Pavement Management Program (PMP) Updates
Engineering Links
2026-101 PMP Street Improvement Project
Neighborhood Informational Meetings
Monday, November 3 at 2:30pm and 5:30pm
Bloomington Public Works Training Room
1700 W 98th St
Bloomington, MN 55431
Public Hearing at City Council
Monday, November 17 at 6:30pm
City Council Chambers (Council meeting starts at 6:30pm)
1800 W Old Shakopee Rd
Bloomington, MN 55431
2025-101 PMP Street Improvement Project
Fremont Avenue/Emerson Avenue/W 80 1/2 St
Paving of the final layer of asphalt is scheduled for the week of October 27.
Oakland Avenue/15th Avenue/E 84th St
Paving of the final layer of asphalt has started and will complete the week of October 27.
2025-102 PMP Street Maintenance Project
France Avenue (Overlook Drive to Old Shakopee Road (CSAH 1))
Final pavement markings will be installed the week of October 27th.
W. 110th Street (Normandale Boulevard to France Avenue)
Final pavement markings will be installed the week of October 27th.
2025-101 PMP Street Improvement Project
Fremont Avenue/Emerson Avenue/W 80 1/2 St
Boulevard restoration will complete the week of October 20 with paving of the final layer of asphalt scheduled for the week of October 27.
Oakland Avenue/15th Avenue/E 84th St
Boulevard restoration will complete the week of October 13 with paving of the final layer of asphalt the week of October 20.
2025-101 PMP Street Improvement Project
Fremont Avenue
Boulevard restoration will continue over the next couple of weeks. Paving of the final layer of asphalt is anticipated for late October and will coincide with final paving of Emerson Avenue.
Emerson Avenue/W 80 1/2 St
Storm sewer, excavation and class 5 installation are complete. Curb and gutter installation is anticipated to complete early in the week of October 13. Final grading of the class 5 gravel and paving of the first layer of asphalt will follow later in the week of October 13 and the week of October 20.
Oakland Avenue/15th Avenue
Paving of the first layer of asphalt is complete. Boulevard restoration will continue the week of October 13 with paving of the final layer of asphalt the week of October 20.
E 84th Street
Paving of the first two layers of asphalt is anticipated to complete by the end of the week of October 6. Boulevard restoration will continue the week of October 13 with paving of the final layer of asphalt the week of October 20.
2025-101 PMP Street Improvement Project
Fremont Avenue
Paving of the first layer of asphalt is complete. Boulevard restoration will continue over the next couple of weeks.
Emerson Avenue/W 80 1/2 St
Storm sewer installation will continue the week of October 6 and will be followed by excavation and class 5 gravel installation. Curb and gutter installation is anticipated to begin late in the week of October 6.
Oakland Avenue/15th Avenue
Grading and tolerancing of the class 5 gravel will complete early in the week of October 6 and be followed by paving of the first layer of asphalt. Boulevard restoration will follow the week of October 13.
E 84th Street
Excavation, grading, class 5 installation, and tolerancing of the class 5 gravel will continue the week of October 6 and be followed by paving of the first layer of asphalt. Boulevard restoration will follow the week of October 13.
2025-102 PMP Street Maintenance Project
Columbus Area (Columbus Road, Columbus Circle, Park Avenue, Portland Avenue, E. 102nd Street, Chicago Circle, 10th Avenue, E. 103rd Street)
Asphalt milling and paving is scheduled to be completed early the week of October 6th.
France Avenue (Overlook Drive to Old Shakopee Road (CSAH 1))
The contractor will continue adjusting utilities the week of October 6th in preparation for asphalt milling & paving. Concrete installation will continue the week of October 6th.
W 110th Street (Normandale Boulevard to France Avenue)
The contractor will continue adjusting utilities the week of October 6th in preparation for asphalt milling & paving. Concrete installation will continue the week of October 6th.
2025-101 PMP Street Improvement Project
Fremont Avenue
Excavation, grading, and Class 5 installation are ongoing and expected to continue through the end of the week of September 22. Paving of the first asphalt layer is scheduled for the week of September 29.
Emerson Avenue/W 80 1/2 St
Removals will begin the week of September 29, followed by storm sewer and utility installation. Excavation and Class 5 installation are scheduled for the week of October 5.
10th Avenue / 99th Street, 12th Avenue, E 90th St, and Elliott Ave
The final layer of asphalt was paved during the week of September 22.
Oakland Avenue/15th Avenue
Curb, gutter, and sidewalk installation is ongoing and will continue through the end of the week of September 22. Grading and tolerancing will follow during the week of September 29.
E 84th Street
Curb and sidewalk installation is nearing completion. The remaining street removals will be finished early in the week of September 29, followed by grading, Class 5 installation, and tolerancing. Paving of the first asphalt layer is tentatively scheduled for the week of October 6.
2025-102 PMP Street Maintenance Project
Columbus Area (Columbus Road, Columbus Circle, Park Avenue, Portland Avenue, E. 102nd Street, Chicago Circle, 10th Avenue, E. 103rd Street)
The contractor will be in the week of September 29th finishing site restoration including topsoil and sod. Asphalt milling and paving is scheduled to be completed the week of October 6th.
France Avenue (Overlook Drive to Old Shakopee Road (CSAH 1))
The contractor will be continuing utility repairs the week of September 29th. Concrete pours will also occur the week of September 29th.
W 110th Street (Normandale Boulevard to France Avenue)
The contractor will continue concrete pours the week of September 29th. Retaining wall work will also be occurring the week of September 29th.
2025-101 PMP Street Improvement Project
Fremont Avenue (W 80 ½ Street to 100’ South 82nd Street)
The sanitary installation along Fremont Avenue has been completed. The contractor will begin storm sewer installation during the week of September 22, with milling, excavation, and grading also scheduled later that week. Removals on Emerson Avenue are expected to start the week of September 29.
10th Avenue and 99th Street
Paving of the final lift of asphalt is scheduled for the end of the week of September 15.
12th Avenue
Xcel Energy’s utility relocation work is ongoing through September 22. Once that work is complete, the contractor will place the final layer of asphalt at the end of the week of September 22.
E 90th Street
The final lift of asphalt is scheduled to be paved at the end of the week of September 15.
Elliott Avenue
The first layer of asphalt was placed the week of September 9. Restoration work is planned for the week of September 15, with the final layer of asphalt to follow during the week of September 22.
Oakland Avenue/15th Avenue
Curb, gutter, and sidewalk installation has been rescheduled to the week of September 29. This will be followed by final grading and tolerancing, with the first layer of asphalt tentatively planned for the week of October 6.
E 84th Street
Curb and sidewalk installation began the week of September 15 and will continue through September 22. Full street removals are taking place from September 15 through September 29, followed by excavation and grading during the week of September 29. The first asphalt layer is tentatively scheduled for the week of October 6.
2025-102 PMP Street Maintenance Project
Columbus Area (Columbus Road, Columbus Circle, Park Avenue, Portland Avenue, E. 102nd Street, Chicago Circle, 10th Avenue, E. 103rd Street)
The contractor will be in the week of September 22nd finishing curb & gutter replacement and asphalt patching.
France Avenue (Overlook Drive to Old Shakopee Road (CSAH 1))
The contractor will be completing utility repairs and concrete removals the week of September 22nd.
W 110th Street (Normandale Boulevard to France Avenue)
The contractor will be completing utility repairs and concrete removals the week of September 22nd. Concrete pours will occur late the week of September 22nd.