2023-101 PMP Street Improvement Project
Assessment informational meetings were held for the 2023-101 PMP Street Improvement Project on Wednesday, October 4 at 2:30pm and 5:30pm in the Bloomington Public Works Training Room. There were 7 residents that attended between the two meetings. The City Council public hearing to consider approval of the assessment is scheduled for October 9 at Bloomington City Council.
Mission Lane (Nicollet Avenue to East Terminus)
Boulevard restoration is scheduled for the week of October 9 and will be followed by paving of the final layer of asphalt later in the week.
Clinton Avenue (102nd Street to 104th Street)
Excavation and installation of class 5 gravel will be completed by the end of the week of October 2. Concrete replacement is anticipated to start late in the week of October 2 and finish early in the week of October 9 and will be followed by paving of the first layer of asphalt. Boulevard restoration will follow the week of October 16.
Bloomington Avenue (82nd Street to North Terminus)
Excavation and installation of class 5 gravel is scheduled for early in the week of October 9 and concrete replacement will follow later in the week. Paving of the first layer of asphalt is anticipated to occur early in the week of October 16 and will be followed by boulevard restoration.
2023-102 PMP Street Maintenance Project
86th Street (17th Avenue to East Terminus)
Old Cedar Avenue (86th Street to Old Shakopee Road)
Boulevard restoration will continue the week of October 9 and will be followed by milling and final asphalt paving.