Pavement Management Program (PMP) Updates
Engineering Links

2025-101 PMP Street Improvement Project
Fremont Avenue
Paving of the first layer of asphalt is complete. Boulevard restoration will continue over the next couple of weeks.
Emerson Avenue/W 80 1/2 St
Storm sewer installation will continue the week of October 6 and will be followed by excavation and class 5 gravel installation. Curb and gutter installation is anticipated to begin late in the week of October 6.
Oakland Avenue/15th Avenue
Grading and tolerancing of the class 5 gravel will complete early in the week of October 6 and be followed by paving of the first layer of asphalt. Boulevard restoration will follow the week of October 13.
E 84th Street
Excavation, grading, class 5 installation, and tolerancing of the class 5 gravel will continue the week of October 6 and be followed by paving of the first layer of asphalt. Boulevard restoration will follow the week of October 13.
2025-102 PMP Street Maintenance Project
Columbus Area (Columbus Road, Columbus Circle, Park Avenue, Portland Avenue, E. 102nd Street, Chicago Circle, 10th Avenue, E. 103rd Street)
Asphalt milling and paving is scheduled to be completed early the week of October 6th.
France Avenue (Overlook Drive to Old Shakopee Road (CSAH 1))
The contractor will continue adjusting utilities the week of October 6th in preparation for asphalt milling & paving. Concrete installation will continue the week of October 6th.
W 110th Street (Normandale Boulevard to France Avenue)
The contractor will continue adjusting utilities the week of October 6th in preparation for asphalt milling & paving. Concrete installation will continue the week of October 6th.
2025-101 PMP Street Improvement Project
Fremont Avenue
Excavation, grading, and Class 5 installation are ongoing and expected to continue through the end of the week of September 22. Paving of the first asphalt layer is scheduled for the week of September 29.
Emerson Avenue/W 80 1/2 St
Removals will begin the week of September 29, followed by storm sewer and utility installation. Excavation and Class 5 installation are scheduled for the week of October 5.
10th Avenue / 99th Street, 12th Avenue, E 90th St, and Elliott Ave
The final layer of asphalt was paved during the week of September 22.
Oakland Avenue/15th Avenue
Curb, gutter, and sidewalk installation is ongoing and will continue through the end of the week of September 22. Grading and tolerancing will follow during the week of September 29.
E 84th Street
Curb and sidewalk installation is nearing completion. The remaining street removals will be finished early in the week of September 29, followed by grading, Class 5 installation, and tolerancing. Paving of the first asphalt layer is tentatively scheduled for the week of October 6.
2025-102 PMP Street Maintenance Project
Columbus Area (Columbus Road, Columbus Circle, Park Avenue, Portland Avenue, E. 102nd Street, Chicago Circle, 10th Avenue, E. 103rd Street)
The contractor will be in the week of September 29th finishing site restoration including topsoil and sod. Asphalt milling and paving is scheduled to be completed the week of October 6th.
France Avenue (Overlook Drive to Old Shakopee Road (CSAH 1))
The contractor will be continuing utility repairs the week of September 29th. Concrete pours will also occur the week of September 29th.
W 110th Street (Normandale Boulevard to France Avenue)
The contractor will continue concrete pours the week of September 29th. Retaining wall work will also be occurring the week of September 29th.
2025-101 PMP Street Improvement Project
Fremont Avenue (W 80 ½ Street to 100’ South 82nd Street)
The sanitary installation along Fremont Avenue has been completed. The contractor will begin storm sewer installation during the week of September 22, with milling, excavation, and grading also scheduled later that week. Removals on Emerson Avenue are expected to start the week of September 29.
10th Avenue and 99th Street
Paving of the final lift of asphalt is scheduled for the end of the week of September 15.
12th Avenue
Xcel Energy’s utility relocation work is ongoing through September 22. Once that work is complete, the contractor will place the final layer of asphalt at the end of the week of September 22.
E 90th Street
The final lift of asphalt is scheduled to be paved at the end of the week of September 15.
Elliott Avenue
The first layer of asphalt was placed the week of September 9. Restoration work is planned for the week of September 15, with the final layer of asphalt to follow during the week of September 22.
Oakland Avenue/15th Avenue
Curb, gutter, and sidewalk installation has been rescheduled to the week of September 29. This will be followed by final grading and tolerancing, with the first layer of asphalt tentatively planned for the week of October 6.
E 84th Street
Curb and sidewalk installation began the week of September 15 and will continue through September 22. Full street removals are taking place from September 15 through September 29, followed by excavation and grading during the week of September 29. The first asphalt layer is tentatively scheduled for the week of October 6.
2025-102 PMP Street Maintenance Project
Columbus Area (Columbus Road, Columbus Circle, Park Avenue, Portland Avenue, E. 102nd Street, Chicago Circle, 10th Avenue, E. 103rd Street)
The contractor will be in the week of September 22nd finishing curb & gutter replacement and asphalt patching.
France Avenue (Overlook Drive to Old Shakopee Road (CSAH 1))
The contractor will be completing utility repairs and concrete removals the week of September 22nd.
W 110th Street (Normandale Boulevard to France Avenue)
The contractor will be completing utility repairs and concrete removals the week of September 22nd. Concrete pours will occur late the week of September 22nd.
2025-101 PMP Street Improvement Project
Fremont Avenue (W 80 ½ Street to 100’ South 82nd Street)
Underground pipe installation on Fremont Avenue is nearing completion with items such as pits backfilling and testing of the new sanitary line remaining to be completed in the week of September 15. This will be followed by installation of a new storm sewer system on Fremont Avenue. Milling of Fremont Avenue along with excavation and grading are scheduled for the week of September 22. Removals on Emerson Avenue are scheduled for the week of September 29.
10th Avenue and 99th Street
The final layer of asphalt has been pushed to the week of September 15.
12th Avenue
Xcel Energy Utility relocation work has been pushed to the week of September 22. The final layer of asphalt will follow later in the same week.
E 90th Street
The final layer of asphalt has been pushed to the week of September 15.
Elliott Avenue
The first layer of asphalt was paved the week of September 9. The contractor plans on doing restoration work the week of September 15 and placement of the final layer of asphalt the week of September 22.
Oakland Avenue/15th Avenue
The Contractor plans on finishing utility work this week. Excavation and grading of both streets will follow the week of September 15. Concrete work has now been pushed to the week of September 24.
E 84th Street
Utility work was completed this week. Removals for concrete work is scheduled for the week of September 15, concrete curb and gutter along with sidewalk installation are scheduled for later that week through the week of September 22. Full street removals along with excavation and grading work are scheduled for the week of September 29.
2025-102 PMP Street Maintenance Project
Columbus Area (Columbus Road, Columbus Circle, Park Avenue, Portland Avenue, E. 102nd Street, Chicago Circle, 10th Avenue, E. 103rd Street)
The contractor will be in the week of September 15th finishing utility work. The contractor will also be in the week of September 15th pouring concrete curb and concrete flatwork.
France Avenue (Overlook Drive to Old Shakopee Road (CSAH 1))
The contractor will mobilize into the site the week of September 15th to begin removals and start utility work.
W 110th Street (Normandale Boulevard to France Avenue)
The contractor will mobilize into the site the week of September 15th to begin removals and start utility work.
2025-101 PMP Street Improvement Project
Fremont Avenue (W 80 ½ Street to 100’ South 82nd Street)
Underground pipe installation is ongoing; the contractor is on schedule to complete the utility work by mid-September. The road reconstruction will begin late in the week of September 15th with pavements removals followed by utility work.
10th Avenue and 99th Street
Restoration work was completed the week of September 1. The final layer of asphalt is now scheduled for the week of September 8.
12th Avenue
Restoration work was completed the week of September 1. Xcel Energy will be working on relocating a couple of Utility poles in anticipation of the final layer of asphalt the week of September 15.
E 90th Street
Restoration work was completed the week of September 1. The final layer of asphalt is now scheduled for the week of September 8.
Elliott Avenue
Concrete curb and gutter installation work is completed. The contractor will be working on final grading and tolerancing the week of September 1. Paving of the first layer of asphalt is scheduled for the week of September 8.
Oakland Avenue/15th Avenue
Utility work is ongoing and is expected to be completed the week of September 8. This will be followed by concrete curb and gutter installation later in the same week.
E 84th Street
The Contractor will begin full removal of pavement surface the week of September 15. Curb and gutter work will follow later that same week.
2025-102 PMP Street Maintenance Project
Columbus Area (Columbus Road, Columbus Circle, Park Avenue, Portland Avenue, E. 102nd Street, Chicago Circle, 10th Avenue, E. 103rd Street)
The contractor will be in the week of September 8th beginning utility work and continuing removals of concrete curb & gutter and concrete panels.
France Avenue (Overlook Drive to Old Shakopee Road (CSAH 1))
The contractor will mobilize into the site the week of September 15th to begin removals and start utility work.
W 110th Street (Normandale Boulevard to France Avenue)
The contractor will mobilize into the site the week of September 15th to begin removals and start utility work.
2025-101 PMP Street Improvement Project
Fremont Avenue (W 80 ½ Street to 100’ South 82nd Street)
Underground pipe installation is ongoing; the contractor is on schedule to complete the utility work by mid-September. The road reconstruction work will follow right after.
10th Avenue and 99th Street
Restoration work initially scheduled for the week of August 18 has now been rescheduled for the week of August 25, this work includes topsoil installation, sod placement and irrigation systems repairs. The final layer of asphalt is now tentatively scheduled for the end of the week of September 1.
12th Avenue
Restoration work initially scheduled for the week of August 18 has now been rescheduled for the week of August 25, this work includes topsoil installation, sod placement and irrigation systems repairs. The final layer of asphalt is now tentatively scheduled for the end of the week of September 1 pending some utility pole relocation by Xcel Energy.
E 90th Street
Restoration work initially scheduled for the week of August 18 has now been rescheduled for the week of August 25, this work includes topsoil installation, sod placement and irrigation systems repairs. The final layer of asphalt is now tentatively scheduled for the end of the week of September 1.
Elliott Avenue
Street grading and levelling work is ongoing and will continue into the week of August 25, this work will be followed by the installation of concrete curb and gutter
Oakland Avenue/15th Avenue
The contractor will begin removals in this area the week of August 25. This will be followed by utility work later in the same week.
E 84th Street
The contractor will begin work in this area the week of August 25, with utility work including storm sewer catch basins installation, sanitary sewer repairs, and water hydrant installation.
2025-102 PMP Street Maintenance Project
Terracewood Area (Terracewood Drive, Morris Circle, Morris Lane, Rich Circle, W. 114th Street, Rich Road)
The contractor will be in the week of August 25th continuing restoration in the disturbed boulevard areas, including topsoil and sod. Milling and paving is scheduled for the week of September 1st.
Kelly Fields Parking Lot Improvements
The contractor will be in the week of August 25th beginning restoration in the disturbed boulevard areas, including topsoil and sod. Asphalt milling is scheduled late the week of August 25th and paving will occur the week of September 1st.