Pavement Management Program (PMP) Updates
Engineering Links

2025-101 PMP Street Improvement Project
Towne Terrace (James Ave to Humboldt Ave)
The contractor is currently performing grading and levelling of the street. This work will continue into the week of July 1.
W 105th Street (Thomas Ave to Sheridan Ave)
The contractor will in the week of July 1 to begin grading and levelling of the street.
6701 W 78th St
The contractor is working on patching the area around the newly constructed median. This work will continue into the week of July 1.
2025-102 PMP Street Maintenance Project
Cavell Area (Cavell Avenue, Cavell Circle (1), Cavell Circle (2), Cavell Circle (3), W. 100th Street)
The contractor will be in early the week of June 30th to complete asphalt paving.
Hyland Area (Hyland Creek Road, Nesbitt Road, Hyland Creek Circle, Norman Ridge Circle)
The contractor will be in the week of June 30th to beginning pouring concrete curb & gutter and sidewalk.
Nine Mile Creek Parkway (W. 90th Street to Stanley Avenue)
The contractor will be in the week of June 30th continuing removals and will begin utility work.
I-494 Reconstruction Project
Portions of both I-494 & I-35W will be closed this weekend to facilitate demolition of the existing I-494 westbound bride over I-35W. The closures are summarized below:
- I-494 eastbound closed between Hwy. 100 and I-35W
- I-494 westbound closed between T.H. 77 and Hwy 100
- I-35W (both directions) closed between I-494 and Hwy 62
The closure will start at 10 P.M. Friday, June 27th through 5 A.M. Monday, June 30th.
2025-101 PMP Street Improvement Project
Towne Terrace (James Ave to Humboldt Ave)
The contractor is scheduled to begin pavement and concrete removals the week of June 16. This will be followed by utility work the week of June 23.
W 105th Street (Thomas Ave to Sheridan Ave)
The contractor is scheduled to begin pavement and concrete removals the week of June 16. This will be followed by utility work the week of June 23.
2025-102 PMP Street Maintenance Project
W. 111th Area (W. 111th Street, Sumter Avenue, Rhode Island Avenue, Quebec Circle)
Asphalt paving has been completed in this area. Traffic control will be picked up the week of June 23rd.
Cavell Area (Cavell Avenue, Cavell Circle (1), Cavell Circle (2), Cavell Circle (3), W. 100th Street)
The contractor will be in this week to complete asphalt milling & paving the week of June 23rd.
Hyland Area (Hyland Creek Road, Nesbitt Road, Hyland Creek Circle, Norman Ridge Circle)
The contractor will continue with utility work the week of June 23rd. Concrete curb & gutter and sidewalk replacement will also begin the week of June 23rd.
Nine Mile Creek Parkway (W. 90th Street to Stanley Avenue)
The contractor will be in the week of June 23rd to begin asphalt and concrete removals. Minor repair of utilities will also begin the week of June 23rd.
2025-101 PMP Street Improvement Project
Towne Terrace (James Ave to Humboldt Ave)
The contractor is scheduled to begin pavement and concrete removals the week of June 16. This will be followed by utility work the week of June 23.
W 105th Street (Thomas Ave to Sheridan Ave)
The contractor is scheduled to begin pavement and concrete removals the week of June 16. This will be followed by utility work the week of June 23.
6701 W 78th St
The contractor will be starting median modifications adjacent to the Enclave Development at 6701 W 78th St the week of June 16.
9830 Nicollet Avenue
The contractor will be installing a hydrant adjacent to 9830 Nicollet Avenue the week of June 16.
2025-102 PMP Street Maintenance Project
W. 111th Area (W. 111th Street, Sumter Avenue, Rhode Island Avenue, Quebec Circle)
Asphalt milling is scheduled to be completed on Friday, June 13th and asphalt paving is scheduled for Monday, June 16th.
Cavell Area (Cavell Avenue, Cavell Circle (1), Cavell Circle (2), Cavell Circle (3), W. 100th Street)
The contractor will be in the week of June 16th to asphalt patch and begin site restoration including topsoil and sod.
Hyland Area (Hyland Creek Road, Nesbitt Road, Hyland Creek Circle, Norman Ridge Circle)
The contractor will continue with utility work the week of June 16th.
Bush Lake Road (Old Shakopee Road to Chalet Road)
The contractor will continue utility work and be completed early the week of June 16th.
2025-101 PMP Street Improvement Project
Towne Terrace (James Ave to Humboldt Ave)
The contractor anticipates starting pavement and concrete removals the week of June 16th.
W 105th Street (Thomas Ave to Sheridan Ave)
The contractor anticipates starting pavement and concrete removals the week of June 16th.
2025-102 PMP Street Maintenance Project
W. 111th Area (W. 111th Street, Sumter Avenue, Rhode Island Avenue, Quebec Circle)
The contractor will be in the week of June 9th for site restoration, including topsoil and sod.
Cavell Area (Cavell Avenue, Cavell Circle (1), Cavell Circle (2), Cavell Circle (3), W. 100th Street)
The contractor will be in the week of June 9th to begin pouring curb & gutter and sidewalk.
Hyland Area (Hyland Creek Road, Nesbitt Road, Hyland Creek Circle, Norman Ridge Circle)
The contractor will mobilize in the week of June 9th to install inlet protection. Removals needed for repair of city-owned utilities may begin late the week of June 9th.
Bush Lake Road (Old Shakopee Road to Chalet Road)
The contractor will be mobilizing into Bush Lake Road the week of June 9th to begin repair of City-owned utilities on Bush Lake Road. This work is in preparation for a Hennepin County overlay of Bush Lake Road scheduled for later this summer.
2025-101 PMP Street Improvement Project
A preconstruction conference was held on Monday, May 19th . Work is expected to begin in early June.
2025-102 PMP Street Maintenance Project
W. 111th Area (W. 111th Street, Sumter Avenue, Rhode Island Avenue, Quebec Circle)
The contractor will be in the week of June 2nd to asphalt patch the new curb areas and begin to prep for site restoration, including topsoil and sod.
Cavell Area (Cavell Avenue, Cavell Circle (1), Cavell Circle (2), Cavell Circle (3), W. 100th Street)
The contractor will be in the week of June 2nd to begin repair of City-owned utilities. Removal and select curb & gutter and concrete sidewalk will also occur the week of June 2nd.
I-494 Reconstruction Project
I-494 between Hwy. 100 and T.H. 77 will be closed this weekend to facilitate the demolition of the existing Portland Avenue bridge. The closure will start at 10 P.M. Friday, May 30th through 5 A.M. Monday, June 2nd.
2025-101 PMP Street Improvement Project
A preconstruction conference was held on Monday, May 19th . Work is expected to begin in early June.
2025-102 PMP Street Maintenance Project
W. 111th Area (W. 111th Street, Sumter Avenue, Rhode Island Avenue, Quebec Circle)
The contractor will be in the week of May 26th to begin installing inlet protection, traffic control, and start removal of existing concrete items.
Cavell Area (Cavell Avenue, Cavell Circle (1), Cavell Circle (2), Cavell Circle (3), W. 100th Street)
The contractor will be in the week of May 26th to begin installing inlet protection, traffic control, and start removal of existing concrete items.
2025-101 PMP Street Improvement Project
A preconstruction conference is scheduled for Monday, May 19th . Work is expected to begin in late May/early June.
2025-102 PMP Street Maintenance Project
W. 111th Area (W. 111th Street, Sumter Avenue, Rhode Island Avenue, Quebec Circle)
The contractor will be in the week of May 19th to begin installing inlet protection, traffic control, and start removal of existing concrete items.
Cavell Area (Cavell Avenue, Cavell Circle (1), Cavell Circle (2), Cavell Circle (3), W. 100th Street)
The contractor will be in the week of May 19th to begin installing inlet protection, traffic control, and start removal of existing concrete items.