2017-901 Storm Sewer Maintenance Project

The City annually contracts work to maintain the City's storm sewer system. The projects are identified by inspections, life cycle evaluations, citizen inquiries, ongoing erosion problems, flood reduction investigations and/or more permanent construction from emergency repairs of flooding situations, sinkholes or other damage or failures. When feasible and cost effective, the repairs are done using trenchless techniques to avoid open-cut construction and the related traffic impacts.

The 2017-901 Storm Sewer Maintenance Project includes work at the following sites:

  • 84XX W. 107th St. – Reconstruct storm sewer manhole
  • 56XX W. 84th St. – Remove and replace existing storm sewer catch basin and pipe
  • 52XX W. Old Shakopee Rd. - Reline existing storm sewer pipe
  • W. 94th St., west of France Ave. S. – Remove and replace storm sewer manhole, two catch basins, pipe and pond outlet at Community College Pond
  • W. Old Shakopee Rd., west of Morgan Ave. S. – Reline existing storm sewer pipe
  • 14XX W. 94th St. – Remove abandoned storm sewer lift station
  • 96XX 10th Ave. S. – Remove and replace storm sewer manhole, two catch basins, pipe and restore street curb and gutter, pavement and driveways, storm sewer work in E. Old Shakopee Rd. is being completed in June to coordinate with the Centerpoint Beltline Project.
  • 5100 W. 91st St. - Construct floodplain mitigation and bio retention basins to satisfy the conditions of the Nine Mile Creek Watershed District Permit for the Normandale Boulevard Reconstruction Project
  • 11001 Nesbitt Ave. S. – Grading and gravel surfacing around spent lime ponds to improve maintenance access

Updates

Throughout the project, updates will be provided via this website, the project updates listed below, and through E-Subscribe.

December 2017

December 1, 2017

10th Ave. S., between E. 96th St. and E. Old Shakopee Rd.
Boulevard sod and landscaping are complete; tree and shrub replacement will be in the spring of 2018.

Nord Myr Park, 91st St. near Poplar Bridge Rd.
All excavation, grading, native seeding and tree planting are complete. Hydro-seeding was used as much as practical to minimize netting in the natural areas.

Polytech Pond, 1401 W. 94th St. & 9500 W. Bloomington Fwy.
Site is graded and seeded with minor clean-up and fence repairs remaining

All other sites:
Work is complete other than minor clean-up and erosion control repairs.

November 2017

November 8, 2017

W. 94th St., just west of France Ave. S.
Storm sewer complete and the street paved. Turf restoration is expected mid-November.

10th Ave. S., between E. 96th St. and E. Old Shakopee Rd.
Street and driveway paving is complete. Boulevard grading and landscaping are mostly complete; sod is expected mid-November, and tree and shrub replacement will be in the spring of 2018.

Nord Myr Park, 91st St. near Poplar Bridge Rd.
Tree clearing is complete. Excavation and grading is expected to start the week of November 13 and complete by the end of the month.

W. Old Shakopee Rd., near Rich. Rd.
Pipe lining completed.

W. Old Shakopee Rd., near Morgan Ave. S.
Pipe lining completed.

Polytech Pond, 1401 W. 94th St. & 9500 W. Bloomington Fwy.
Electrical disconnects planned for November 10; lift station abandonment and restoration planned for the following week.

November 3, 2017

W. 94th St., just west of France Ave. S.
Paving is expected to be complete on Friday, November 3. Turf restoration is planned for the week of November 6.

10th Ave. S., between E. 96th St. and E. Old Shakopee Rd.
Paving is expected to be complete on Friday, November 3. Turf and boulevard restoration is planned for the week of November 6. Some landscaping and tree replacement is expected next spring.

[accordion]

October 2017

October 27, 2017

W. 83rd St. between Normandale Lake Blvd. and Norman Center Dr.
Paving is complete, turf restoration will be coordinated with other small sites in next couple weeks.

W. 94th St., just west of France Ave. S.
Curb work planned for early week of October 30, with paving later in the week.

10th Ave. S., between E. 96th St. and E. Old Shakopee Rd.
Storm sewer and fire hydrant construction were completed this week. Grading work will start Friday, October 27, so the road can be reopened. Curb is planned for early week of October 30, with paving late in the week. Boulevard restoration planned for the following week.

October 20, 2017

W 83rd St between Normandale Lake Blvd and Norman Center Dr
Pavement restoration is expected to be complete on Friday, October 20.

W 94th St, just west of France Ave S
Pipe work was completed on Thursday, October 19. Curb and paving is expected to be completed the week of October 30.

10th Ave S, between E 96th St and E Old Shakopee Rd
Storm sewer and fire hydrant construction is planned to start on Tuesday, October 24. A street closure is required for several days. Residents will still have access to driveways.

October 13, 2017

107th St & Cavell Ave S
Storm sewer manhole repairs have been completed.

Nord Myr Park, 91st St near Poplar Bridge Rd
Tree clearing and buckthorn removal have been completed; excavation and grading are expected to start in late October.

W Old Shakopee Rd, near Rich Rd, and at Morgan Ave S
Storm sewer pipe lining has been delayed; expect several days’ notice.

Polytech Pond, 1401 W 94th St & 9500 W Bloomington Fwy
Removal of the abandoned storm sewer lift station is on hold for electrical disconnects. Local businesses have been notified.

W 83rd St between Normandale Lake Blvd and Norman Center Dr
The storm sewer pipe and catch basin are expected to be complete on Friday, October 13; the work required a one-day temporary road closure. Any restoration will only require lane closures.

10th Ave S, between E 96th St and E Old Shakopee Rd
Trees have been removed. Storm sewer and hydrant construction are expected to start the week of October 16.

W 94th St, just west of France Ave S
Storm sewer construction is planned for Thursday and Friday, October 19 and 20 (MEA break) to avoid Normandale College traffic.

October 6, 2017

Site A: 107th St. & Cavell Ave. S.
Storm sewer manhole rehabilitation will take place early in the week of October 9.

Site E: Nord Myr Park, 91st St. near Poplar Bridge Rd.
Tree clearing to begin Monday October 9; excavation and grading will start in a couple weeks.

Site D: W. Old Shakopee Rd., near Rich. Rd.
Relining of the storm sewer pipe is scheduled for Tuesday, October 10. There will be a temporary eastbound right lane closure.

Site G: W. Old Shakopee Rd., near Morgan Ave. S.
Relining of the storm sewer pipe is planned for Wednesday, October 11. There will be a temporary westbound left lane closure.

Site H: Polytech Pond, 1401 W. 94th St. & 9500 W. Bloomington Fwy.
Removal of abandoned storm sewer lift station and pipe is planned to start mid-week of October 9.

Site C: W. 83rd St. between Normandale Lake Blvd. and Norman Center Dr.
The storm sewer pipe and catch basin are planned to be replaced on Friday October 13, requiring temporary road closure. Signs will be installed for advance notice of the closure.

Site I: 10th Ave. S., between E. 96th St. and E. Old Shakopee Rd.
Several trees will be removed early the week of October 9. Storm sewer and hydrant construction will begin early the week of October 16.

Site F: W. 94th St., just west of France Ave. S.
Storm sewer construction is planned for Thursday, October 19 and Friday, October 20 (MEA break) to avoid Normandale College traffic.

Site B: Lime Ponds, 11001 W. Nesbitt Ave. S.
Grading of the access road is planned for early in the week of October 23.