Lift Station No. 26 Valve Structure Project

Bush Lake Lift Station #26 Project

An underground wastewater pumping station located at 9701 W. Bush Lake Rd. at the south end of Bush Lake is to be upgraded with the installation of a new underground valve structure and discharge pipe. This work is required to reduce breakdowns at the station and to improve operability, safety and reliability. No interruption of service is expected for any properties served by the station.

Lift Station #26 Crew

Lift Station #26

Project Dates & Route

The work is currently planned to start in July and be completed by the end of August. Because some street excavation will be required to install the new structure and piping, some traffic diversion will be needed to perform the work. Closure of the westbound turn lane on West Bush Lake Rd at the Lindstrom intersection will direct traffic to the 90 degree intersection of Lindstrom Drive and Bush Lake to make the turn to West Bush Lake Rd.

Lift Station No. 26

Lift Station #26 Project Route

Updates

September 2017

September 8, 2017

Construction of the valve vault, forcemain, and control panel is complete. Street restoration is underway with curb and gutter installation this week and paving next week. Traffic control is expected to be removed and the street re-opened. Final hatch assemblies and restoration at the lift station site will be completed in the coming weeks.

August 2017

August 18, 2017

Construction of new forcemain was completed this week and structures were backfilled. The station is fully operational. Control panel replacement and top slab/access hatch work is anticipated to take place in the next two weeks with restoration to follow.

August 11, 2017

Work continued this week on forcemain construction. Control panel upgrades and top slab/access hatch work will take place in the next two weeks.

July 2017

July 28, 2017

The new valve structure has been set in place. Pipe work will begin next week.

July 14, 2017

Work to install a new valve structure, force main and replace access hatches should begin the last week in July.  Construction will likely last through the end of August.  Traffic control has been delivered to the site and erosion control measures will be installed prior to excavation.