replacement project.  The expected start date is Monday, August 1st.

July 21, 2016

2016-101 PMP Street Improvement Project
South Bay Area (includes South Bay Drive, South Bay Circle)
Concrete replacement and paving of the first layer of bituminous is complete.  Raising of manholes and gate valves is anticipated to complete by early in the week of July 25.  Sod installation is scheduled for the week of July 25.  Milling and paving of the final layer of bituminous is anticipated to occur the week of August 1.

90th Street (from 12th Avenue to Old Cedar Avenue)
The first two layers of bituminous are scheduled to be paved early in the week of July 25.  This will be followed by paving of the bituminous driveways along with the remainder of the concrete replacements.  Boulevard restoration is anticipated to begin late in the week of July 25 and continue the week of August 1.

American Boulevard sidewalk (from Portland Avenue to Chicago Avenue)
Excavation and grading for the new sidewalk is anticipated to complete early in the week of July 25.  Concrete sidewalk installation has been slightly delayed and is anticipated to begin late in the week of July 25.

Chalet Road (from Normandale Lake Drive to Hyland Hills Ski Chalet)
Pavement removal is complete.  Storm sewer work has started and is anticipated to complete by early in the week of July 25.  Excavation, grading and placement of class 5 is scheduled for the week of July 25.

85th Area (includes 85th Street, 1st Avenue)
Pavement removal has started and will complete by the end of the week of July 18.  Storm sewer work is scheduled for the week of July 25.  This will be followed by excavation, grading and placement of class 5.

July 18, 2016

2016-102 PMP Street Maintenance Project
Nesbitt Area (Nesbitt Avenue from W. 102nd to W. 98th Street and W. 98th Street from Nesbitt Avenue to Normandale Boulevard)
Restoration of the boulevards and pavement striping on W. 98th Street and Nesbitt Avenue was completed this week.  Installation of ground in pavement messages and pedestrian crosswalks will take place late this week.

East Bush Lake Road (Right Turn Lane at W. 86th Street)
Paving of the asphalt base course occurred early this week and will be followed by restoration work to be completed next week.  Final paving of the turn lane addition will be scheduled with the paving of W. 84th Street.

Auto Club Area (Auto Club Road, Bluff Drive and Normandale Boulevard)
Paving and restoration activities were completed early this week and was followed by the painting of pavement markings on Auto Club Road.  Landscaping of an existing retaining wall on Auto Club Road was also completed this week.

Lyndale Avenue (from W. 94th Street to W. 86th Street)
Center Point Energy continues to work on the installation of gas services and will continue their work on the curb lanes of Lyndale Avenue.
The removal of light poles and bases will be completed late this week in anticipation of the light pole installation work scheduled to begin on Monday, July 18 by Xcel Energy.

W. 84th Street (from Normandale Lake Boulevard to Normandale Boulevard)
Removal and replacement of existing concrete was completed this week in conjunction with underground utility and traffic systems work in the area.  Restoration is scheduled to begin late this week and carry into the beginning of next week.

W. 98th Street Retaining Wall (2620 W. 98th Street)
Excavation of the retaining wall trench began this week and is expected to be completed early next week.  The excavation will be followed by the construction of a concrete footing.  The sidewalk adjacent to the wall remains closed.

July 15, 2016

2016-101 PMP Street Improvement Project
Drew Area (includes Drew Avenue, Ewing Road, 103rd Street, 104th Street)
Sod installation, raising of manholes and gate valves and paving of the final layer of bituminous is complete.  Punch list work remains.

South Bay Area (includes South Bay Drive, South Bay Circle)
A minor amount of concrete replacement remains and is anticipated to complete by early in the week of July 18.  Paving of the first layer of bituminous is scheduled to complete on Friday, July 15.  Paving of bituminous driveways along with boulevard restoration is scheduled for the week of July 18.

90th Street (from 12th Avenue to Old Cedar Avenue)
Concrete replacement has started and is anticipated to complete the week of July 18.  This will be followed by fine grading of the class 5 in preparation of the first two layers of bituminous.  The first two layers of bituminous are anticipated to be paved the week of July 25.

Garden Circle (from Louisiana Avenue to West Terminus), Colorado Road (a location just north of Colorado Circle)
Sod installation and paving of the final layer of bituminous is complete.

American Boulevard sidewalk (from Portland Avenue to Chicago Avenue)
Excavation and grading for the new sidewalk has started and is anticipated to complete the week of July 18.  Concrete sidewalk installation is anticipated to begin late in the week of July 18 and complete the week of July 25.  Storm sewer catch basin relocation is complete.

Chalet Road (from Normandale Lake Drive to Hyland Hills Ski Chalet)
Pavement removal is scheduled to begin mid-week of July 18.  This will be followed by storm sewer work late in the week of July 18.  Excavation, grading and placement of class 5 will follow storm sewer work the week of July 25.

85th Area (includes 85th Street, 1st Avenue)
Pavement removal is scheduled for late in the week of July 18.  This will be followed by storm sewer work the week of July 25.  Excavation, grading and placement of class 5 will follow storm sewer work.

July 8, 2016

2016-101 PMP Street Improvement Project
Drew Area (includes Drew Avenue, Ewing Road, 103rd Street, 104th Street)
Boulevard restoration and sod installation is anticipated to complete by early in the week of July 11.  Raising of manholes and gate valves are also anticipated to complete by early in the week of July 11.  Paving of the final layer of bituminous is scheduled for the week of July 11.

South Bay Area (includes South Bay Drive, South Bay Circle)
Placement of class 5 is complete.  Concrete replacement has started and is anticipated to complete by early in the week of July 11.  Fine grading of class 5 gravel along with paving of the first layer of bituminous is anticipated to occur the week of July 11.  This paving will be followed by paving of bituminous driveways and boulevard restoration.

90th Street (from 12th Avenue to Old Cedar Avenue)
Excavation, grading and placement of class 5 is anticipated to complete by early in the week of July 11.  Concrete removal and replacement is scheduled for the week of July 11.

Garden Circle (from Louisiana Avenue to West Terminus), Colorado Road (a location just north of Colorado Circle)
Boulevard restoration and sod installation is scheduled to complete by early in the week of July 11.  Paving of the final layer of bituminous on Colorado Road is scheduled to complete the week of July 11.

American Boulevard sidewalk (from Portland Avenue to Chicago Avenue)
Excavation and grading for the new sidewalk is scheduled to begin the week of July 11.  This will also include some minor storm sewer catch basin relocation the week of July 11.  Concrete installation is anticipated to occur the week of July 18.

Chalet Road (from Normandale Lake Drive to Hyland Hills Ski Chalet)
Street reconstruction work in this area is anticipated to begin the week of July 18.  More information will be given when the schedule is determined.

85th Area (includes 85th Street, 1st Avenue)
Street reconstruction work in this area is anticipated to begin the week of July 18.  More information will be given when the schedule is determined.

2016-102 PMP Street Maintenance Project
Nesbitt Area (Nesbitt Avenue from W. 102nd to W. 98th Street and W. 98th Street from Nesbitt Avenue to Normandale Boulevard)
W. 98th Street from Nesbitt Avenue to Briar Road has been paved and is open to traffic.  Paving for the area occurred early this week and is awaiting final pavement marking to take place next Monday, July 11.  Restoration of the boulevards will also take place early next week.  Work on the filtration basin in the center median has been delayed; further information will be provided once a schedule has been determined.

East Bush Lake Road (Right Turn Lane at W. 86th Street)
Installation of concrete curb and gutter has been completed, as well as the adjacent pedestrian access ramps.  Additional prep work on the area will take place late this week in anticipation of the base course of asphalt pavement to be placed mid to late next week.

Auto Club Area (Auto Club Road, Bluff Drive and Normandale Boulevard)
The contractor completed both the milling of the existing roadways and paving of the area this week.  Final pavement marking will take place on Monday, July 11.  Restoration work in the area is scheduled to begin late this week to early next week.

Lyndale Avenue (from W. 94th Street to W. 86th Street)
Center Point Energy continues to work on the installation of gas services and will continue their work on the curb lanes of Lyndale Avenue.  Their work is expected to last until the end of next week to be followed by restoration.
As part of the 2016-102 PMP Overlay project the contractor will be removing light poles and light pole base in the area beginning next week on Monday, July 11.  This is preliminary work being done in conjunction with Xcel Energy’s light pole replacement project.


W. 84th Street (from Normandale Lake Boulevard to Normandale Boulevard)
The reconstruction and adjustment of existing utility structures has been completed this week. Removal and replacement of concrete curb and gutter, and concrete flat work is scheduled to take place early next week.  Work on existing traffic loop detectors is also scheduled to take place early next week.

W. 98th Street Retaining Wall (2620 W. 98th Street)
Removal of the existing retaining wall has been completed with excavation work to follow next week.  The sidewalk adjacent to the wall remains closed.

 

July 1, 2016

2016-101 PMP Street Improvement Project
Drew Area (includes Drew Avenue, Ewing Road, 103rd Street, 104th Street)
Paving of the first layer of bituminous along with bituminous driveway paving is complete in the entire area.  Boulevard restoration has started and will continue the week of July 5 along with sod installation.  Raising of manholes and gate valves in preparation for the final layer of bituminous is anticipated to occur the week of July 11.

Washburn Area (includes Washburn Avenue, Vincent Avenue, Thomas Avenue, Sheridan Avenue, Russell Avenue, Queen Avenue, 87th Street and 87 ½ Street)
CenterPoint Energy has completed service installation in the area. 
 

South Bay Area (includes South Bay Drive, South Bay Circle)
Excavation and placement of drain tile is complete.  Placement and grading of class 5 has started and will continue the week of July 5.  Concrete replacement is scheduled to begin mid-week of July 5.

90th Street (from 12th Avenue to Old Cedar Avenue)
Storm sewer and water main work is complete. Excavation, grading and placement of class 5 has started and will continue the week of July 5.  Concrete replacement is anticipated to begin late in the week of July 5 or the week of July 11.

Garden Circle (from Louisiana Avenue to West Terminus), Colorado Road (a location just north of Colorado Circle)
Concrete curb and sidewalk replacement is complete in both areas.  Bituminous patching is complete on Garden Circle and the first layer of bituminous has been paved on Colorado Road.  Bituminous driveway patching is scheduled for Friday, July 1 on Colorado Road.  Boulevard restoration is scheduled for the week of July 5, which will be followed by paving of the final layer of bituminous on Colorado Road the week of July 11.

American Boulevard sidewalk (from Portland Avenue to Chicago Avenue)
The Contractor anticipates starting excavation and grading for sidewalk installation on the south side of American Boulevard from Portland Avenue to Chicago Avenue the week of July 11.  This will also include a small fill-in section of sidewalk on the east side of Chicago Avenue just north of American Boulevard.

Chalet Road (from Normandale Lake Drive to Hyland Hills Ski Chalet)
Canadian Pacific Railway has completed the railroad crossing replacement on the south end of Chalet Road at the entrance to Hyland Hills.  Street reconstruction work in this area is anticipated to begin the week of July 18.

2016-102 PMP Street Maintenance Project
Nesbitt Area (Nesbitt Avenue from W. 102nd to W. 98th Street and W. 98th Street from Nesbitt Avenue to Normandale Boulevard)
W. 98th Street from Nesbitt Avenue to Briar Road will be open late in the afternoon on Friday, July 1.  Residents in the area will have to follow the detour provided until the contractor completes paving of the area.  The road will be open to traffic for the holiday weekend and moving forward.
The contractor completed milling of the roadways and is currently working on restoration of the areas.  W. 98th Street from Nesbitt Avenue to Normandale Boulevard is scheduled to be paved Friday, July 1.  Nesbitt Avenue from W. 102nd Street to W. 98th Street is scheduled to be paved the morning of Wednesday, July 6.

East Bush Lake Road (Right Turn Lane at W. 86th Street)
Excavation and embankment work was completed in preparation for the installation of concrete curb and gutter to take place the day after the Fourth of July holiday.  The area will be graded and prepped for the base course of asphalt pavement late next week.

Auto Club Area (Auto Club Road, Bluff Drive and Normandale Boulevard)
Concrete work and the adjustment of existing utilities are expected to be completed Friday, July 1 before the holiday weekend.  With restoration occurring early next week after the holiday, followed by milling and paving scheduled to take place on Wednesday, July 6.

Lyndale Avenue (from W. 94th Street to W. 86th Street)
CenterPoint Energy has completed installation of their gas main at the intersection of Lyndale Avenue and W. 94th Street.  Restoration work has begun and is expected to be completed by week’s end.  Center Point’s services crew has begun work in the boulevards along Lyndale and will continue this work for an estimated two weeks.  Traffic control is expected to be removed prior to the holiday weekend.

W. 84th Street (from Normandale Lake Boulevard to Normandale Boulevard)
The contractor is schedule to begin work in the area immediately following the Fourth of July holiday.  Preliminary saw cutting may take place late this week.

June 2016

June 24, 2016

2016-101 PMP Street Improvement Project
Drew Area (includes Drew Avenue, Ewing Road, 103rd Street, 104th Street)
The Contractor has been granted a noise exception for Saturday, June 25 to start at 7:00 am.  Paving of the first layer of bituminous is complete on Ewing Road and 104th Street.  Minor soil corrections will be completed on portions of 103rd Street and Drew Avenue prior to paving the first layer of bituminous on these street segments.  These corrections are anticipated to occur on Saturday, June 25 (weather permitting).  Paving of bituminous driveways is scheduled for Saturday, June 25 (weather permitting) and boulevard restoration is anticipated to start the week of June 27.

Washburn Area (includes Washburn Avenue, Vincent Avenue, Thomas Avenue, Sheridan Avenue, Russell Avenue, Queen Avenue, 87th Street and 87 ½ Street)
CenterPoint Energy anticipates completing gas service installation by early July in this area.  Street reconstruction is not anticipated to start until early August.

South Bay Area (includes South Bay Drive, South Bay Circle)
The Contractor has been granted a noise exception for Saturday, June 25 to start at 7:00 am.  Minor storm sewer work is complete.  Pavement removal on South Bay Drive is complete and excavation, grading and drain tile placement has started and will continue the week of June 27.  Placement of class 5 will follow behind excavation and grading.  Concrete replacement is anticipated to start late in the week of June 27 or the week of July 4.

90th Street (from 12th Avenue to Old Cedar Avenue)
90th Street is currently closed from 12th Avenue to Old Cedar Avenue and will remain closed until the completion of street reconstruction.  Pavement removal is complete.  Storm sewer and water main work has started and will complete the week of June 27.  The water main work, which includes a hydrant relocation and a minor pipe replacement, will require water main shutdowns for some properties along 90th Street and Bloomington Avenue on Monday, June 27.  Residents affected by these shutdowns have been notified.  Excavation, grading and placement of class 5 will follow behind storm sewer and water main work the week of June 27 and continue into the week of July 4.

Garden Circle (from Louisiana Avenue to West Terminus), Colorado Road (a location just north of Colorado Circle)
Pavement removal, excavation and subgrade correction in both of these locations is complete.  Concrete curb and sidewalk replacement is scheduled to begin Friday, June 24.  Bituminous patching in these areas is anticipated to occur the week of June 27.

Chalet Road (from Normandale Lake Drive to Hyland Hills Ski Chalet)
Three Rivers Park District is working with Canadian Pacific Railway to replace the railroad crossing on the south end of Chalet Road at the entrance to Hyland Hills.  This work is scheduled to occur between Monday, June 27 and Wednesday, June 29.  Chalet Road will be closed at the entrance to Hyland Hills during this work.  Street reconstruction work in this area is anticipated to begin in mid-July.

2016-102 PMP Street Maintenance Project
Telegraph Area (includes Telegraph Road, Rhode Island Avenue and Pennsylvania Road)
Restoration and paving of the area has been completed.

Nesbitt Area (Nesbitt Avenue from W. 102nd to 98th Street and W. 98th Street from Nesbitt Avenue to Normandale Boulevard)
W. 98th Street remains closed from Nesbitt Avenue to Briar Road until Friday, July 1.  Residents in the area will have to follow the detour provided.
The contractor completed concrete work in the area and will begin work on the construction of a filtration basin in the center island.  Restoration of the area and paving of the W. 98th Street is scheduled to be completed.
The contractor has been granted a variance to begin work at 7:00 AM on Saturday, June 25.

W. 98th Street Retaining Wall (2620 W. 98th Street)
Work on the retaining wall has been postponed by the contractor due to scheduling conflicts.  Further information will be provided once a schedule has been determined.  The sidewalk adjacent to the wall has been closed.

East Bush Lake Road (Right Turn Lane at W. 86th Street)
Construction of a right turn lane at the intersection of East Bush Lake Road and W. 86th Street will begin on Monday, June 27.

Auto Club Area (Auto Club Road, Bluff Drive and Normandale Boulevard)
The contractor will work on the reconstruction and adjustment of existing man holes, gate valves and catch basins beginning Monday, June 27.

Lyndale Avenue (from W. 94th Street to W. 86th Street)
CenterPoint Energy has completed restoration at the intersection of Lyndale Avenue and W. 90th Street.  Work at the intersection of W. 94th Street and Lyndale Avenue is scheduled to begin Monday, June 27, the intersection will be set to an all way stop and include a truck detour route.  Installation of the gas main and restoration is expected to last through the end of next week.

June 17, 2016

2016-102 PMP Street Maintenance Project
Telegraph Area (includes Telegraph Road, Rhode Island Avenue and Pennsylvania Road)

Restoration of sod in the area has been completed with minimal landscaping to be done early next week.  On Friday June 17 and Monday, June 20 the contractor will be working to complete milling and paving of the area.

Nesbitt Area (Nesbitt Avenue from W. 102nd to 98th Street and W. 98th Street from Nesbitt Avenue to Normandale Boulevard)

W. 98th Street will be closed from Nesbitt Avenue to Briar Road, the closure will last two weeks starting Friday, June 17 to Friday, July 1.  Residents in the area will have to follow the detour provided. The closure will be used to accommodate safe working conditions for workers and travelers alike.

The contractor has completed the reconstruction of existing man holes in the area and will proceed to the removal and replacement of existing curb and gutter.  During the closure of W. 98th  Street the contractor will work to install curb and gutter for a resized center island median that will feature an iron enhanced filtration basin to help treat storm water in the area.

The contractor has been granted a variance to begin work at 7:00 AM on Saturday, June 18.

W. 98th Street Retaining Wall (2620 W. 98th Street)

Removal of the wood timber wall at 2620 W. 98th Street will begin Monday, June 20 and is anticipated to last through the end of the week.

Auto Club Area (Auto Club Road, Bluff Drive and Normandale Boulevard)

Preliminary saw cutting was done this week in preparation for the work beginning Monday, June 20. The contractor will work on the reconstruction and adjustment of existing man holes, gate valves and catch basins early next week.

Lyndale Avenue (from W. 94th Street to W. 86th Street)

CenterPoint Energy has completed their work at the intersection of Lyndale Avenue and W. 90th Street and will next be working north of the intersection of Lyndale Avenue and W. 94th Street at the end of this week and into next week.  Once the installation of their main is completed the crews will work on the installation of gas services.

2016-101 PMP Street Improvement Project

Drew Area (includes Drew Avenue, Ewing Road, 103rd Street, 104th Street)

The majority of concrete replacement is complete with the remainder to complete the week of June 20.  Fine grading of class 5 has started and will complete early in the week of June 20.  Paving of the first layer of bituminous is scheduled for early in the week of June 20 (weather permitting).  Paving of bituminous driveways and boulevard restoration will begin late in the week of June 20.

 

Washburn Area (includes Washburn Avenue, Vincent Avenue, Thomas Avenue, Sheridan Avenue, Russell Avenue, Queen Avenue, 87th Street and 87 ½ Street)

CenterPoint Energy has completed gas main installation in this area and service installation has started.  This in expected to take another 2-3 weeks to complete. 

 

South Bay Area (includes South Bay Drive, South Bay Circle)

Drain tile installation in South Bay Circle is complete.  Concrete removal has started in the area and will continue the week of June 20.  The removal of street pavement on South Bay Drive is scheduled to begin on Monday, June 20.  This will be followed by minor storm sewer work along with excavation, grading, drain tile placement and placement of class 5 the week of June 20.  This will continue the week of June 27. 

 

90th Street (from 12th Avenue to Old Cedar Avenue)

90th Street will be closed to through traffic from 12th Avenue to Old Cedar Avenue starting Monday, June 20 at 7am.  This closure is anticipated to be in place for 6-8 weeks and a detour will be provided.  The detour will utilize Portland Avenue, 86th Street and Old Cedar Avenue.  Access will remain open for north and southbound traffic on 12th Avenue with intermittent periods of time when access will be delayed.  Northbound and southbound traffic on Old Cedar Avenue will also remain open.  The Contractor is scheduled to complete street pavement removal on June 20 and 21, which will be followed by minor storm and water main work the remainder of the week.  The water main work will include water main shutdowns for some properties in the area either late in the week of June 20 or early in the week of June 27.  Residents affected by these shutdowns will be individually notified when a schedule has been determined.  CenterPoint Energy anticipates completing gas service work in the area the week of June 20. 

 

Garden Circle (from Louisiana Avenue to West Terminus), Colorado Road (a location just north of Colorado Circle)

These two roadways have individual locations of known subgrade soil issues with frost susceptible soils that have caused “frost heaves” in recent years.  The Contractor anticipates removing pavement, excavating and replacing material in these locations the week of June 20.  This work may also include removal and replacement of concrete curb and/or sidewalk in these locations.  

June 10, 2010

2016-102 PMP Street Maintenance Project

Telegraph Area (includes Telegraph Road, Rhode Island Avenue and Pennsylvania Road)

Concrete work in the area has been completed and the contractor will be working to restore the area early next week.  The contractor will also be working to adjust manholes and gate valves in preparation for paving.  Paving is scheduled to be done late in the week following milling of the asphalt early next Friday and may extend into Saturday morning.

Nesbitt Area (Nesbitt Ave from 102nd to 98th and W 98th St from Nesbitt Ave to Normandale Blvd)
The contractor will continue to work on the reconstruction of existing manholes in the area and is expected to finish this work on Monday, June 13. That same day, the underground contractor will be installing new valves for the water main on W 98th St, this work will require a temporary shutdown of water for the residents in the area from 9:00 AM to 3:00 PM, Monday, June 13.  Affected residents have already been notified of the temporary shutoff via mailings.  Late next week the contractor will also be working on the removal and replacement of damaged concrete curb and sidewalks on Nesbitt.

W 98th St is scheduled to be closed from Nesbitt Avenue to Briar Road, the closure will last two weeks starting Friday, June 17 to Friday, July 1.  Residents in the area will have to follow the detour provided. The closure will be used to accommodate safe working conditions for workers and travelers alike

Lyndale Avenue (from W 94th St to W 86th St)
CenterPoint Energy has completed their work at the intersection of Lyndale and 86th St and will be working at the intersection of Lyndale and 90th St beginning on Monday, June 13.  To accommodate this work the intersection signals will be on flash and require All Way Stops.

June 9, 2016

2016-101 PMP Street Improvement Project

 

Drew Avenue area (includes Drew Avenue, Ewing Road, 103rd Street, 104th Street)
Storm sewer work is complete.  Grading and placement of class 5 is anticipated to complete by the end of the day Fri, June 10 (weather permitting).  Concrete replacement is scheduled for the week of June 13 which will be followed by fine grading of class 5 later in the week.  The first layer of bituminous is anticipated to be placed the week of June 20.

Washburn Area (includes Washburn Avenue, Vincent Avenue, Thomas Avenue, Sheridan Avenue, Russell Avenue, Queen Avenue, 87th Street and 87 ½ Street)
CenterPoint Energy continues gas main installation in this area which is anticipated to complete the week of June 13.  This will be followed by installation of the gas services which is expected to take 3-4 weeks to complete.

South Bay Area (includes South Bay Drive, South Bay Circle)
The Contractor has been granted a noise exception for Saturday, June 11 from 7:00 am – 9:00 am in this area and they plan to install drain tile in a few locations on South Bay Circle.  The removal of pavement, minor storm sewer work and grading are scheduled to start the week of June 20.

90th Street (from 12th Avenue to Old Cedar Avenue)
90th Street will be closed to through traffic from 12th Avenue to Old Cedar Avenue starting Monday, June 20.  This closure is anticipated to be in place for 6-8 weeks and a detour will be provided.  The detour will utilize Portland Avenue, 86th Street and Old Cedar Avenue.  Access will remain open for north and southbound traffic on 12th Avenue with intermittent periods of time when access will be delayed.  The Contractor is scheduled to complete pavement removal early in the week of June 20, which will be followed by minor storm and water main work.  CenterPoint Energy has complete gas main installation in this area and will start the installation of services the week of June 13.

June 3, 2016

2016-101 PMP Street Improvement Project

Drew Avenue area (includes Drew Avenue, Ewing Road, 103rd Street, 104th Street)
The Contractor has been granted a noise exception for Saturday, June 4 from 7:00 AM – 9:00 AM in this area.  Street pavement removal has started and will continue the week of June 6.  Excavation, grading and placement of class 5 is scheduled to begin late in the week of May 30 (weather permitting) and continue the week of June 6.  Storm sewer work and tree removals are scheduled to occur the week of June 6.

Washburn Area (includes Washburn Avenue, Vincent Avenue, Thomas Avenue, Sheridan Avenue, Russell Avenue, Queen Avenue, 87th Street and 87 ½ Street)
CenterPoint Energy has started gas main installation in this area and will continue the week of June 6.

South Bay Area (includes South Bay Drive, South Bay Circle)
The Contractor anticipates starting the installation of drain tile in South Bay Circle the week of June 6.  The removal of pavement and the start of street reconstruction in the area is not anticipated to begin until the week of June 20.

90th Street (from 12th Avenue to Old Cedar Avenue)
CenterPoint Energy has started gas main crossing replacement in the area.  This work is anticipated to take 2 ½ weeks to complete.  Street reconstruction in this area is not anticipated to begin until the week of June 20, however the Contractor anticipates completing tree removal in advance of the reconstruction the week of June 6.  90th Street will be closed to through traffic when street reconstruction begins and a detour will be provided.  More information will be given prior to the start of construction. 

2016-102 PMP Street Maintenance Project

Telegraph Area (includes Telegraph Road, Rhode Island Avenue and Pennsylvania Road)

Underground utility work was completed this week on Wednesday, June 1 as was the corresponding patching.  Removal and replacement of curb and gutter will be completed by week’s end with grading, patching and restoration scheduled for next week.

Nesbitt Area (Nesbitt Ave from 102nd to 98th and W 98th St from Nesbitt Ave to Normandale Blvd)

Reconstruction of existing sanitary and storm manholes is scheduled to begin Wednesday, June 8 barring any delays.  Installation of underground utilities will follow soon after.

Lyndale Avenue (from W 94th St to W 86th St)

CenterPoint Energy will begin restoration at the intersection of W 86th St and Lyndale next week beginning on Monday, June 6 and the work is expected to last a maximum of four days and continue to remain an All-Way Stop with a closure of the eastbound lanes.  Once restoration is completed traffic control will be removed and relocated to the intersection of Lyndale and W 90th St.

May 2016

May 26, 2016

2016-101 PMP Street Improvement Project
A Pre-Construction Conference was held on May 25 and the Contractor plans to begin work on the project on May 31.

Drew Avenue area (includes Drew Avenue, Ewing Road, 103rd Street, 104th Street)The Contractor plans to begin street and concrete removals in this area beginning Tues, May 31.  This will be followed by excavation, grading and placement of class 5 later in the week and the week of June 6.  Storm sewer work is scheduled for the week of June 6.

85th Street Area (includes 85th Street and 1st Avenue)
CenterPoint Energy has completed installation of gas main in this area and anticipates completing installation of services the week of May 30 (weather permitting).  Street reconstruction work in this area is not anticipated to begin until July.  More information will be given as construction nears.

Washburn Area (includes Washburn Avenue, Vincent Avenue, Thomas Avenue, Sheridan Avenue, Russell Avenue, Queen Avenue, 87th Street and 87 ½ Street)
CenterPoint Energy will be replacing gas main and services in this area and anticipates starting by early June.  This work should take approximately 6-8 weeks to complete.  Street reconstruction work in this area will not begin until CenterPoint is complete.

May 20, 2016

2016-101 PMP Street Improvement Project

A Pre-Construction Conference has been scheduled for Wed, May 25.  The Contractor anticipates starting the week of May 30.  The schedule will be confirmed after the Pre-Construction Conference as to which areas will begin first.

2016-102 PMP Street Maintenance Project

Telegraph Area (includes Telegraph Road, Rhode Island Avenue and Pennsylvania Road)
Construction is scheduled to begin early next week on Tuesday, May 24 north of Highwood Drive to the northern terminus on Telegraph Road, Rhode Island Avenue and Pennsylvania Road.  The limits of construction will also include the adjacent circles on each street.  Work will include the adjustments of the existing manholes and gate valves on each road as well as some manhole and catch basin reconstruction.

Nesbitt Area (Nesbitt Ave from 102nd to 98th and W 98th St from Nesbitt Ave to Normandale Blvd)
Advanced notice traffic control was placed earlier this week for preliminary work scheduled for next week that will include saw cutting and minor root grubbing.

Auto Club Area (included Auto Club Drive, Bluff Drive and Normandale Boulevard)
Preliminary saw cutting was completed on Bluff Drive and Normandale Boulevard this week.

Lyndale Avenue (from W 94th St to W 86th St)
CenterPoint Energy continues their installation of gas main on Lyndale and will work between 94th St and 90th St next week.

 

December 2015

December 18, 2015

2016-101 PMP Street Improvement Project
The public hearing for Drew Avenue, Ewing Road, W 103rd Street, W 104th Street, Washburn Avenue, W 87th Street, W 87 ½ Street, Vincent Avenue, Thomas Avenue, Sheridan Avenue, Russell Avenue and Queen Avenue is scheduled for December 21.

December 4, 2015

2016-101 PMP Street Improvement Project
The public hearing for Drew Avenue, Ewing Road, W 103rd Street, W 104th Street, Washburn Avenue, W 87th Street, W 87 ½ Street, Vincent Avenue, Thomas Avenue, Sheridan Avenue, Russell Avenue and Queen Avenue is scheduled for December 21.

2015-101 PMP Street Improvement Project
90th Street (from Lyndale Avenue to Wentworth Avenue): 
Bituminous paving and striping is complete. Boulevards have been restored with topsoil and hydroseeding of the boulevards is scheduled to occur the week of December 7. The signal system at 90th Street and Lyndale Avenue has been activated. Punch list work remains.  

95th Street (from Pleasant Avenue to Nicollet Avenue): 
Striping is complete. Punch list work remains.

November 2015

November 20, 2015

2016-101 PMP Street Improvement Project
The public hearing for the project was held on November 16th.  An additional public hearing is scheduled for December 21 for the streets that were continued at the November 16 hearing.  These streets include Drew Avenue, Ewing Road, W 103rd Street, W 104th Street, Washburn Avenue, W 87th Street, W 87 ½ Street, Vincent Avenue, Thomas Avenue, Sheridan Avenue, Russell Avenue and Queen Avenue.

2015-101 PMP Street Improvement Project
90th Street (from Lyndale Avenue to Wentworth Avenue): 
Raising of manholes and gate valves was delayed due to the recent rain and is scheduled to complete by the end of the week of November 16.  Paving of the final layer of bituminous is scheduled for early in the week of November 23.  Final boulevard restoration is also scheduled for early in the week of November 23.  Activation of the signal system at 90th Street and Lyndale Avenue will be scheduled after final paving and striping is complete.  

95th Street (from Pleasant Avenue to Nicollet Avenue): 
95th St has been reopened to traffic.  Boulevard restoration and paving of the final layer of bituminous are complete.  Striping is anticipated to complete by early in the week of November 23.

November 13, 2015

2015-101 PMP Street Improvement Project

90th Street (from Lyndale Avenue to Wentworth Avenue): 
Concrete replacement is anticipated to complete by the end of the week of November 9 (weather permitting). Paving of the first two layers of blacktop on the south side is complete.  Boulevard restoration along with raising of manholes and gate valves are anticipated to complete early in the week of November 16. Traffic lanes shifts will be needed to accommodate this work on both sides of the street. Paving of the final layer of bituminous along with completion of the signal work are anticipated to complete the week of November 16 (weather permitting).   

95th Street (from Pleasant Avenue to Nicollet Avenue): 
95th Street between Pleasant Avenue and Nicollet Avenue is currently closed to through traffic and will remain for the duration of construction. The Contractor has been granted a noise exception for Saturday, November 14 from 7:00 AM – 9:00 AM. Concrete work is complete. Raising of manholes and gate valves are complete. Boulevard restoration has started and is anticipated to complete by the end of the week of November 9. Paving of the final layer of bituminous is anticipated to complete the week of November 16.

November 6, 2015

2016-101 PMP Street Improvement Project
Public informational meetings were held on Monday, November 2 at 2:00PM and 5:30 PM in the Public Works Training Room. The public hearing is scheduled for November 16th.

2015-101 PMP Street Improvement Project
89th Street area (includes 89th Street, Fremont Avenue, Emerson Avenue, Colfax Avenue): 
Paving of the final layer of bituminous is complete.  Punch list work remains.         

90th Street (from Lyndale Avenue to Wentworth Avenue): 
Concrete replacement was delayed due to the wet conditions but has now started and is scheduled to complete the week of November 9. Final grading of class 5 is anticipated to begin late in the week of November 2 or early the week of November 9. This grading will be followed by paving of the first two layers of bituminous on the south side of 90th Street the week of November 9. Paving will then be followed by boulevard restoration and raising of manholes and gate valves on the 90th Street. Traffic lanes shifts will be needed to accommodate this work on both sides of the street. Signal work continues and installation of the signal poles is scheduled to begin late in the week of November 2. Signal work will continue the week of November 9.   

95th Street (from Pleasant Avenue to Nicollet Avenue): 
95th Street between Pleasant Avenue and Nicollet Avenue is currently closed to through traffic and will remain for the duration of construction.  Concrete work is scheduled to complete by the end of the week of November 2 (weather permitting).  The first layer of bituminous has been paved and raising of manholes and gate valves is scheduled to begin late in the week of November 2.  Boulevard restoration is scheduled for the week of November 9.  Paving of the final layer of bituminous is anticipated to occur late in the week of November 9 (weather permitting).

October 2015

October 30, 2015

2016-101 PMP Street Improvement Project
The first of three public informational meetings was held on Monday, October 26 at 5:30 PM in the Public Works Training Room. Public informational meetings are scheduled for November 2 at 2:00 PM and 5:30 PM for the remainder of the 2016 PMP areas in the Public Works Training Room. The public hearing is scheduled for November 16.

2015-101 PMP Street Improvement Project
89th Street area (includes 89th Street, Fremont Avenue, Emerson Avenue, Colfax Avenue): 
Sod installation is complete along with raising of manholes and gates valves. Paving of the final layer of bituminous has been delayed due to the recent weather and is anticipated to begin late in the week of October 26 (weather permitting).        

90th Street (from Lyndale Avenue to Wentworth Avenue): 
Initial grading and placement of class 5 was slightly delayed due to the recent rain but is now complete. Concrete removal is scheduled to complete late in the week of October 26 with concrete replacement to follow. Signal work at the intersection of 90th Street and Lyndale Avenue will continue the week of November 2.  

95th Street (from Pleasant Avenue to Nicollet Avenue): 
95th Street between Pleasant Avenue and Nicollet Avenue is currently closed to through traffic and will remain for the duration of construction. Concrete curb work is complete with a few sidewalk areas remaining to be completed over the next week. Final grading of class 5 prior to paving the first layer of bituminous has been slightly delayed due to the recent rain but is anticipated to begin late in the week of October 26 (weather permitting). This will be followed by paving of the first layer of bituminous the week of November 2.

October 23, 2015

2016-101 PMP Street Improvement Project
Notices regarding the 2016 PMP Street Improvement Project have been mailed to all affected properties. Public informational meetings are scheduled for October 26 at 5:30 PM for Old Cedar Avenue and November 2 at 2:00 PM and 5:30 PM for the remainder of the 2016 PMP areas in the Public Works Training Room. The public hearing is scheduled for November 16.

2015-101 PMP Street Improvement Project

Lyndale Avenue (from 82nd Street to 86th Street):  
Striping is complete along with median concrete and landscaping. Punch list work remains.        

89th Street area (includes 89th Street, Fremont Avenue, Emerson Avenue, Colfax Avenue): 
Sod installation is anticipated to complete by the end of the week of October 19 along with raising of manholes and gate valves. Paving of the final layer of bituminous is scheduled to begin the week of October 26.    

90th Street (from Lyndale Avenue to Wentworth Avenue): 
Traffic has been switched to the north side of 90th Street. Pavement removal is complete and initial grading and placement of class 5 is anticipated to complete by the end of the week of October 19 (weather permitting). Concrete removal and replacement is scheduled for the week of October 26. Signal work at the intersection of 90th Street and Lyndale Avenue will continue the week of October 26.    

95th Street (from Pleasant Avenue to Nicollet Avenue): 
95th Street between Pleasant Avenue and Nicollet Avenue is currently closed to through traffic and will remain for the duration of construction. Concrete removals along with grading and placement of class 5 is complete. Concrete work is scheduled to start late in the week of October 19 (weather permitting) and continue the week of October 26.

October 16, 2015

2016-101 PMP Street Improvement Project
Notices regarding the 2016 PMP Street Improvement Project will be mailed to all affected properties by the end of the day Friday, October 16. Public informational meetings are scheduled for October 26 at 5:30 PM and November 2 at 2:00 PM and 5:30 PM in the Public Works Training Room. The public hearing is scheduled for November 16.

2015-101 PMP Street Improvement Project

Lyndale Avenue (from 82nd Street to 86th Street):  
Final striping is anticipated to occur late in the week of October 12 or the week of October 19. Median concrete work is scheduled to complete by the end of the week of October 12. Landscaping restoration within the median will be completed by late October.         

89th Street area (includes 89th Street, Fremont Avenue, Emerson Avenue, Colfax Avenue): 
Boulevard restoration and sod installation continues and will continue the week of October 19. Raising manholes of manholes and gate valves is anticipated to complete late in the week of October 12. Paving of the final layer of bituminous in the area will begin when sod installation is nearly complete, possibly the week of October 19.    

90th Street (from Lyndale Avenue to Wentworth Avenue): 
Final grading of class 5 is complete and paving of the first two layers of bituminous on the north side will complete by the end of the week of October 12. Traffic will be switched to the north side of 90th Street with removals beginning on the south side after this paving is complete either late in the week of October 12 or early in the week of October 19. Signal work at 90th Street and Lyndale Avenue continues. The intersection is currently in a 4-way stop condition and this will remain until signal work is complete. This signal work will require the closure of Lyndale Avenue on the north side of 90th Street for a period of 1-2 days, which has been slightly delayed. East and westbound traffic on 90th Street will remain open and northbound Lyndale Avenue traffic will be able to access 90th Street during the closure. Southbound Lyndale Avenue traffic will be able to take a right to head westbound on 90th Street during the closure. This is anticipated to occur mid-late in the week of October 19. A detour will be provided for this closure.  

95th Street (from Pleasant Avenue to Nicollet Avenue): 
95th Street between Pleasant Avenue and Nicollet Avenue is currently closed to through traffic and will remain for the duration of construction. The existing gate valves and manholes have been lowered and the pavement has been removed. Concrete removals along with grading and placement of class 5 has started and will continue the week of October 19. Concrete work will follow placement of class 5.

October 9, 2015

2015-101 PMP Street Improvement Project

Lyndale Avenue (from 82nd Street to 86th Street):  
Sod and seed installation is complete. The final layer of bituminous has been paved and the signal at 84th Street and Lyndale Avenue has been activated. Minor median concrete work and landscaping restoration will be completed this Fall. A contractor is currently installing new wiring and light poles along this corridor of Lyndale Avenue under a separate Xcel Energy project.        

89th Street area (includes 89th Street, Fremont Avenue, Emerson Avenue, Colfax Avenue): 
Paving of the first layer of bituminous is complete in this area. Boulevard restoration, sod installation and bituminous driveway placement continues in the entire area and will continue the week of October 12. The Contractor will also continue raising manholes and gate valves in the entire area the week of October 12.  

90th Street (from Lyndale Avenue to Wentworth Avenue): 
Concrete curb and sidewalk replacement on the north side has started and is anticipated to complete the end of the week of October 5. Final grading of class 5 will continue after concrete work is complete the week of October 12. Paving of the first two layers of the bituminous in this area is anticipated to occur late in the week of October 12 or the week of October 19. Signal work at 90th Street and Lyndale Avenue continues. The intersection is currently in a 4-way stop condition and this will remain until signal work is complete. This signal work will require the closure of northbound Lyndale Avenue on the north side of 90th Street for a period of 1-2 days and is anticipated to occur late in the week of October 12 or the week of October 19. A detour will be provided for this closure.   

95th Street (from Pleasant Avenue to Nicollet Avenue): 
95th Street between Pleasant Avenue and Nicollet Avenue will be closed to through traffic starting Monday, October 12 for approximately 6 weeks. A detour will be provided for this closure. Access will be maintained for residents that live along the corridor, the Fire Station and school busses during this closure. The Contractor is scheduled to lower existing manholes and gate valves early in the week of October 12, followed by pavement removal and grading/placement of class 5 later in the week of October 12.

October 2, 2015

2015-101 PMP Street Improvement Project

Assessment informational meetings were held on Monday, September 28 at 2:00 PM and 5:30 PM in the Bloomington Public Works Training Room.  The assessment hearing at City Council is scheduled for Monday, October 5.

Lyndale Avenue (from 82nd Street to 86th Street): Sod and seed installation has started and is anticipated to complete late in the week of September 28.  The final layer of bituminous is anticipated to be paved early in the week of October 5.  The signal at 84th Street and Lyndale Avenue will be turned on after paving of the final layer of bituminous is complete.  Minor median landscaping restoration will remain after the final layer of bituminous is paved.

89th Street area (includes 89th Street, Fremont Avenue, Emerson Avenue, Colfax Avenue):  The Contractor has been granted a noise exception for Saturday, October 3 from 7:00 AM – 9:00 AM in this area.  Concrete curb and driveway replacement on Emerson Avenue and Colfax Avenue is mostly complete with a minor amount of work to complete the week of October 5.  Paving of the first layer of bituminous on Fremont Avenue from 90th Street to 87th Street is complete and the remainder of Fremont Avenue along with 89th Street is anticipated to complete late in the week of September 28 (weather permitting).  This will be followed by boulevard restoration and paving of bituminous driveways.  Fine grading of class 5 on Emerson Avenue and Colfax Avenue is anticipated to complete early in the week of October 5, which will be followed by paving of the first layer of bituminous.  The Contractor has also started raising manholes and gate valves on the streets that have been paved and this will continue as more streets receive the first layer of bituminous.

90th Street (from Lyndale Avenue to Wentworth Avenue):  The Contractor has been granted a noise exception for Saturday, October 3 from 7:00 AM – 9:00 AM in this area.  Grading and placement of class 5 on the north side of 90th Street is anticipated to complete by the end of the week of September 28.  Concrete curb and sidewalk replacement on the north side is anticipated to occur the week of October 5.  Signal work at 90th Street and Lyndale Avenue has started and will continue the week of October 5.  The intersection is currently in a 4-way stop condition and this will remain until signal work is complete.

95th Street (from Pleasant Avenue to Nicollet Avenue):  Street reconstruction is anticipated to begin in this area the week of October 12.  95th Street between Pleasant Avenue and Nicollet Avenue will be closed to through traffic for the duration of construction with a detour provided.  The detour will utilize Lyndale Avenue, Old Shakopee Road and Nicollet Avenue.  Access will be maintained for residents that live along the corridor, the Fire Station and school busses during this closure.

September 2015

September 25, 2015

2015-101 PMP Street Improvement Project
Assessment informational meetings are scheduled for Monday, September 28 at 2:00 PM and 5:30 PM in the Bloomington Public Works Training Room. The public hearing is scheduled for Monday, October 5. Mailings have been sent to affected property owners regarding these meetings.  

Lyndale Avenue (from 82nd Street to 86th Street):  
Sod and seed installation has been delayed due to the recent rain and is anticipated to start late in the week of September 21 or early in the week of September 28. The final layer of bituminous is anticipated to be paved the week of September 28 (weather permitting). The signal at 84th Street and Lyndale Avenue will be turned on after paving of the final layer of bituminous is complete. Minor median landscaping restoration will remain after the final layer of bituminous is paved.          

89th Street area (includes 89th Street, Fremont Avenue, Emerson Avenue, Colfax Avenue): 
The Contractor has been granted a noise exception for Saturday, September 26 from 7:00 AM – 9:00 AM for concrete and paving work in this area. Concrete curb and driveway replacement on Emerson Avenue and Colfax Avenue has been delayed due to the recent rain and is anticipated to begin late in the week of September 21. Paving of the first layer of bituminous on Fremont Avenue was also delayed due to the rain and is scheduled for late in the week of September 21 (weather permitting). This will be followed by boulevard restoration and paving of bituminous driveways. Fine grading of class 5 on 89th Street along with paving of the first layer of bituminous is anticipated to complete the week of September 28.  

90th Street (from Lyndale Avenue to Wentworth Avenue): 
The Contractor has been granted a noise exception for Saturday, September 26 from 7:00 AM – 9:00 AM for grading in the area. Concrete removals along with grading and placement of class 5 on the north side of 90th Street was delayed due to the recent rain, but has started once again and will continue the week of September 28. Concrete curb and sidewalk replacement will occur after placement of class 5. Signal work at 90th Street and Lyndale Avenue is also anticipated to begin the week of September 28. The intersection will be placed in a 4-way stop condition when work occurs on the signal over the next few weeks. CenterPoint Energy has complete gas main and service installation in this area. 

95th Street (from Pleasant Avenue to Nicollet Avenue): 
Street reconstruction is anticipated to begin in this area in early-mid October.

September 23, 2015

As part of the feasibility investigation for the trail and road improvements along Old Cedar Avenue north of the bridge, geotechnical information will be gathered. One of the boring locations will require removal of brush to provide access for the drill rig. City crews will be out brushing this location as time permits. Braun Intertec has indicated that their rig schedule is out six weeks, but it may occur sooner if there is a cancellation especially given the proximity of the site to their office.

September 18, 2015

2015-101 PMP Street Improvement Project

Lyndale Avenue
 (from 82nd Street to 86th Street):  
The Contractor has been granted a noise exception for Saturday, September 19 from 7:00 AM – 9:00 AM for final milling and patching in this area. Raising of manholes and gate valves in this area is complete. Concrete work is complete except for some minor median work. Sod and seed installation is scheduled to start late in the week of September 14 (weather permitting) and continue the week of September 21. The final layer of bituminous is anticipated to be paved the week of September 21. Electrical work at the 84th Street and Lyndale Avenue intersection is anticipated to complete late in the week of September 14, with the signal being turned on after paving of the final layer of bituminous is complete. Minor median landscaping restoration will remain after the final layer of bituminous is paved.     

89th Street area (includes 89th Street, Fremont Avenue, Emerson Avenue, Colfax Avenue): 
Concrete curb and driveway replacement is complete on Fremont Avenue and most of 89th Street with the remainder to complete the week of September 21. Concrete curb and driveway replacement on Emerson Avenue and Colfax Avenue is anticipated to begin the week of September 21. Fine grading of class 5 in preparation for the first layer of bituminous on Fremont Avenue is nearly complete and paving of the first layer of bituminous is scheduled for early in the week of September 21. This will be followed by boulevard restoration and paving of bituminous driveways. Fine grading of class 5 on 89th Street along with paving of the first layer of bituminous is anticipated to begin the week of September 21.  

90th Street (from Lyndale Avenue to Wentworth Avenue): 
Storm sewer work is complete. Pavement removal on the north half of 90th Street is complete and traffic has been shifted to the south side of 90th Street with one lane in both directions. Grading and placement of class 5 has started and will continue the week of September 21. CenterPoint Energy has started replacing approximately 500’ of gas main on the north side of 90th Street from Lyndale Avenue to the east and will complete early in the week of September 21. This work will require northbound Lyndale Avenue to be closed for 1-2 days at the north side of the 90th Street intersection to allow for the gas main connection at the intersection of 90th Street and Lyndale Avenue. Southbound Lyndale Avenue will remain open during this closure along with east and westbound traffic on 90th Street at Lyndale Avenue. This closure is scheduled to begin on Monday, September 21 and reopen by the end of the day on Tuesday, September 22.

2015-102 PMP Street Maintenance Project

Rich Area (includes Rich Avenue, Palmer Avenue, Quinn Avenue, Stanley Avenue, Toledo Avenue, West 109th Street, Toledo Circle, West 108th Street): 
Sod installation is complete. Punch list work remains.

September 10, 2015

2015-101 PMP Street Improvement Project

Lyndale Avenue
 (from 82nd Street to 86th Street):  
Raising of manholes and gate valves in this area continues and is anticipated to complete the week of September 14. Concrete work is nearly complete with primarily median work remaining, which is anticipated to complete the week of September 14. Electrical work at the 84th Street and Lyndale Avenue signal continues and is anticipated to complete the week of September 14. Boulevard restoration and placement of topsoil is nearly complete with sod and seed installation anticipated to begin the week of September 14. Traffic will be shifted as needed to the outer and inner lanes as restoration completes in the boulevard and median.        

89th Street area (includes 89th Street, Fremont Avenue, Emerson Avenue, Colfax Avenue): 
Grading and initial placement of class 5 is complete. Concrete curb and driveway replacement is complete on Fremont Avenue between 90th Street and 87th Street along with a portion of 89th Street. Fine grading of class 5 in preparation for the first layer of bituminous in the area that has received curb is scheduled for the week of September 14. Concrete curb and driveway replacement in the remainder of the 89th Street area is scheduled to begin mid-week of September 14.  

Dupont Avenue (from 90th Street to 92nd Street): 
Paving of the final layer of bituminous is complete. Punch list work remains.

90th Street (from Lyndale Avenue to Wentworth Avenue): 
The Contractor has been granted a noise exception for Saturday, September 12 from 7:00 AM – 9:00 AM for pavement removal in this area. Storm sewer work on the south side of 90th Street is complete and the north side is anticipated to complete the week of September 14 after the pavement is removed. Traffic will be shifted to the south side of 90th Street with one lane in both directions late in the week of September 7 and the Contractor will remove the pavement on the north half of the street. CenterPoint Energy will be replacing approximately 500’ of gas main on the north side of 90th Street from Lyndale Avenue to the east the week of September 14 after the pavement is removed. This work will require northbound Lyndale Avenue to be closed for 1 day at 90th Street to allow for the gas main connection at the intersection of 90th Street and Lyndale Avenue. Southbound Lyndale Avenue will remain open during this closure along with east and westbound traffic on 90th Street at Lyndale Avenue. This is anticipated to occur early in the week of September 21 and more information will be given when a schedule is determined.

2015-102 PMP Street Maintenance Project

Rich Area (includes Rich Avenue, Palmer Avenue, Quinn Avenue, Stanley Avenue, Toledo Avenue, West 109th Street, Toledo Circle, West 108th Street): 
Milling and paving is complete. Final sod installation is scheduled to start late in the week of September 7 and complete the week of September 14.

September 4, 2015

2015-101 PMP Street Improvement Project

Lyndale Avenue
 (from 82nd Street to 86th Street):  
Paving of the first two layers of bituminous on the west side of Lyndale Avenue is complete. Raising of manholes and gate valves in this area has started and will continue the week of September 7. The remaining concrete work and boulevard restoration on the entire corridor will be done under lane closures starting the week of September 7. Electrical work at the 84th Street and Lyndale Avenue signal continues.      

89th Street area (includes 89th Street, Fremont Avenue, Emerson Avenue, Colfax Avenue): 
Grading and placement of class 5 continues and is anticipated to complete the week of September 7. Concrete curb and driveway replacement has started and will continue the week of September 7. 

Dupont Avenue (from 90th Street to 92nd Street): 
Paving of the final layer of bituminous is anticipated to complete late in the week of August 31 or the week of September 7.

90th Street (from Lyndale Avenue to Wentworth Avenue): 
Storm sewer work continues and is anticipated to complete the week of September 7. The Contractor anticipates removing the north half of 90th Street late in the week of September 7, shifting traffic to one lane in both directions on the south side of 90th Street.

2015-102 PMP Street Maintenance Project

Rich Area (includes Rich Avenue, Palmer Avenue, Quinn Avenue, Stanley Avenue, Toledo Avenue, West 109th Street, Toledo Circle, West 108th Street): 
Bituminous patching and raising of manholes are complete. Boulevard restoration has started and will complete the week of September 7. Milling and paving of the area is anticipated to occur the week of September 7.

Nicollet Avenue, W 102nd Street (includes Nicollet Avenue from West 98th Street to West 102nd Street, West 102nd Street from Lyndale Avenue to Nicollet Avenue): 
Boulevard restoration, milling and paving is complete. Punch list work remains.

Auto Club Road Retaining Wall: 
Topsoil and turf restoration is complete along with paving of the final layer of bituminous on Auto Club Road. Punch list work remains.

 

August 2015

August 28, 2015

2015-101 PMP Street Improvement Project

Lyndale Avenue
 (from 82nd Street to 86th Street):  
Paving of the first two layers of bituminous on the west side of Lyndale Avenue has started and is anticipated to complete by the end of the week of August 24 (weather permitting). Concrete replacement is nearly complete and the remainder will be done under lane closures after paving is complete. Boulevard restoration is anticipated to start the week of August 31. Electrical work at the 84th Street and Lyndale Avenue signal continues.    

89th Street area (includes 89th Street, Fremont Avenue, Emerson Avenue, Colfax Avenue): 
Storm sewer work in the area is complete. Grading and placement of class 5 has started and will continue the week of August 31. Concrete curb and driveway replacement is scheduled to start mid-week of August 31.  

Dupont Avenue (from 90th Street to 92nd Street): 
Boulevard restoration and raising of manholes and gate valves is complete. Paving of the final layer of bituminous is anticipated to complete late in the week of August 24 (weather permitting) or the week of August 31.

90th Street (from Lyndale Avenue to Wentworth Avenue): 
Work has started in this area, which includes manhole reconstruction and storm sewer work in the center lanes with traffic remaining open to one lane in both directions in the outer lanes. This phase of storm sewer work is anticipated to complete mid-late in the week of August 31. The Contractor anticipates removing the north half of 90th Street the week of September 7, shifting traffic to one lane in both directions on the south side of 90th Street.

2015-102 PMP Street Maintenance Project

Rich Area (includes Rich Avenue, Palmer Avenue, Quinn Avenue, Stanley Avenue, Toledo Avenue, West 109th Street, Toledo Circle, West 108th Street): 
The Contractor has been granted a noise exception for Saturday, August 29 from 7:00 AM – 9:00 AM in this area. Concrete replacement is complete. Bituminous patching and raising of manholes and gate valves will complete early in the week of August 31. Boulevard restoration is scheduled for the week of August 31. Milling and paving of the area is anticipated to occur the week of September 7.

Minnesota Drive, Johnson Avenue and W 78th Street (includes Minnesota Drive from Johnson Avenue to Edinborough Way, Johnson Avenue from Minnesota Drive to West: 
Punch list work remains.

Nicollet Avenue, W 102nd Street (includes Nicollet Avenue from West 98th Street to West 102nd Street, West 102nd Street from Lyndale Avenue to Nicollet Avenue): 
The Contractor has been granted a noise exception for Saturday, August 29 from 7:00 AM – 9:00 AM in this area. Milling is complete and paving is anticipated to complete late in the week of August 24 (weather permitting). Boulevard restoration is scheduled to complete the week of August 31.

Auto Club Road Retaining Wall: 
The Contractor has been granted a noise exception for Saturday, August 29 from 7:00 AM – 9:00 AM in this area. Sidewalk and fence installation is complete. Grading of class 5 and paving of the first layer of bituminous on Auto Club Road is complete. Topsoil and turf restoration has started and will complete the week of August 31. Paving of the final layer of bituminous on Auto Club Road is anticipated to occur the week of September 7.

August 21, 2015

2015-101 PMP Street Improvement Project

Lyndale Avenue
 (from 82nd Street to 86th Street):  
The Contractor has been granted a noise exception for Saturday, August 22 from 7:00 AM – 9:00 AM in this area. Concrete replacement in the area has been delayed due to the recent rain and is anticipated to begin late in the week of August 17 and continue the week of August 24. Final grading of class 5 will follow concrete replacement the week of August 24. Paving of the first two layers of bituminous in the current phase on the west side of Lyndale Avenue will follow class 5 grading late in the week of August 24 (weather permitting). Electrical work at the 84th Street and Lyndale Avenue signal continues. 

89th Street area (includes 89th Street, Fremont Avenue, Emerson Avenue, Colfax Avenue): 
Storm sewer work in the area is anticipated to complete early in the week of August 24. Grading and placement of class 5 has been delayed due to the recent rain and is scheduled to start on 89th Street and Fremont Avenue early in the week of August 24 and then continue to Colfax Avenue and Emerson Avenue. Concrete curb and driveway replacement is anticipated to begin mid to late in the week of August 24.

Park Avenue (from 90th Street to 88th Street): 
Paving of the final layer of bituminous is complete. Punch list work remains.

Dupont Avenue (from 90th Street to 92nd Street): 
Boulevard restoration was delayed due to the recent rain and is anticipated to complete by the end of the week of August 17 with sod installation to follow early in the week of August 24 (weather permitting). Raising of manholes and gate valves has started and is anticipated to complete late in the week of August 17. The remaining concrete work  will complete late in the week of August 17 or early in the week of August 24. Paving of the final layer of bituminous is anticipated to occur late in the week of August 24.

90th Street (from Lyndale Avenue to Wentworth Avenue): 
The Contractor is anticipating starting work in this area late in the week of August 24. The first phase will include a closure of the inner lanes with traffic moved to the outer lanes in both directions. During this phase the existing median at Lyndale Avenue will be removed and manholes will be reconstructed.

2015-102 PMP Street Maintenance Project

Rich Area (includes Rich Avenue, Palmer Avenue, Quinn Avenue, Stanley Avenue, Toledo Avenue, West 109th Street, Toledo Circle, West 108th Street): 
The Contractor has been granted a noise exception for Saturday, August 22 from 7:00 AM – 9:00 AM in this area. Manhole reconstruction and storm sewer work is complete. Concrete replacement has started and will complete early in the week of August 24. Bituminous patching and raising of manholes and gate valves are scheduled for the week of August 24.

Minnesota Drive, Johnson Avenue and W 78th Street (includes Minnesota Drive from Johnson Avenue to Edinborough Way, Johnson Avenue from Minnesota Drive to West: 
Final paving on West 78th Street, Johnson Avenue and Minnesota Drive is complete. Final striping in the area has been slightly delayed due to the weather and is scheduled to complete late in the week of August 17.

Nicollet Avenue, W 102nd Street (includes Nicollet Avenue from West 98th Street to West 102nd Street, West 102nd Street from Lyndale Avenue to Nicollet Avenue): 
The Contractor has been granted a noise exception for Saturday, August 22 from 7:00 AM – 9:00 AM in this area. Concrete replacement is complete. Boulevard restoration along with manhole and gate valve adjustment was slightly delayed due to the recent weather and is scheduled to continue late in the week of August 17 and the week of August 24. Final milling and paving is scheduled for the week of August 24.

Auto Club Road Retaining Wall: 
The Contractor has been granted a noise exception for Saturday, August 22 from 7:00 AM – 9:00 AM in this area. Concrete curb and gutter installation is complete on Auto Club Road adjacent to the wall. Sidewalk is anticipated to be installed late in the week of August 17 and fence installation is scheduled for the week of August 24. Grading of class 5 and paving of the first layer of bituminous on Auto Club Road is also scheduled for the week of August 24. This will be followed by topsoil and turf restoration in front of the wall.

August 14, 2015

2015-101 PMP Street Improvement Project

Lyndale Avenue
 (from 82nd Street to 86th Street):  
Grading and placement of class 5 on the west side of Lyndale Avenue is complete.  Concrete removal continues and concrete replacement is scheduled for the week of August 17.  Final grading of class 5 will follow concrete replacement.  Paving of the first two layers of bituminous in the current phase on the west side of Lyndale Avenue has been delayed slightly and is anticipated to occur late in the week of August 17 or the week of August 24.  Electrical work at the 84th Street and Lyndale Avenue signal continues.

89th Street area (includes 89th Street, Fremont Avenue, Emerson Avenue, Colfax Avenue): 
Storm sewer work on 89th Street and Fremont Avenue is complete.  Storm sewer work on Emerson Avenue and Colfax Avenue has started and will complete the week of August 17.  Grading and placement of class 5 on 89th Street and Fremont Avenue is scheduled for the week of August 17, which will be followed by concrete curb and driveway installation late in the week of August 17 or early in the week of August 24.  Pavement removal on Colfax Avenue and Emerson Avenue is complete.

Park Avenue (from 90th Street to 88th Street): 
Boulevard restoration, sod installation and paving of bituminous driveways are anticipated to complete by the end of the week of August 10.  Paving of the final layer of bituminous is anticipated to occur the week of August 17.

Dupont Avenue (from 90th Street to 92nd Street): 
Paving of the first layer of bituminous is complete.  Boulevard restoration will continue the week of August 17.  Raising of manholes and gate valves in preparation for the final layer of bituminous is scheduled for the week of August 17.  Paving of the final layer of bituminous is anticipated to occur late in the week of August 17 or the week of August 24.

90th Street (from Lyndale Avenue to Wentworth Avenue): 
The Contractor is anticipating starting pavement removal in this area the week of August 24.  More information will be given when a schedule is determined. 
 

2015-102 PMP Street Maintenance Project

Rich Area (includes Rich Avenue, Palmer Avenue, Quinn Avenue, Stanley Avenue, Toledo Avenue, West 109th Street, Toledo Circle, West 108th Street): 
Manhole reconstruction and storm sewer work is anticipated to complete by the end of the week of August 10.  Concrete removal and replacement is scheduled for the week of August 17.

Minnesota Drive, Johnson Avenue and W 78th Street (includes Minnesota Drive from Johnson Avenue to Edinborough Way, Johnson Avenue from Minnesota Drive to West 78th Street, West 78th Street from West 78th St Circle to Johnson Avenue): 
The Contractor has been granted a noise exception for Thursday, August 13 to Saturday, August 15 from 3:00 AM-7:00 AM for milling and paving in the area.  Milling of West 78th Street and Johnson Avenue is complete.  Final paving on West 78th Street, Johnson Avenue and Minnesota Drive is scheduled for Friday, August 14 and Saturday, August 15 (weather permitting).  Sanitary sewer work on West 78th Street is complete and West 78th Street has been re-opened to traffic in the location of this work.  Final striping in the area is scheduled for the week of August 17

Nicollet Avenue, W 102nd Street (includes Nicollet Avenue from West 98th Street to West 102nd Street, West 102nd Street from Lyndale Avenue to Nicollet Avenue): 
The Contractor has been granted a noise exception for Saturday, August 15 from 7:00 AM-9:00 AM in this area.  Concrete removal and replacement is anticipated to complete by the end of the week of August 10.  Boulevard restoration along with manhole and gate valve adjustment is scheduled for the week of August 17.  Final milling and paving has been slightly delayed and is anticipated to occur the week of August 24.

Auto Club Road Retaining Wall: 
Installation of the retaining wall is complete.  Restoration on Auto Club Road in the boulevard and around the new retaining wall is scheduled for the weeks of August 17 and 24.   Traffic is currently shifted to the west bound side of Auto Club Road with one lane in both directions.

August 7, 2015

2015-101 PMP Street Improvement Project

Lyndale Avenue (from 82nd Street to 86th Street)
Grading and placement of class 5 in the current phase on the west side of Lyndale Avenue is anticipated to complete late in the week of August 3.  Concrete removal and replacement has started and will continue the week of August 10.  Final grading of class 5 will follow concrete replacement.  Paving of the first two layers of bituminous in the current phase on the west side of Lyndale Avenue is anticipated to occur early in the week of August 17.  Electrical work at the 84th Street and Lyndale Avenue signal continues.

89th Street area (includes 89th Street, Fremont Avenue, Emerson Avenue, Colfax Avenue)
Storm sewer work on 89th Street and Fremont Avenue is anticipated to complete early in the week of August 10.  Grading and placement of class 5 will follow storm sewer work on 89th Street and Fremont Avenue.  Pavement removal on Colfax Avenue and Emerson Avenue is anticipated to occur early in the week of August 10.  This will be followed by storm sewer work the remainder of the week of August 10.

Park Avenue (from 90th Street to 88th Street)
Boulevard restoration and sod installation is anticipated to complete late in the week of August 3 along with paving of bituminous driveways (weather permitting).  Paving of the final layer of bituminous is anticipated to occur late in the week of August 10 or early in the week of August 17.

Dupont Avenue (from 90th Street to 92nd Street)
Final grading of class 5 is nearly complete and paving of the first layer of bituminous is anticipated to complete late in the week of August 3 or early in the week of August 10.  Boulevard restoration, paving of bituminous driveways and raising manholes and gate valves in preparation for the final layer of bituminous are scheduled for the week of August 10.

2015-102 PMP Street Maintenance Project

Rich Area (includes Rich Avenue, Palmer Avenue, Quinn Avenue, Stanley Avenue, Toledo Avenue, West 109th Street, Toledo Circle, West 108th Street)
Tree removal is complete.  Manhole reconstruction and storm sewer work is scheduled to start late in the week of August 3 and continue the week of August 10.  Concrete removal and replacement is anticipated to occur the week of August 17.

Minnesota Drive, Johnson Avenue and W 78th Street (includes Minnesota Drive from Johnson Avenue to Edinborough Way, Johnson Avenue from Minnesota Drive to West 78th Street, West 78th Street from West 78th St Circle to Johnson Avenue)
The Contractor has been granted a noise exception for Saturday, August 8 from 7:00 AM-9:00 AM and for Monday, August 10 from 5:00 AM-7:00 AM in this area.  Signal loop installation on Minnesota Drive is complete.  Sanitary sewer work on West 78th Street just south of Johnson Avenue is complete.  Restoration of West 78th Street in this location has started and will complete early in the week of August 10.  West 78th Street just south of Johnson Avenue is closed and is anticipated to re-open mid-week of August 10.  A detour is provided for the closure that will utilize Computer Avenue, West 77th Street and Johnson Avenue.  Final milling and paving of 78th Street, Johnson Avenue and Minnesota Drive is anticipated to occur late in the week of August 10.  The Contractor is anticipating starting this milling and paving operation early in the AM due to the high traffic levels in the area.

Nicollet Avenue, W 102nd Street (includes Nicollet Avenue from West 98th Street to West 102nd Street, West 102nd Street from Lyndale Avenue to Nicollet Avenue)
The Contractor has been granted a noise exception for Saturday, August 8 from 7:00 AM-9:00 AM in this area.  Manhole reconstruction in this area is complete.  Concrete removal and replacement has started and will complete the week of August 10.  Manhole and gate valve adjustment along with boulevard restoration is scheduled for the week of August 10.  Final milling and paving is anticipated to occur the week of August 17.

Auto Club Road Retaining Wall
The Contractor has been granted a noise exception for Saturday, August 8 from 7:00 AM-9:00AM in this area.  Concrete and bituminous removals are complete.  Xcel energy has also competed relocation of their existing underground line.  Retaining wall removal is complete and installation of the new retaining wall will continue the week of August 10.  Traffic is currently shifted to the west bound side of Auto Club Road with one lane in both directions.

July 2015

July 30, 2015

2015-101 PMP Street Improvement Project

Lyndale Avenue (from 82nd Street to 86th Street):
Storm sewer work in the current phase on the west side of Lyndale Avenue is complete.  Grading and placement of class 5 is scheduled to start late in the week of July 27 and continue the week of August 3.  Concrete removal and replacement is also anticipated to begin the week of August 3.  Electrical work at the 84th Street/Lyndale Avenue signal continues.   

1st Avenue (from 100th Street to 102nd Street):
Minor sod work and punch list work remains.  Remaining sod installation is scheduled for the week of August 3.

11th Avenue (from 98th Street to 100th Street): 
Minor sod work and punch list work remains.  Remaining sod installation is scheduled for the week of August 3.

89th St area (includes 89th Street, Fremont Avenue, Emerson Avenue, Colfax Avenue): 
Pavement removal on Fremont Avenue and 89th Street is complete.  Storm sewer work has started in the area and will continue the week of August 3.  Grading and placement of class 5 will follow storm sewer work late in the week of August 3 or the week of August 10.  Pavement removal on Colfax Avenue and Emerson Avenue is anticipated to occur the week of August 10. 

Park Avenue (from 90th Street to 88th Street): 
Paving of the first layer of bituminous is complete.  Boulevard restoration has started and will continue the week of August 3.  Paving of bituminous driveways is anticipated to occur late in the week of July 27 or the week of August 3.

Dupont Avenue (from 90th Street to 92nd Street):
Concrete work has started and will continue the week of August 3.  Final grading of class 5 will follow concrete work the week of August 3.  Paving of the first layer of bituminous is anticipated to occur late in the week of August 3 (weather permitting).

2015-102 PMP Street Maintenance Project

Rich Area (includes Rich Ave, Palmer Ave, Quinn Ave, Stanley Ave, Toledo Ave, W 109th St, Toledo Cir, W 108th St):
The Contractor is scheduled to remove trees in this area the week of August 3 along with starting manhole reconstruction and storm sewer work.  Concrete removal and replacement is anticipated to occur the week of August 10.

Minnesota Drive, Johnson Avenue and W 78th Street (includes Mn Drive from Johnson Ave to Edinborough Way, Johnson Ave from Mn Drive to W 78th St, W 78th St from W 78th St Cir to Johnson Ave):
The Contractor has been granted a noise exception for Sat, August 1 from 7am-9am in this area.  Paving of the first layer of bituminous on Minnesota Drive is complete.  Signal loop installation on Minnesota Drive is anticipated to complete by the end of the day Fri, July 31.  Sanitary sewer work on W 78th Street just south of Johnson Avenue is scheduled to start on Mon, Aug 3.  W 78th Street just south of Johnson Avenue will be closed starting Fri, July 31 to begin removals for the sanitary sewer work.  This closure is anticipated to last 1- 1 ½ weeks and a detour will be provided for the closure that will utilize Computer Avenue, W 77th Street and Johnson Avenue.  Final milling and paving of 78th Street and Johnson Avenue will occur upon completion of this sanitary sewer work along with the remaining concrete work and boulevard restoration in this area.

Nicollet Avenue, W 102nd Street (includes Nicollet Ave from W 98th St to W 102nd St, W 102nd St from Lyndale Ave to Nicollet Ave):
The Contractor has been granted a noise exception for Sat, August 1 from 7am-9am in this area.  Manhole reconstruction in this area has started and is anticipated to complete by the end of the week of July 31.  Concrete removal and replacement is scheduled for the week of August 3.

Auto Club Road Retaining Wall
Concrete and bituminous removals adjacent to the retaining wall are scheduled to begin Mon, August 3.  Xcel energy will be relocating an existing underground electric line mid-week of August 3 with removal of the existing retaining wall starting later in the week of August 3.  Traffic will be shifted to the west bound side of Auto Club Road for the duration of the work with one lane maintained in both directions.

July 24, 2015

2015-101 PMP Street Improvement Project

Lyndale Avenue (from 82nd Street to 86th Street):
Placement of class 5 is complete and paving of the first two layers of bituminous on the east side is complete and traffic has been switched to the east side.  The second phase of construction on the west side has started and pavement removals are complete.  Storm sewer work has started and is anticipated to complete by the end of the week of July 20.  Grading and placement of class 5 is scheduled for the week of July 27, which will be followed by concrete removal and replacement.   

1st Avenue (from 100th Street to 102nd Street):
Minor sod work and punch list work remains.

11th Avenue (from 98th Street to 100th Street): 
Concrete work is scheduled to complete by the end of the week of July 20.  Minor sod work and punch list work remains.

89th St area (includes 89th Street, Fremont Avenue, Emerson Avenue, Dupont Avenue, Colfax Avenue): 
Pavement removal on Fremont Avenue and 89th Street has started and will complete by the end of the week.  Lowering of manholes and gate valves in advance of the pavement removal is complete.  Storm sewer work on the street segments that have been removed is scheduled for the week of July 27

Park Avenue (from 90th Street to 88th Street): 
Final grading of class 5 and paving of the first layer of bituminous is anticipated complete by the end of the week of July 20 (weather permitting).  Boulevard restoration is scheduled for the week of July 27.

Dupont Avenue (from 90th Street to 92nd Street):Concrete work has been slightly delayed and is scheduled for early in the week of July 27.  This will be followed by final grading of the class 5 prior to paving the first layer of bituminous.

2015-102 PMP Street Maintenance Project

Rich Area (includes Rich Ave, Palmer Ave, Quinn Ave, Stanley Ave, Toledo Ave, W 109th St, Toledo Cir, W 108th St):
CenterPoint Energy is complete in this area.  The Contractor for the 2015-102 Project anticipates starting manhole reconstruction and storm sewer work in the area the week of August 3.

Minnesota Drive, Johnson Avenue and W 78th Street (includes Mn Drive from Johnson Ave to Edinborough Way, Johnson Ave from Mn Drive to W 78th St, W 78th St from W 78th St Cir to Johnson Ave):
The Contractor has been granted a noise exception for Fri, July 24 and Sat, July 25 from 3am-7am in this area.  Minnesota Drive is scheduled to be milled on Fri, July 24 and the first of two layers of bituminous will be paved on Sat, July 25 starting at 3am both days.  Boulevard restoration will continue the week of July 27 along with signal loop installation on Minnesota Drive.  Sanitary sewer work on W 78th Street just south of Johnson Avenue is anticipated to start on Mon, Aug 3.  This will require the closure of 78th Street just south of Johnson Avenue and is scheduled to close starting Fri, July 31 to begin removals for the sanitary sewer work.  This closure is anticipated to last 1 week and a detour will be provided for the closure that will utilize Computer Avenue, W 76th Street and Johnson Avenue.  Final milling and paving of 78th Street and Johnson Avenue will occur upon completion of this sanitary sewer work along with the remaining concrete work and boulevard restoration in this area.

Nicollet Avenue, W 102nd Street (includes Nicollet Ave from W 98th St to W 102nd St, W 102nd St from Lyndale Ave to Nicollet Ave):
Tree removals are complete in this area.  The Contractor anticipates starting manhole reconstruction in this area the week of July 27 which will be followed by concrete removal and replacement the week of August 3.

Auto Club Road Retaining Wall
Removal and replacement of the retaining wall adjacent to 6901/6970 Auto Club Road is anticipated to begin the week of August 3.  Tree removals adjacent to the wall are complete.

July 17, 2015

2015-101 PMP Street Improvement Project

Lyndale Avenue (from 82nd Street to 86th Street):
Placement of class 5 is complete and paving of the first two layers of bituminous on the east side is scheduled to complete by Fri, July 17 (weather permitting).  Depending on the paving progress, the Contractor plans to switch traffic to the east side of Lyndale Avenue and begin pavement removals on the west side late in the week of July 13 or the week of July 20.  Pavement removal will be followed by storm sewer work the week of July 20.  Minor signal work and concrete work at the intersection of 84th Street/Lyndale Avenue is scheduled for the week of July 20.    

1st Avenue (from 100th Street to 102nd Street):
Paving of the final layer of bituminous is complete.  A minor amount of sod work remains and is anticipated to be completed the week of July 20.  Punch list work remains.

11th Avenue (from 98th Street to 100th Street): 
Paving of the final layer of bituminous is complete.  A minor amount of concrete sidewalk replacement remains and is scheduled to complete the week of July 20.  Punch list work remains.

89th St area (includes 89th Street, Fremont Avenue, Emerson Avenue, Dupont Avenue, Colfax Avenue): 
CenterPoint Energy gas service installation is complete.  The 2015-101 Contractor has started manhole reconstruction in the area and will continue storm sewer work the week of July 27 after pavement removal has started in the area.  Lowering of manholes and gate valves and pavement removal is anticipated to start late in the week of July 20 or early in the week of July 27.  

Park Avenue (from 90th Street to 88th Street): 
Concrete work is complete.  Final grading of class 5 and paving of the first layer of bituminous is anticipated to occur the week of July 20, which will be followed by boulevard restoration.

Dupont Avenue (from 90th Street to 92nd Street):
Storm sewer installation is complete.  Initial grading and placement of class 5 is complete.  Concrete work is scheduled for early in the week of July 20.

2015-102 PMP Street Maintenance Project

Rich Area (includes Rich Ave, Palmer Ave, Quinn Ave, Stanley Ave, Toledo Ave, W 109th St, Toledo Cir, W 108th St):
CenterPoint Energy is scheduled to complete work in this area late in the week of July 13.  The 2015-102 Project work is anticipated to begin in early-mid August in this area.

Minnesota Drive, Johnson Avenue and W 78th Street (includes Mn Drive from Johnson Ave to Edinborough Way, Johnson Ave from Mn Drive to W 78th St, W 78th St from W 78th St Cir to Johnson Ave):
The Contractor has been granted a noise exception for Saturday, July 18 from 7am – 9am in this area.  Concrete sidewalk removal and replacement is complete.  Manhole reconstruction along with minor storm sewer work is also complete.  Boulevard restoration has started and will continue the week of July 20.  Milling and paving of Minnesota Drive between Johnson Avenue and Edinborough Way is anticipated to occur the week of July 27.  Sanitary sewer work on W 78th Street just south of Johnson Avenue is anticipated to occur in early August upon completion of private utility relocation.  More information will be given when a schedule is determined as this will require the closure of 78th Street just south of Johnson Avenue.  Final milling and paving of 78th Street and Johnson Avenue will occur upon completion of this sanitary sewer work along with the remaining concrete work and boulevard restoration in this area.

Nicollet Avenue, W 102nd Street (includes Nicollet Ave from W 98th St to W 102nd St, W 102nd St from Lyndale Ave to Nicollet Ave):
The Contractor anticipates starting manhole reconstruction and concrete removals in this area the week of July 27.

July 9, 2015

2015-101 PMP Street Improvement Project

Lyndale Avenue (from 82nd Street to 86th Street):
Work continues on the current phase on the east side of Lyndale Avenue.  Placement of class 5 is complete and concrete replacement is scheduled to start late in the week of July 6.  Signal work at the intersection of 84th Street and Lyndale Avenue for the current phase is scheduled to complete early in the week of July 13.  Final grading of class 5 and paving of the first two layers of bituminous are anticipated to occur the week of July 13.  Upon completion of this paving, traffic will be switched to the east side of Lyndale Avenue and the removals on the west side of Lyndale Avenue will begin.  

1st Avenue (from 100th Street to 102nd Street):
Paving of bituminous driveways has started and will complete late in the week of July 6 or early the week of July 13.  Raising of manholes and gate valves is complete.  Sod installation is anticipated to complete by early in the week of July 13.  Paving of the final layer of bituminous is scheduled to occur the week of July 13.

11th Avenue (from 98th Street to 100th Street): 
Paving of bituminous driveways has started and will complete late in the week of July 6 or early the week of July 13.  Raising of manholes and gate valves is complete.  Sod installation is anticipated to complete by early in the week of July 13.  Paving of the final layer of bituminous is scheduled to occur the week of July 13.

89th St area (includes 89th Street, Fremont Avenue, Emerson Avenue, Dupont Avenue, Colfax Avenue): 
CenterPoint Energy gas service installation is scheduled to complete by the end of the week of July 6.  The 2015-101 Contractor plans to start minor manhole reconstruction in the area the week of July 13.  Pavement removal is anticipated to begin late in the week of July 20 or the week of July 27. 

Park Avenue (from 90th Street to 88th Street): 
Grading and placement of class 5 is complete.  Concrete work is scheduled to start late in the week of July 6.  Final grading of class 5 and paving of the first layer of bituminous is anticipated to occur the week of July 13.

Dupont Avenue (from 90th Street to 92nd Street):
Pavement removal is complete.  Storm sewer installation has started and is anticipated to complete by the end of the day Fri, July 10.  Grading and placement of class 5 is scheduled for the week of July 13 which will be followed by concrete work.
 

2015-102 PMP Street Maintenance Project

Morris Area (includes Morris Rd, W 88th St):
Boulevard restoration and paving of the final layer of bituminous is complete.  Punch list work remains. 

Oxborough Area (includes Rich Rd, W 95th St, W 95 ½ St, Oxborough Curve):
Paving of the final layer of bituminous is complete.  Punch list work remains.  

Rich Area (includes Rich Ave, Palmer Ave, Quinn Ave, Stanley Ave, Toledo Ave, W 109th St, Toledo Cir, W 108th St):
CenterPoint Energy continues gas service replacement in the area, which is anticipated to complete the week of July 13.

Minnesota Drive, Johnson Avenue and W 78th Street (includes Mn Drive from Johnson Ave to Edinborough Way, Johnson Ave from Mn Drive to W 78th St, W 78th St from W 78th St Cir to Johnson Ave):
The Contractor has been granted a noise exception for Saturday, July 11 from 7am – 9am in this area.  Lowering of manholes and gate valves on Minnesota Drive is complete.  Concrete sidewalk removal and replacement has started and will continue the week of July 13.  Manhole reconstruction along with minor storm sewer work has started and will complete the week of July 13.  Work in this area will require lane closures, which will also include right turn restrictions at the intersection of France Avenue and Minnesota Drive.  Sanitary sewer work on W 78th Street just south of Johnson Avenue has been slightly delayed due to private utility conflicts.  The closure of 78th Street just south of Johnson Avenue that was scheduled to close on Fri, July 10, has been delayed and further notice will be given when the closure is rescheduled.

July 2, 2015

2015-101 PMP Street Improvement Project

Lyndale Avenue (from 82nd Street to 86th Street):
Work continues on the current phase on the east side of Lyndale Avenue.  Concrete removals along with grading and placement of class 5 have started and will continue early in the week of July 6.  Signal work at the intersection of 84th Street and Lyndale Avenue will also continue the week of July 6.  Concrete replacement is scheduled for later in the week of July 6.  The Contractor is anticipating paving the first two layers of bituminous on the east side of Lyndale Avenue the week of July 13. 

1st Avenue (from 100th Street to 102nd Street):
Minor concrete work and paving of bituminous driveways will complete the week of July 6 which will be followed by sod installation.  Raising of manholes and gate valves is anticipated to complete early in the week of July 6.  Paving of the final layer of bituminous is scheduled to occur the week of July 13.

11th Avenue (from 98th Street to 100th Street): 
Minor concrete work and paving of bituminous driveways will complete the week of July 6 which will be followed by sod installation.  Raising of manholes and gate valves is anticipated to complete early in the week of July 6.  Paving of the final layer of bituminous is scheduled to occur the week of July 13.

89th St area (includes 89th Street, Fremont Avenue, Emerson Avenue, Dupont Avenue, Colfax Avenue): 
CenterPoint Energy continues gas service installation in this area, which is anticipated to complete the week of July 6.  The 2015-101 Contractor anticipates starting manhole reconstruction in the area the week of July 13.

Park Avenue (from 90th Street to 88th Street): 
Pavement removal and storm sewer work is complete.  Grading and placement of class 5 is scheduled to begin early in the week of July 6 which will be followed by concrete curb and driveway installation.

Dupont Avenue (from 90th Street to 92nd Street):
Pavement removal is scheduled to begin Mon, July 6.  This will be followed by storm sewer work the remainder of the week of July 6.

2015-102 PMP Street Maintenance Project

Morris Area (includes Morris Rd, W 88th St):
Concrete work and milling is complete.  Boulevard restoration has started and will continue the week of July 6.  Paving of the final layer of bituminous is scheduled for early in the week of July 6. 

Oxborough Area (includes Rich Rd, W 95th St, W 95 ½ St, Oxborough Curve):
Boulevard restoration and milling is complete.  Paving of the final layer of bituminous is scheduled for early in the week of July 6. 

Rich Area (includes Rich Ave, Palmer Ave, Quinn Ave, Stanley Ave, Toledo Ave, W 109th St, Toledo Cir, W 108th St):
CenterPoint Energy continues gas service replacement in the area, which is anticipated to take another 2-3 weeks to complete.

Minnesota Drive, Johnson Avenue and W 78th Street (includes Mn Drive from Johnson Ave to Edinborough Way, Johnson Ave from Mn Drive to W 78th St, W 78th St from W 78th St Cir to Johnson Ave):
The Contractor is scheduled to start work in this area on Mon, July 6.  The Contractor plans to lower manholes and gate valves on Minnesota Drive the week of July 6 along with starting curb and sidewalk removals.  Manhole reconstruction is scheduled for later in the week of July 6.  Work in this area will require lane closures, which will also include right turn restrictions at the intersection of France Avenue and Minnesota Drive.  Sanitary sewer work on W 78th Street just south of Johnson Avenue will require a road closure and this closure is anticipated to begin on Fri, July 10 and last approximately 1 week.  A detour will be provided for this closure that utilizes Computer Avenue, W 77th Street and Johnson Avenue.

June 2015

June 26, 2015


2015-101 PMP Street Improvement Project

Lyndale Avenue (from 82nd Street to 86th Street):
Work continues in the existing phase on the east side of Lyndale Avenue.  Storm sewer work and manhole reconstruction is complete.  Concrete removals along with grading and placement of class 5 are anticipated to start by the end of the week and will continue the week of June 29.  Signal work at the intersection of 84th Street and Lyndale Avenue will also continue the week of June 29.  Weather permitting, the Contractor is anticipating to pave the first two layers of bituminous on the east side of Lyndale Avenue the week of July 6. 

1st Avenue (from 100th Street to 102nd Street):
Concrete work is complete along with paving of the first layer of bituminous.  Paving of bituminous driveways, boulevard restoration and raising of manholes and gate valves will continue the week of June 29.

11th Avenue (from 98th Street to 100th Street):
Concrete work is nearly complete with minor curb and sidewalk replacements remaining.  Paving of the first layer of bituminous is complete.  Paving of bituminous driveways, boulevard restoration and raising of manholes and gate valves will continue the week of June 29.

89th St area (includes 89th Street, Fremont Avenue, Emerson Avenue, Dupont Avenue, Colfax Avenue):  
CenterPoint Energy continues gas service installation in this area, which is anticipated to take another 2 weeks to complete.

Park Avenue (from 90th Street to 88th Street): 
The Contractor anticipates removing the existing pavement the end of the week of June 22 along with starting storm sewer work.  This work will continue the week of June 29.

2015-102 PMP Street Maintenance Project

Morris Area (includes Morris Rd, W 88th St):
The Contractor has been granted a noise exception for Saturday, June 20 from 7am – 9am in this area.  Manhole adjustment, patching and milling of the pavement is scheduled for the week of June 29.  This will be followed by boulevard restoration.  Concrete removal and replacement in this area has started and will complete the week of June 29.

Oxborough Area (includes Rich Rd, W 95th St, W 95 ½ St, Oxborough Curve):
The Contractor has been granted a noise exception for Saturday, June 20 from 7am – 9am in this area.  Concrete removal and replacement is complete.  Bituminous patching and manhole adjustment has started along with boulevard restoration.  Milling of the pavement is scheduled for mid-week of June 29 which will be followed by paving of the final layer of bituminous.

Rich Area (includes Rich Ave, Palmer Ave, Quinn Ave, Stanley Ave, Toledo Ave, W 109th St, Toledo Cir, W 108th St):  
CenterPoint Energy continues gas service replacement in the area.

Minnesota Drive, Johnson Avenue and W 78th Street (includes Mn Drive from Johnson Ave to Edinborough Way, Johnson Ave from Mn Drive to W 78th St, W 78th St from W 78th St Cir to Johnson Ave):
The Contractor anticipates starting work in this area the week of July 6 which will require lane closures as work proceeds in the area.  Sanitary sewer work on W 78th St just south of Johnson Ave will require a road closure which is anticipated to occur in mid-July.  More information will be given when a schedule is determined.

June 18, 2015


2015-101 PMP Street Improvement Project

Lyndale Avenue (from 82nd Street to 86th Street):  
Work continues in the existing phase on the east side of Lyndale Avenue.  Storm sewer work and manhole reconstruction is anticipated to complete by early in the week of June 22.  Grading and placement of class 5 will follow the storm sewer work the week of June 22.  Concrete removals will also continue the week of June 22.  Signal work at the intersection of 84th Street and Lyndale Avenue has started and will continue the week of June 22. 

1st Avenue (from 1st Avenue from 100th Street to 102nd Street):  
Concrete work has started and is anticipated to complete by the end of the week of June 15.  Final grading of class 5 is scheduled for early in the week of June 22 which will be followed by paving of the first layer of bituminous later in the week.

11th Avenue (from 11th Avenue from 98th Street to 100th Street):  
Concrete work has started and is anticipated to complete by the end of the week of June 15.  Final grading of class 5 is scheduled for early in the week of June 22 which will be followed by paving of the first layer of bituminous later in the week.

89th St area (includes 89th Street, Fremont Avenue, Emerson Avenue, Dupont Avenue, Colfax Avenue):  
CenterPoint Energy continues gas service installation in this area, which is anticipated to take another 3 weeks to complete.

Park Avenue (from 90th Street to 88th Street):    
CenterPoint Energy has completed gas main and service installation in this area.  The 2015-101 PMP Contractor anticipates completing pavement removal early in the week of June 22 followed by storm sewer work later in the week.


2015-102 PMP Street Maintenance Project

Little Area (includes Little Rd, College Heights Circles, Morris Circles, Little Cir): 
Paving of the final layer of bituminous is complete.  Punch list work remains.

Morris Area (includes Morris Rd, W 88th St):  
The Contractor has been granted a noise exception for Saturday, June 20 from 7am – 9am in this area.  Manhole adjustment is anticipated to begin late in the week of June 22.  Concrete removal and replacement in this area is scheduled for the week of June 29.

Oxborough Area (includes Rich Rd, W 95th St, W 95 ½ St, Oxborough Curve)
The Contractor has been granted a noise exception for Saturday, June 20 from 7am – 9am in this area.  Manhole reconstruction and storm sewer work is complete.  Concrete removal and replacement has started and will continue early in the week of June 22.  Bituminous patching and manhole adjustment is scheduled for the week of June 22 along with boulevard restoration.

Rich Area (includes Rich Ave, Palmer Ave, Quinn Ave, Stanley Ave, Toledo Ave, W 109th St, Toledo Cir, W 108th St):
CenterPoint Energy has started gas main replacement in this area, which will continue the week of June 22.  Gas main and service replacement in this area is anticipated to complete by mid-late July.

June 12, 2015

2015-101 PMP Street Improvement Project

Lyndale Avenue (from 82nd Street to 86th Street)
Traffic has been shifted to the west side of Lyndale Avenue with one lane in both directions as work has started on the east side of Lyndale Avenue.  Storm sewer work and manhole reconstruction has started and will continue the week of June 15.  Bituminous and concrete removals have started and will continue the week of June 15. 

1st Avenue (from 1st Avenue from 100th Street to 102nd Street)
Class 5 installation on the roadway is complete.  Concrete work is scheduled for the week of June 15.

11th Avenue (from 11th Avenue from 98th Street to 100th Street)
Class 5 installation on the roadway is complete.  Concrete work is scheduled for the week of June 15.

89th St area (includes 89th Street, Fremont Avenue, Emerson Avenue, Dupont Avenue, Colfax Avenue)
CenterPoint Energy has completed gas main installation and has started gas service installation.  This is anticipated to take approximately 3-4 weeks to complete.

Park Avenue (from 90th Street to 88th Street) 
CenterPoint Energy has started gas main and service installation in the area and anticipates completing early in the week of June 15.  The Contractor anticipates starting storm sewer work in the area as part of the 2015-101 Project upon completion of CenterPoint Energy’s work late in the week of June 15 or the week of June 22.

2015-102 PMP Street Maintenance Project

Kentucky Area (includes Kentucky Avenue, Kentucky Circles, Kingslee Road, W 82nd Street, W 83rd Street, W 83rd Street Terrace)
Final paving of the area is complete.  Punch list work remains. 

Quebec Area (includes W 109th Street, Rhode Island Avenue, Quebec Avenue)
Final paving and striping is complete.  Punch list work remains. 

Little Area (includes Little Rd, College Heights Circles, Morris Circles, Little Cir)
The Contractor has been granted a noise exception for Saturday, June 13 from 7am – 9am in this area.  Raising of manholes and gate valves along with boulevard restoration is complete.  Milling is anticipated to complete on Thurs, June 11 (weather permitting).  Paving of the final layer of bituminous is scheduled to complete late in the week of June 8.

Morris Area (includes Morris Rd, W 88th St)
Tree removal is complete.  The concrete removals in this area have been slightly delayed and will occur in late June.

Oxborough Area (includes Rich Rd, W 95th St, W 95 ½ St, Oxborough Curve)
The Contractor has been granted a noise exception for Saturday, June 13 from 7am – 9am in this area.  Manhole reconstruction and minor storm sewer work is scheduled to start on Fri, June 12 and complete early in the week of June 15.  Concrete removal and replacement is also scheduled for the week of June 15.

June 5, 2015

2015-101 PMP Street Improvement Project

Lyndale Avenue (from 82nd Street to 86th Street)
The Contractor has completed removing a portion of the surface median between 83rd St and 82nd St and will be temporary paving this location to provide a crossover for traffic. Traffic will be shifted to the west side of Lyndale Avenue on Mon, June 8 with one lane in both directions as reconstruction of the east side of Lyndale Avenue begins. Bituminous and concrete removals along with storm sewer work will begin on the east side following the traffic switch the week of June 8. Access will remain open for businesses on the east side of Lyndale Avenue when this area is reconstructed with access open to 84th Street and also Garfield Circle from W 86th Street.

1st Avenue (from 1st Avenue from 100th Street to 102nd Street)
Storm sewer work in the area is complete. Street pavement has been removed and the Contractor plans to begin grading and placing class 5 the week of June 8.

11th Avenue (from 11th Avenue from 98th Street to 100th Street)
Storm sewer work in the area is complete. Street pavement has been removed and the Contractor plans to begin grading and placing class 5 the week of June 8.

89th St area (includes 89th Street, Fremont Avenue, Emerson Avenue, Dupont Avenue, Colfax Avenue)
CenterPoint Energy anticipates completing gas main installation the week of June 8 with gas service work to follow. Gas service work is anticipated to take 3-4 weeks to complete.

Park Avenue (from 90th Street to 88th Street)
CenterPoint Energy is scheduled to start gas main and service removal and replacement in this area the week of June 8. This work is anticipated to take 1-2 weeks to complete.

2015-102 PMP Street Maintenance Project

Kentucky Area (includes Kentucky Avenue, Kentucky Circles, Kingslee Road, W 82nd Street, W 83rd Street, W 83rd Street Terrace):
The Contractor has been granted a noise exception for Saturday, June 6 from 7am – 9am in this area. Milling of the area is anticipated to complete by Fri, June 5. Paving of the area is anticipated to begin on Saturday, June 6 and complete early in the week of June 8.

Quebec Area (includes W 109th Street, Rhode Island Avenue, Quebec Avenue):
The Contractor has been granted a noise exception for Saturday, June 6 from 7am – 9am in this area. Concrete work is complete. Milling and final paving of the area are anticipated to complete on Saturday, June 6 (weather permitting). Striping of the pavement is scheduled for the week of June 8.

Little Area (includes Little Rd, College Heights Circles, Morris Circles, Little Cir):
The Contractor has been granted a noise exception for Saturday, June 6 from 7am – 9am in this area. Raising of manholes and gate valves has started and will continue the week of June 8 along with bituminous driveway and street patching. Boulevard restoration is scheduled for the week of June 8. Milling and final paving of the area is anticipated to occur late in the week of June 8 (weather permitting).

Morris Area (includes Morris Rd, W 88th St):
CenterPoint Energy gas main and service work is complete. Minor storm sewer work and manhole reconstruction is complete. Tree removal is scheduled for the week of June 8 along with concrete removals.

Oxborough Area (includes Rich Rd, W 95th St, W 95 ½ St, Oxborough Curve):
The Contractor plans to start manhole reconstruction and minor storm sewer work in this area either late in the week of June 8 or the week of June 15.

May 2015

May 28, 2015

2015-101 PMP Street Improvement Project

Lyndale Avenue (from 82nd Street to 86th Street):  
The Contractor plans to start work in this area on June 4.  The first phase will include the removal of a portion of the surface median between 83rd St and 82nd St to provide a crossover for traffic.  One side of Lyndale Avenue will then be reconstructed at a time with traffic shifted to the opposite side with one lane in both directions.  The Contractor anticipates reconstructing the east side of Lyndale Avenue first, with traffic shifted to one lane in both directions on the west side.  Bituminous and concrete removals are scheduled for the week of June 8.  Access will remain open for businesses on the east side of Lyndale Avenue when this area is reconstructed with access open to 84th Street and also Garfield Circle from W 86th Street.

1st Avenue (from 1st Avenue from 100th Street to 102nd Street):
The Contractor plans to start bituminous and concrete removals the week of June 1 with storm sewer work will follow later in the week.

11th Avenue (from 11th Avenue from 98th Street to 100th Street):  
The Contractor plans to start bituminous and concrete removals the week of June 1 with storm sewer work to follow later in the week.

89th St area (includes 89th Street, Fremont Avenue, Emerson Avenue, Dupont Avenue, Colfax Avenue):  
CenterPoint Energy will continue gas main replacement in this area the week of June 1.
 

2015-102 PMP Street Maintenance Project

Kentucky Area (includes Kentucky Avenue, Kentucky Circles, Kingslee Road, W 82nd Street, W 83rd Street, W 83rd Street Terrace):  
Boulevard restoration in the area is complete.  Milling and final paving of the area is scheduled to occur late in the week of June 1. 

Quebec Area (includes W 109th Street, Rhode Island Avenue, Quebec Avenue):  
Concrete replacement in the area continues and will complete early in the week of June 1.  Raising of manholes and gate valves along with boulevard restoration will complete the week of June 1.  Milling is scheduled for late in the week of June 1 with final paving to occur early in the week of June 8 (weather permitting). 

Little Area (includes Little Rd, College Heights Circles, Morris Circles, Little Cir):  
Minor storm sewer work and manhole reconstruction is complete.  Concrete removal and replacement has started and will continue the week of June 1 followed by raising of manholes and gate valves.

Morris Area (includes Morris Rd, W 88th St):  
CenterPoint Energy anticipates completing work in the area the week of June 1.  The Contractor for the 2015-102 Project plans to start minor storm sewer work and reconstruct manholes in the area the week of June 1.

May 22, 2015

2015-101 PMP Street Improvement Project

A Pre-Construction Conference was held on Wednesday May 20 in the Bloomington Public Works Training Room.  The Contractor anticipates starting work on the project the week of June 1, with the first areas to be started including 1st Avenue, 11th Avenue, and Lyndale Avenue.  More information will be given next week when a firm schedule has been determined.

89th St. area (includes 89th Street, Fremont Avenue, Emerson Avenue, Dupont Avenue, Colfax Avenue):  
CenterPoint Energy will be replacing gas main and services in this area prior to start of reconstruction work for the 2015-101 Project.  This work is scheduled to start on Fri, May 22 and is anticipated to last approximately 4-6 weeks. 
 

2015-102 PMP Street Maintenance Project

Kentucky Area (includes Kentucky Avenue, Kentucky Circles, Kingslee Road, W 82nd Street, W 83rd Street, W 83rd Street Terrace):  
Concrete replacement is complete along with raising of manholes and gate valves in the area.  Boulevard restoration has started and will continue the week of May 25.  Milling and final paving of the area is anticipated to occur the week of June 1. 

Quebec Area (includes W 109th Street, Rhode Island Avenue, Quebec Avenue):  
Concrete replacement has started and will continue the week of May 25.  Raising of manholes and gate valves are scheduled for late in the week of May 25, which will be followed by boulevard restoration.

Little Area (includes Little Rd, College Heights Circles, Morris Circles, Little Cir):  
Minor storm sewer work and manhole reconstruction has started and is anticipated to complete by Fri, May 22.  Concrete removal and replacement is scheduled for the week of May 25.

Morris Area (includes Morris Rd, W 88th St):  
CenterPoint Energy is currently replacing gas main and services in this area and is anticipated to complete by the week of June 1.  The Contractor for the 2015-102 Project anticipates starting work in this area the week of June 1 following the completion of the CenterPoint Energy work.

May 15, 2015

2015-101 PMP Street Maintenance Project

A Pre-Construction Conference has been scheduled for Wednesday, May 20.

2015-102 PMP Street Maintenance Project

Kentucky Area (includes Kentucky Avenue, Kentucky Circles, Kingslee Road, W 82nd Street, W 83rd Street, W 83rd Street Terrace)
Concrete replacement has started and will continue the week of May 18.  Raising of manholes and gate valves in the area is anticipated to occur the week of May 18, which will be followed by boulevard restoration.

Quebec Area (includes W 109th Street, Rhode Island Avenue, Quebec Avenue)
Minor storm sewer work and manhole reconstruction is complete.  Concrete removals have started and will continue the week of May 18 along with replacement of the concrete.  Tree removals are also scheduled for the week of May 18.

Little Area (Little Rd, College Heights Circles, Morris Circles, Little Cir)
Concrete saw cutting has started and will continue the week of May 18.  Minor storm sewer work and manhole reconstruction is scheduled to occur the week of May 18 followed by concrete removals.  Tree removals are scheduled for the week of May 18.

May 8, 2015

2015-102 PMP Street Maintenance Project

Kentucky Area (includes Kentucky Avenue, Kentucky Circles, Kingslee Road, W 82nd Street, W 83rd Street, W 83rd Street Terrace): 
The Contractor has been granted a noise exception for Saturday, May 9 from 7am – 9am in this area.  Manhole reconstruction is complete along with the majority of the concrete sidewalk and curb removals which will continue late in the week of May 4 and the week of May 11.  Concrete replacement is scheduled to occur the week of May 11.  Tree removals are complete.

Quebec Area (includes W 109th Street, Rhode Island Avenue, Quebec Avenue): 
The Contractor has been granted a noise exception for Saturday, May 9 from 7am – 9am in this area.  Minor storm sewer work and manhole reconstruction is scheduled to start the week of May 11.  Saw cutting along with concrete sidewalk and curb removals are also scheduled to start late in the week of May 4 and continue the week of May 11.

May 5, 2015

2015-102 PMP Street Maintenance Project

A pre-construction conference was held on Mon, April 27.  The Contractor is scheduled to begin work on the project the week of May 4.

Kentucky Area (includes Kentucky Avenue, Kentucky Circles, Kingslee Road, W 82nd Street, W 83rd Street, W 83rd Street Terrace):
The Contractor plans to start saw cutting concrete for removals late in the week of April 27.  Concrete removals are scheduled to occur the week of May 4 along with minor utility manhole reconstruction.  Tree removals are also scheduled for the week of May 4.

Quebec Area (includes W 109th Street, Rhode Island Avenue, Quebec Avenue):
The Contractor anticipates starting work in this area the week of May 11.

April 2015

April 24, 2015

2015-102 PMP Street Maintenance Project

A pre-construction conference is scheduled for Mon, April 27.