Pavement Management Program (PMP) Updates
Engineering Links

2025-101 PMP Street Improvement Project
Fremont Avenue (W 80 ½ Street to 100’ South 82nd Street)
Underground pipe installation is ongoing; the contractor is on schedule to complete the utility work by mid-September. The road reconstruction work will follow right after.
10th Avenue and 99th Street
The first layer of asphalt was paved the week of August 11. The contractor will be working on restoration type item most of the week of August 18. The final layer of asphalt is tentatively scheduled for the end of the week of August 25.
12th Avenue
The first layer of asphalt was paved the week of August 11. The contractor will be working on restoration type item most of the week of August 18. The final layer of asphalt is tentatively scheduled for the end of the week of August 25.
E 90th Street
The first layer of asphalt was paved the week of August 11. The contractor will be working on restoration type item most of the week of August 18. The final layer of asphalt is tentatively scheduled for the end of the week of August 25.
Elliott Avenue
The utility work is completed. The Contractor will be working on grading and levelling the street the week of August 18. Concrete curb installation is tentatively scheduled for the week of August 25.
Oakland Avenue/15th Avenue
The contractor will begin removals in this area the week of August 25. This will be followed by utility work later in the same week.
2025-102 PMP Street Maintenance Project
Terracewood Area (Terracewood Drive, Morris Circle, Morris Lane, Rich Circle, W. 114th Street, Rich Road)
The contractor will finish concrete work this week. The contractor will be in the week of August 18th beginning restoration in the disturbed boulevard areas, including topsoil and sod.
Kelly Fields Parking Lot Improvements
Contractor will continue concrete removal and replacement the week of August 18th.
2025-102 PMP Street Maintenance Project
Vincent Area (Vincent Place, Vincent Circle)
The contractor completed asphalt paving on Thursday, August 7th.
Terracewood Area (Terracewood Drive, Morris Circle, Morris Lane, Rich Circle, W 114th Street, Rich Road)
The contractor will begin pouring back concrete curb & gutter and sidewalk the week of August 8th.
2025-101 PMP Street Improvement Project
Towne Terrace (James Avenue to Humboldt Avenue)
Paving of the final Layer of asphalt has been rescheduled for the week of August 4.
W 105th Street (Thomas Avenue to Sheridan Avenue)
Paving of the final Layer of asphalt has been rescheduled for the week of August 4.
Fremont Avenue (W 80 1/2 Street to 100' South 82nd St)
The utility subcontractor begun pipe jacking operations the week of July 28. This portion of the work is scheduled for 9 to 10 weeks, during this time Freemont Avenue will only be open to local traffic.
10th Avenue and 99th Street
Concrete curb and gutter installation work has been rescheduled for the end of the week of July 28 . This work will be followed by final grading and paving of the first layer of asphalt the week of August 4. Restoration work will follow the week after.
12th Avenue
Concrete curb and gutter installation work has been rescheduled for the end of the week of July 28 . This work will be followed by final grading and paving of the first layer of asphalt the week of August 4. Restoration work will follow the week after.
E 90th Street
The contractor has begun installing concrete curb and gutter along with sidewalks the week of July 28. This work will be followed by final grading and paving of the first layer of asphalt the week of August 4. Restoration work will follow later in the same week.
Elliott Avenue
The Contractor will begin Utility work the week of August 4.
2025-102 PMP Street Maintenance Project
Vincent Area (Vincent Place, Vincent Circle)
The contractor will be in early the week of August 4th finishing restoration. Asphalt milling is scheduled for Wednesday, August 6th and asphalt paving for Friday, August 8th.
Terracewood Area (Terracewood Drive, Morris Circle, Morris Lane, Rich Circle, W 114th Street, Rich Road)
The contractor will continue utility work and begin pouring back concrete curb & gutter and sidewalk the week of August 4th.
2025-101 PMP Street Improvement Project
Towne Terrace (James Avenue to Humboldt Avenue)
The Contractor will be paving the final layer of asphalt the week of July 28
W 105th Street (Thomas Avenue to Sheridan Avenue)
The Contractor will be paving the final layer of asphalt the week of July 28
Fremont Avenue (W 80 1/2 Street to 100' South 82nd St)
The utility subcontractor will begin pipe jacking operations the week of July 28. This portion of the work is scheduled for 9 to 10 weeks, during this time Freemont Avenue will only be open to local traffic.
10th Avenue and 99th Street
The contractor will be installing concrete curb and gutter the week of July 28. This work will be followed by final grading and paving of the first layer of asphalt the week of August 4. Restoration work will follow later in the same week.
12th Avenue
The contractor will be installing concrete curb and gutter the week of July 28. This work will be followed by final grading and paving of the first layer of asphalt the week of August 4. Restoration work will follow later in the same week.
E 90th Street
The contractor will be installing concrete curb and gutter along with sidewalks the week of July 28. This work will be followed by final grading and paving of the first layer of asphalt the week of August 4. Restoration work will follow later in the same week.
Elliott Avenue
The contractor will begin removals on this segment towards the end of the week of July 21. This will be followed by utility work the week of July 28.
2025-102 PMP Street Maintenance Project
Hyland Area (Hyland Creek Road, Nesbitt Road, Hyland Creek Circle, Norman Ridge Circle)
Asphalt paving is scheduled for Friday, July 18th.
Nine Mile Creek Parkway (W. 90th Street to Stanley Avenue)
Asphalt milling is scheduled for Friday, July 25th and paving will be completed early the week of July 28th.
Vincent Area (Vincent Place, Vincent Circle)
The contractor will be in the week of July 28th adjusting irons and pouring back concrete curb & gutter.
Terracewood Area (Terracewood Drive, Morris Circle, Morris Lane, Rich Circle, W 114th Street, Rich Road)
The contractor will continue utility work the week of July 28th.
2025-101 PMP Street Improvement Project
Towne Terrace (James Avenue to Humboldt Avenue)
The contractor will finish paving the first layer of asphalt the week of July 14. This work will be followed by soft surface restoration around the yards. The paving of the final layer of asphalt will follow later in the week of July 21
W 105th Street (Thomas Avenue to Sheridan Avenue)
The contractor will finish paving the first layer of asphalt the week of July 14. This work will be followed by soft surface restoration around the yards. The paving of the final layer of asphalt will follow later in the week of July 21.
Fremont Avenue
The contractor completed removals earlier the week of July 14. The utility subcontractor has begun installing the various pits required for pipe jacking operations. The utility portion of this work is scheduled for 9 to 10 weeks, during this time Freemont Avenue will only be open to local traffic.
10th Avenue and 99th Street
Levelling and grading work is ongoing and will run through the week of July 14. Concrete curb and gutter installation along with paving of the first layer of asphalt are scheduled for the week of July 28
12th Avenue
Utility work is ongoing and will continue through the week. Levelling and grading work will follow in the week July 22. Concrete curb and gutter installation along with paving of the first layer of asphalt are scheduled for the week of July 28
E 90th Street
Levelling and grading work is scheduled for the week July 21. Concrete curb and gutter installation along with paving of the first layer of asphalt are scheduled for the week of July 28.
Elliott Avenue
The contractor will begin removals on this segment around mid-week the week of July 21.
2025-102 PMP Street Maintenance Project
Hyland Area (Hyland Creek Road, Nesbitt Road, Hyland Creek Circle, Norman Ridge Circle)
Asphalt paving is scheduled for Friday, July 18th.
Nine Mile Creek Parkway (W. 90th Street to Stanley Avenue)
The contractor will be in the week of July 21st to begin site restoration including topsoil and sod. Asphalt milling is scheduled for Friday, July 25th.
Vincent Area (Vincent Place, Vincent Circle)
The contractor will be in the week of July 21st to begin removals and utility work.
Terracewood Area (Terracewood Drive, Morris Circle, Morris Lane, Rich Circle, W 114th Street, Rich Road)
The contractor mobilize into the site the week of July 21st. They will be installing inlet protection and begin utility work.
2025-101 PMP Street Improvement Project
Towne Terrace (James Avenue to Humboldt Avenue)
The contractor completed the installation of curb and gutter this week. They plan on paving the first layer of asphalt the week of July 14.
W 105th Street (Thomas Avenue to Sheridan Avenue)
The contractor will be paving the first layer of asphalt the week of July 14.
Fremont Avenue
The contractor is working on removals of the areas necessary to allow the utility crews to begin installation of the new sanitary sewer the week of July 7. The utility subcontractor will move in the week of July 14 to begin excavation of the jacking pits required for the trenchless installation of the new sanitary sewer line. The utility portion of this work is scheduled for 9 to 10 weeks, during this time Freemont Avenue will only be open to local traffic.
10th Avenue and 99th Street
The contractor finished removals of the asphalt surface earlier in the week of July 7. Utility work is ongoing and will continue through the week. Levelling and grading work will follow in the week July 14.
12th Avenue
The contractor finished removals of the asphalt surface the week of July 7. Utility work is ongoing and will continue through the week. Levelling and grading work will follow in the week July 22.
E 90th Street
The contractor finished removals of the asphalt surface earlier the week of July 7. Utility work is completed. Levelling and grading work will follow in the week July 14.
2025-102 PMP Street Maintenance Project
Hyland Area (Hyland Creek Road, Nesbitt Road, Hyland Creek Circle, Norman Ridge Circle)
The contractor be in early the week of July 14th to continue sod installation. Asphalt milling is scheduled for July 16th and asphalt paving is scheduled for Friday, July 18th. Work is weather dependent and subject to change.
Nine Mile Creek Parkway (W. 90th Street to Stanley Avenue)
The contractor will be in the week of July 14th raising maintenance hole and gate valve covers in preparation for asphalt milling & paving.
Vincent Area (Vincent Place, Vincent Circle)
The contractor will be in the week of July 14th to begin removals.